Exhibit 99.2

 

 

MANAGEMENT’S DISCUSSION AND ANALYSIS

 

FOR THE QUARTER ENDED SEPTEMBER 30, 2026

 

 

 

 

Table of Contents

 

Company Overview 4
2026 Third Quarter Highlights 7
Management Business Overview and Outlook 9
Selected Quarterly Production Results 10
Mining Operations - Bolivar Mine Operating Results 14
Mining Operations - Porco Mine Operating Results 16
Mining Operations - Caballo Blanco Group Operating Results 18
Mining Operations - Zimapan Mine 20
Ore Processing Operations - San Lucas Group Operating Results 22
Other Properties 23
Qualified Person and Technical Disclosures 24
Overview of Financial Results 24
Summary of Quarterly Financial Results 24
Financial Results for the Quarters ended September 30, 2026 and 2025 25
Financial Results for the nine months ended September 30, 2026 and 2025 27
Liquidity, Capital Resources and Contractual Obligations 29
Liquidity 29
Off-balance Sheet Arrangements 31
Transactions with Related Parties 31
Subsequent Events 31
Material Accounting Estimates and Judgments 32
Accounting Policies Including Changes in Accounting Policies and Initial Adoption 32
Financial Instruments and Other Instruments 32
Risk Factors 34
Outstanding Share Data 36
Internal Controls over Financial Reporting and Disclosure Controls and Procedures 36
Non-GAAP Measures 37
Cash cost of production per tonne milled, cash cost per silver ounce or zinc tonne sold, all-in sustaining cost (“AISC”) per silver ounce or zinc tonne sold - Mining operations 40
Average realized price per silver ounce and zinc tonne sold – Mining operations 50
Realized mining margin for silver ounces and zinc tonnes sold – Mining operations 55
Cash cost of production per tonne milled, cash cost per silver ounce or zinc tonne sold, all-in sustaining cost (“AISC”) per silver ounce or zinc tonne sold – Ore processing 56
Average realized price per silver ounce and zinc tonne sold - Ore processing 58
Realized ore processing margin for silver ounces and zinc tonnes sold 59
Adjusted EBITDA 60
Cautionary Note to United States Investors Concerning Estimates of Mineral Reserves & Resources 61
Cautionary Note Regarding Forward-looking Information 61
Additional Information 62

 

- 2 -

 

 

MANAGEMENT’S DISCUSSION AND ANALYSIS OF RESULTS OF OPERATIONS AND FINANCIAL CONDITION

 

This Management’s Discussion and Analysis of results of operations and financial condition (“MD&A”) should be read in conjunction with the unaudited condensed interim consolidated financial statements for the three and nine months ended September 30, 2026 and the notes thereto of Santacruz Silver Mining Ltd. (“the Company” or “Santacruz”) which have been prepared in accordance with IFRS Accounting Standards (“IFRS®”), as issued by the International Accounting Standards Board (“IASB”).

 

All dollar amounts are expressed in thousands of US dollars unless otherwise indicated. Unless otherwise noted, references to “C$” are to thousands of Canadian dollars, references to “MXN” are to thousands of Mexican pesos and references to “BOB” are to thousands of Bolivian bolivianos.

 

Certain amounts shown in this MD&A may not add exactly to total amounts due to rounding differences. Throughout this MD&A, the terms first quarter, second quarter, third quarter, fourth quarter and year to date are respectively used interchangeably with the terms Q1, Q2, Q3, Q4 and YTD.

 

This MD&A contains “forward-looking information” within the meaning of applicable Canadian securities regulation and should be read in conjunction with the “Risk Factors” and “Cautionary Note Regarding Forward-looking Information” section in this MD&A.

 

All information contained in this MD&A is current and has been approved by the Board of Directors of the Company as of November 12, 2026.

 

- 3 -

 

 

Company Overview

 

Santacruz was incorporated pursuant to the Business Corporations Act of British Columbia on January 24, 2011. The Company’s registered office is located at 1600 – 925 West Georgia Street, Vancouver, British Columbia, Canada V6C 3L2. The Company is listed for trading on the Toronto Stock Exchange (‘‘TSX’’) under the symbol “SCZ” and the Nasdaq Capital Market (“NASDAQ”) under the symbol “SCZM”.

 

The Company is engaged in the operation, acquisition, exploration and development of mineral properties in Latin America, with a primary focus on silver and zinc, but also produces lead and copper. As at September 30, 2026, the Company had acquired ownership including mining concession rights to the following mineral properties:

 

Bolivia:

 

● Sinchi Wayra (“Sinchi Wayra”), which consists of the following mineral properties and businesses located in Bolivia:

 

  ○ the Caballo Blanco Group which includes the Tres Amigos and Colquechaquita mines (the “Caballo Blanco Group” or “Caballo Blanco”) and the Don Diego processing plant (the “Don Diego Processing Plant” or “Don Diego”), which processes production from the Caballo Blanco Group as well as toll milling from the San Lucas feed sourcing business;

 

  ○ the San Lucas Group which includes the San Lucas feed sourcing and trading business and the Reserva mine (the “San Lucas Group” or “San Lucas”); and

 

  ○ the Soracaya exploration project (the “Soracaya Project” or “Soracaya”).

 

● Illapa (“Illapa”), with its operations held under a net operating cash flow interest agreement with Corporación Minera de Bolivia (“COMIBOL”) a Bolivian state-owned entity comprising:

 

  ○ the Bolivar mine (the “Bolivar Mine” or “Bolivar”) and process plant complex; and

 

  ○ the Porco mine (the “Porco Mine” or “Porco”) and process plant complex.

 

Mexico:

 

  ○ The Zimapan mine (the “Zimapan Mine” or “Zimapan”) and processing plant located in Hidalgo, Mexico.

 

Management has assessed the nature of its interest in the Illapa business and determined it to be a joint operation. The Company records its 45% interest in the assets, liabilities, revenues and expenses of the Illapa business in its consolidated financial statements. The Company is solely responsible for certain specific transactions made by the Illapa business, and for these transactions, the assets, liabilities, revenues and expenses are recognized at 100% in the Company’s Financial Statements and result in balances payable to or owed from COMIBOL for its share of the joint operation. The Company reports its segment information on a 100% basis with respect to Bolivar and Porco together with an elimination column representing COMIBOL’s 55% interest (refer to Note 22 of the condensed interim consolidated financial statements).

 

In this MD&A, The Company reports 100% of production and sales from the Bolivar and Porco operations. Under the Association Agreement, Illapa S.A. is the designated operator and holds exclusive, comprehensive responsibility for all technical, financial, labor, legal, and commercial aspects of the operations. The Agreement grants Illapa full control over the mining production chain, including the exclusive right to commercialize concentrates in both domestic and international markets and to manage all related commercial processes.

 

COMIBOL’s entitlement under the Agreement is not a direct share of production, but rather a 55% participation in net cash flow. Accordingly, management believes that reporting production on a 100% gross basis appropriately reflects the operational substance of the arrangement, while COMIBOL’s interest is more accurately represented as an economic participation in net cash flow rather than a direct operational interest in the underlying production.

 

Since the Company is the operator of the Bolivar and Porco mines, management evaluates the performance of each operation by reviewing production on a 100% basis. Since the information of 100% production results is used to make decisions about allocating resources and assessing performance, this MD&A is prepared under the same basis.

 

- 4 -

 

 

Company Overview (continued)

 

In this MD&A, operational information for Bolivar and Porco is presented at 100%. Readers of this MD&A are cautioned that although in the operating section of this MD&A the Company reports 100% of the production and sales information, the Company records 45% of the assets, liabilities, revenues and expenses in its consolidated financial statements. In contrast to the operational information, all financial information presented in this MD&A is reported showing 45% of the assets, liabilities, revenues and expenses which coincides with the information presented in the condensed interim consolidated financial statements.

 

Update to non-GAAP performance measures and silver/zinc equivalent ounces metrics

 

Commencing in Q1 2026 the Company updated its non-GAAP performances measures to provide management and readers with useful information to evaluate the performance of the Company. Refer to the Non-GAAP measures section of this MD&A for a detailed explanation of the metrics and methodology used to determine them. All of the changes made have been applied retrospectively for the comparative periods. The following section provides a summary of the changes made:

 

Segregation of mining operations & ore processing: Operational and cost metrics are now presented as either Mining operations or Ore processing operations because the underlying business processes and profitability drivers each type of operation are fundamentally different. Our mining operations consist of Bolivar, Porco, Caballo Blanco and the Zimapan mines. Mining operations include the production metrics, revenues and costs from extracting ore from our mineral properties which is then processed and sold in concentrate form. Ore processing operations consist of the San Lucas feed sourcing business and includes the production metrics, revenue and costs from purchasing ore from third-party miners which is then processed and sold in concentrate form. Mining operations generate high margins because the input for the final product, metal concentrates, is from ore that is extracted from the Company’s mine properties that it owns. Ore processing generates significantly lower margins because the ore is purchased from third-party miners and the amount paid for the purchased ore is based upon the ore’s metal content and prevailing metal prices at the time of purchase.

 

Co-product costing methodology: The Company will no longer focus on costs per silver equivalent ounces sold and will now provide costs per actual silver ounce and zinc tonne sold in the period using a co-product cost methodology which allocates costs between each metal. The Company’s primary payable metals are silver and zinc, the revenue generated by each metal varies depending on prevailing metal prices but because each metal generates greater than 30% of the total revenues, the Company has concluded that reporting costs as co-products by silver ounce sold and zinc tonne sold is the most appropriate way to assess the performance of its operations. The total tonnes of ore milled in the period generates silver and zinc payable metals for sale, the ratio of payable silver and zinc produced from each tonne milled is used to allocate each period’s production costs between silver ounces sold and zinc tonnes sold, which will generate the following metrics: cash cost per silver ounce and zinc tonne sold, all-in sustaining cost per silver ounce and zinc tonne sold and will also provide an average realized price per silver ounce and zinc tonne sold.

 

By-product credits from secondary metal sales: The Company’s operations are poly-metallic whereby each tonne of ore milled generates primarily payable ounces of silver and tonnes of zinc but also generates payable tonnes of lead and copper. The combined revenues of lead and copper are incidental to our primary metal production of silver and zinc because they generate less than 10% of total revenues. Lead and copper concentrate is produced primarily to obtain the silver contained within so the Company has adopted the practice of calculating the net cost of producing an ounce of silver, after deducting revenues gained from incidental by-product production of lead and copper.

 

- 5 -

 

 

Company Overview (continued)

 

Silver equivalent ounces and zinc equivalent tonnes: The Company has modified its production disclosures to include zinc equivalent tonnes produced and has updated the method of calculating silver equivalent ounces produced. Previously the Company used budgeted metal prices which were updated annually to convert metal sales into silver equivalents, the new methodology uses the period’s average actual metal prices to determine the conversion factor. The Company considers silver equivalent (“AgEq”) ounces and zinc equivalent (“ZnEq”) tonnes to be useful production metrics for evaluating its multi-metal production profile but they should be considered only supplemental to the actual production volumes of silver and zinc produced and sold. The Company will continue to present the silver equivalent ounces produced and zinc equivalent tonnes produced for the combined mining and ore processing operations, but will no longer report the figure for each operation. The Company will no longer report its cash cost and all-in sustaining cost per silver equivalent ounce sold to focus on the more relevant metrics of cash cost and all-in sustaining cost per silver ounce and zinc tonne sold instead.

 

Average realized price per silver ounce and zinc tonne sold: Revenues are presented as the sum of invoiced revenues related to delivered shipments of zinc, lead and copper concentrates, after having deducted treatment, smelting and refining charges made by the customer. The average realized price per silver ounce and zinc tonne sold is an analysis of the gross revenues prior to the charges made by the customer which is then divided by silver ounces and zinc tonnes sold. In prior periods the Company added back only treatment, smelting and refining charges. Commencing Q2 2026, the Company modified its methodology to provide readers with a more comparable figure against the actual market prices of the metal and to be consistent with peers by also adding back metallurgical deductions to determine the average realized price per silver ounce and zinc tonne sold. Prior periods have been restated with the new calculation methodology.

 

Realized mining margin and realized ore processing margin: Management has created two new non-GAAP measures: the realized mining margin and realized ore processing margin. Management believes the margins are an effective way to evaluate the profitability of the Company’s operations. The margin is calculated by subtracting the all-in sustaining cost (“AISC”) per silver ounce or zinc tonne sold from the average realized price per silver ounce or zinc tonne sold.

 

As there are no standardized methods of calculating non-GAAP measures, the Company’s methods may differ from those used by others and, accordingly, the Company’s use of these measures may not be directly comparable to similarly titled measures used by others. Accordingly, these non-GAAP measures are intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. Refer to the Non-GAAP Measures section in this MD&A for a detailed explanation of the metrics, the methodology used and a reconciliation of these measures to our revenues and operating expenses, as reported in our unaudited condensed interim consolidated financial statements which are prepared under IFRS. All of the changes made to the non-GAAP measures have been applied retrospectively to comparative periods.

 

- 6 -

 

 

2026 Third Quarter Highlights

 

Operational Highlights  2026 Q3   2026 Q2  

Change

Q3 vs Q2

   2025 Q3  

Change

‘26 Q3 vs‘25 Q3

  

 

2026 YTD

   2025 YTD  

Change

‘26 YTD vs ‘25 YTD

 

Mining Operations & Ore Processing(1)

                                        
Tonnes milled   509,108    521,956    (2)%   486,584    5%   1,518,841    1,439,220    6%
Silver ounces produced   1,500,958    1,573,100    (5)%   1,241,929    21%   4,415,557    4,255,073    4%
Zinc tonnes produced   22,080    23,240    (5)%   21,581    2%   66,960    63,449    6%
Lead tonnes produced   3,316    3,165    5%   2,603    27%   9,167    8,093    13%
Copper tonnes produced   355    337    5%   331    7%   1,000    839    19%
                                         
Supplemental context metrics                                        
Silver equivalent ounces produced (2)   3,027,229    2,814,489    8%   2,389,032    27%   8,123,183    7,614,976    7%
Zinc equivalent tonnes produced (2)   49,577    59,680    (17)%   50,658    (2)%   168,627    161,472    4%
                                         

Mining Operations(1)

                                        
Tonnes milled   416,187    406,532    2%   386,034    8%   1,215,729    1,157,002    5%
Silver ounces produced   1,186,507    1,161,733    2%   915,056    30%   3,348,334    3,313,545    1%
Zinc tonnes produced   16,018    15,548    3%   14,549    10%   46,062    43,759    5%
Lead tonnes produced   2,680    2,293    17%   2,028    32%   7,057    6,528    8%
Copper tonnes produced   355    337    5%   331    7%   1,000    839    19%
Silver ounces sold (3)   1,317,704    894,167    47%   900,319    46%   3,083,623    3,471,906    (11)%
Zinc tonnes sold (3)   17,191    14,419    19%   12,765    35%   45,636    38,221    19%
Cash cost of production per tonne milled (4)   95.63    86.83    10%   76.42    25%   89.96    71.06    27%
Cash cost per silver ounce sold ($/oz) (4)    12.72    15.54    (18)%   20.37    (38)%   16.39    14.90    10%
Cash cost per zinc tonne sold ($/t) (4)   1,890    1,746    8%   1,700    11%   1,830    1,606    14%
Average realized price per silver ounce sold ($/oz) (4)   64.72    72.17    (10)%   41.14    57%   71.41    35.21    103%
All-in sustaining cost per silver ounce sold ($/oz) (4)    19.73    21.87    (10)%   29.35    (33)%   24.20    20.73    17%
Realized mining margin per silver ounce sold (4)   44.99    50.30    (11)%   11.79    281%   47.21    14.48    226%
Average realized price per zinc tonne sold ($/t) (4)   4,011    3,302    21%   3,336    20%   3,601    3,203    12%
All-in sustaining cost per zinc tonne sold ($/t) (4)   2,410    2,219    9%   2,247    7%   2,391    2,066    16%
Realized mining margin per zinc tonne sold (4)   1,601    1,083    48%   1,089    47%   1,210    1,137    6%
                                         

Ore Processing (1)

                                        
Tonnes milled   92,921    115,424    (19)%   100,550    (8)%   303,112    282,218    7%
Silver ounces produced   314,451    411,367    (24)%   326,873    (4)%   1,067,223    941,528    13%
Zinc tonnes produced   6,062    7,692    (21)%   7,032    (14)%   20,898    19,690    6%
Lead tonnes produced   636    872    (27)%   575    11%   2,110    1,565    35%
Silver ounces sold (3)   449,355    333,899    35%   353,965    27%   1,418,129    1,006,827    41%
Zinc tonnes sold (3)   6,362    8,796    (28)%   6,199    3%   22,555    16,591    36%
Realized ore processing margin per silver ounce sold (4)   21.39    33.42    (36)%   (4.56)   569%   21.14    2.50    746%
Realized ore processing margin per zinc tonne sold (4)   464    819    (43)%   1,306    (64)%   727    1,605    (55)%

 

Notes:

 

(1) Mining operations includes production volumes extracted from the Company’s Bolivar, Porco, Caballo Blanco and Zimapan mines. Ore processing operations is production volumes from third-party purchased ore from the Company’s San Lucas ore sourcing and trading business. Readers are cautioned that Bolivar and Porco production figures are presented at 100% however the Company records only its 45% interest in the assets, liabilities, revenues and expenses of the Illapa business in its consolidated financial statements. The Company reports its segment information on a 100% basis with respect to Bolivar and Porco together with an elimination column representing COMIBOL’s 55% interest (refer to segment information note of the condensed interim consolidated financial statements).

(2) Silver equivalent ounces and zinc equivalent tonnes produced have been calculated using the period’s average metal prices quoted on the London Metal Exchange. The silver and zinc equivalent production is calculated by dividing each metal’s price by the price of Silver or Zinc to arrive at their equivalent. Refer to the section titled “Non-GAAP Measures” for further information.

(3) Silver ounces sold and zinc tonnes sold may be lower or higher than the volumes produced in the period due to two effects: (i) timing - concentrates produced in a quarter may be shipped and invoiced in a subsequent period or have been produced in a prior period; and (ii) commercial terms - payable ounces under offtake agreements are lower than produced ounces due to standard treatment and quality deductions applied by the customer.

(4) The Company reports non-GAAP measures, which include: cash cost of production per tonne milled, cash cost per silver ounce and zinc tonne sold, average realized price per silver ounce and zinc tonne sold, all-in sustaining cost per silver ounce, zinc tonne sold, realized mining margin per silver ounce or zinc tonne sold and realized ore processing margin per silver ounce or zinc tonne sold. The Company has adopted the practice of reporting costs on a co-product basis allocating production costs between Silver and Zinc and also records sales revenue from lead and copper as by-product credits to silver costs. These measures are widely used in the mining industry as a benchmark for performance, but do not have a standardized meaning and may differ from methods used by other companies even though the metrics have the same or similar names. Refer to the section titled “Non-GAAP Measures” in this MD&A.

 

- 7 -

 

 

2026 Third Quarter Highlights (continued)

 

 

 

Financial Highlights

  2026 Q3   2026 Q2  

Change

Q3 vs Q2

   2025 Q3  

Change

‘26 Q3

vs‘25 Q3

  

 

2026 YTD

  

 

 

2025 YTD

  

Change

‘26 YTD vs ‘25 YTD

 
Revenues   153,276    113,458    35%   79,989    92%   394,263    223,598    76%
Gross profit   60,107    51,139    18%   20,166    198%   154,115    73,313    110%
Net income (loss)   37,617    2,005    1776%   16,344    130%   68,092    46,772    46%
Net earnings (loss) per share - basic ($/share) (1)   0.40    0.02    1900%   0.18    122%   0.74    0.52    42%
Adjusted EBITDA (2)    61,086    46,663    31%   19,509    213%   150,317    73,795    104%
Cash & cash equivalents   102,836    50,398    104%   40,018    157%   102,836    40,018    157%
Marketable securities(3)   21,798    22,421    (3)%   19,212    13%   21,798    19,212    13%
Working capital   113,254    86,122    32%   69,208    64%   113,254    69,208    64%

 

Notes:

 

(1) On December 10, 2025 the Company consolidated its issued and outstanding common shares on the basis of one post-consolidated common share for every four pre-consolidated common shares. The number of issued and outstanding shares and any per share amounts have been retrospectively restated.

 

(2) The Company reports non-GAAP measures, which includes adjusted EBITDA, these measures are widely used in the mining industry as a benchmark for performance, but do not have a standardized meaning and may differ from methods used by other companies even though the metrics have the same or similar names. Refer to the section titled “Non-GAAP Measures” in the MD&A.

 

(3) Marketable securities consist of US treasury notes and US treasury bills which are held as part of the Company’s cash position and liquidity management strategy.

 

The net income for the three months ended September 30, 2026 (2026 Q3) was impacted by a higher income tax expense that was a non-recurring event due to the devaluation of the Bolivian Boliviano which resulted in large taxable foreign exchange gains. Refer to the section titled “Overview of Financial Results” on page 25 and 26 of this MD&A for further details.

 

Year to Date Production Summary - By Segment

 

   Mining Operations(1)   Ore Processing(1)   Combined 
   Bolivar(2)   Porco(2)   Caballo Blanco Group   Zimapan  

2026 Q3

Total

   San Lucas Group  

2026 Q3

Total

 
Material Processed (tonnes milled)   213,849    146,089    187,438    668,353    1,215,729    303,112    1,518,841 
Silver Ounces Produced   1,011,244    260,717    920,322    1,156,051    3,348,334    1,067,223    4,415,557 
Zinc Tonnes Produced   11,022    8,770    12,635    13,635    46,062    20,898    66,960 
Lead Tonnes Produced   637    351    2,331    3,738    7,057    2,110    9,167 
Copper Tonnes Produced    N/A      N/A      N/A     1,000    1,000     N/A     1,000 
                                    
Average head grades per mine:                                   
Silver (g/t)   165    67    167    76    105    134    110 
Zinc (%)   5.59    6.28    7.19    2.71    4.34    7.73    5.01 
Lead (%)   0.40    0.32    1.49    0.72    0.73    1.04    0.79 
Copper (%)    N/A      N/A      N/A     0.27    0.27    N/A     0.27 
                                    
Metal recovery per mine:                                   
Silver (%)   89    83    92    71    79    82    79 
Zinc (%)   92    96    94    75    83    89    85 
Lead (%)   74    75    83    78    77    67    75 
Copper (%)    N/A      N/A      N/A     56    56     N/A     56 

 

Notes:

 

(1) Mining operations includes production volumes extracted from the Company’s Bolivar, Porco, Caballo Blanco, and Zimapan mines. Ore processing operations is production volumes from third-party purchased ore from the Company’s San Lucas ore sourcing and trading business.

(2) Readers are cautioned that Bolivar and Porco production figures are presented at 100% however the Company records only its 45% interest in the assets, liabilities, revenues and expenses of the Illapa business in its consolidated financial statements. The Company reports its segment information on a 100% basis with respect to Bolivar and Porco together with an elimination column representing COMIBOL’s 55% interest (refer to segment information note of the condensed interim consolidated financial statements).

 

- 8 -

 

 

Management Business Overview and Outlook

 

2026 Bolivian Operating Priorities:

 

The Company’s Bolivian operations remain focused on operational stability, cost discipline and plant performance in 2026. At Bolivar, the recovery of the areas affected by the localized flooding event encountered in 2025 is progressing on schedule, with production in Q3 2026 approaching pre-flooding levels and full recovery expected in Q4 2026. At Porco, the Company’s smallest and predominantly zinc-oriented mining operation, the priority remains to maintain operating stability and support revenue generation through continued focus on zinc production. At Caballo Blanco, management’s objective is to sustain throughput, recoveries and margins while maintaining cost discipline.

 

On September 18, 2026 the Company announced the acquisition of a 500 tonne-per-day milling facility in Bolivia with an initial payment of $4,645 that was recorded to property plant and equipment. The newly acquired facility will be dedicated to processing ore from the San Lucas business. The Company made an additional payment of $2,787 on October 21, 2026 with a final payment of $1,858 due in November 2026. The facility will be commissioned in the fourth quarter of 2026.

 

San Lucas continues to play a strategic role in keeping plants utilized through third-party ore supply, supporting fixed-cost absorption, cost efficiency and meaningful margin contribution; priority in the allocation of mill capacity is given to higher-margin ore from the Company’s own mines so the recently acquired 500-tonne-per-day milling facility, dedicated to San Lucas ore, will facilitate higher production volumes from San Lucas. Across the Bolivian platform, the Company’s strategy remains centered on optimizing mining costs, improving plant recoveries and maintaining the flexibility of its integrated operating base.

 

2026 Mexican Operating Priorities:

 

In Mexico, the Company’s principal operating focus in 2026 remains on improving metallurgical recoveries and concentrate quality at Zimapan. As the Company’s highest-volume operation, Zimapan has a significant impact on consolidated revenue and operating performance metrics, making recoveries and concentrate quality key priorities. Capital has already been invested toward these objectives and began to deliver results in Q3 2026, with silver recovery improving to 76% from 72% in Q2 2026, and management expects those initiatives to continue supporting operating improvement through 2026. The Company will also maintain its focus on cost discipline, process optimization and the continued strengthening of operating integration across the broader portfolio in support of more consistent production and financial performance.

 

- 9 -

 

 

Selected Quarterly Production Results

 

   2026 Q3  

 

 

2026 Q2

  

 

 

2026 Q1

  

 

 

2025 Q4

   2025 Q3   2025 Q2  

 

 

2025 Q1

  

Change

Q3 ‘26 vs Q2 ‘26

  

Change

Q3‘26 vs

Q3 ‘25

 
Tonnes milled                                             
Bolivar (1)   76,724    72,081    65,044    63,267    52,023    54,803    62,356    6%   47%
Porco (1)   48,597    52,195    45,297    51,416    49,161    49,152    47,501    (7)%   (1)%
Caballo Blanco Group   68,442    59,997    58,999    63,067    62,221    57,773    51,648    14%   10%
Zimapan   222,424    222,259    223,670    222,703    222,629    224,162    223,573    0%   (0)%
San Lucas Group   92,921    115,424    94,767    105,587    100,550    94,973    86,695    (19)%   (8)%
Total   509,108    521,956    487,777    506,040    486,584    480,863    471,773    (2)%   5%
                                              
Silver ounces produced                                             
Bolivar (1)   408,087    343,522    259,635    202,193    132,146    304,468    421,040    19%   209%
Porco (1)   89,134    100,875    70,708    82,047    92,001    105,901    120,537    (12)%   (3)%
Caballo Blanco Group   287,219    326,215    306,888    289,446    294,524    294,786    313,266    (12)%   (2)%
Zimapan   402,067    391,121    362,863    403,321    396,385    398,292    440,199    3%   1%
San Lucas Group   314,451    411,367    341,405    366,600    326,873    319,634    295,021    (24)%   (4)%
Total   1,500,958    1,573,100    1,341,499    1,343,607    1,241,929    1,423,081    1,590,063    (5)%   21%
                                              
Zinc tonnes produced                                             
Bolivar (1)   3,682    3,684    3,656    3,973    3,186    3,225    3,983    (0)%   16%
Porco (1)   2,963    2,974    2,833    2,727    2,488    2,786    2,674    (0)%   19%
Caballo Blanco Group   4,542    4,126    3,967    4,409    4,131    3,974    3,549    10%   10%
Zimapan   4,831    4,764    4,040    5,008    4,744    4,521    4,498    1%   2%
San Lucas Group   6,062    7,692    7,144    7,729    7,032    6,643    6,015    (21)%   (14)%
Total   22,080    23,240    21,640    23,846    21,581    21,149    20,719    (5)%   2%
                                              
Lead tonnes produced                                             
Bolivar (1)   206    233    198    187    104    182    201    (12)%   98%
Porco (1)   101    136    114    108    103    132    161    (26)%   (2)%
Caballo Blanco Group   799    765    767    769    722    595    486    4%   11%
Zimapan   1,574    1,159    1,005    1,237    1,099    1,354    1,389    36%   43%
San Lucas Group   636    872    602    699    575    509    481    (27)%   11%
Total   3,316    3,165    2,686    3,000    2,603    2,772    2,718    5%   27%
                                              
Copper tonnes produced                                             
Zimapan   355    337    308    287    331    229    279    5%   7%
Total   355    337    308    287    331    229    279    5%   7%

 

Notes:

 

(1) Readers are cautioned that Bolivar and Porco production figures are presented at 100% however the Company records only its 45% interest in the assets, liabilities, revenues and expenses of the Illapa business in its consolidated financial statements. The Company reports its segment information on a 100% basis with respect to Bolivar and Porco together with an elimination column representing COMIBOL’s 55% interest (refer to segment information note of the condensed interim consolidated financial statements).

 

- 10 -

 

 

Selected Quarterly Production Results (continued)

 

Mining Operations Results (1)  2026 Q3  

 

 

2026 Q2

  

 

 

2026 Q1

  

 

 

2025 Q4

   2025 Q3   2025 Q2  

 

 

2025 Q1

  

Change

Q3 ‘26 vs Q2 ‘26

  

Change

‘26 Q3

vs ‘25 Q3

 

Cash cost of production per tonne milled (2)

                                             
Bolivar (1)   125.20    109.33    131.88    121.15    139.92    94.96    81.20    15%   (11)%
Porco (1)   102.31    93.40    113.05    91.00    90.27    66.26    69.14    10%   13%
Caballo Blanco Group   113.77    94.61    90.87    78.84    69.45    54.70    56.27    20%   64%
Zimapan   78.39    75.90    67.98    71.44    60.47    68.53    64.75    3%   30%
Total   95.63    86.83    87.19    82.97    76.42    69.92    66.82    10%   25%
                                              

Cash cost per silver ounce sold (2)

                                             
Bolivar (1)   16.67    16.42    28.00    28.50    38.81    12.19    10.50    2%   (57)%
Porco (1)   35.44    35.25    42.66    48.81    36.08    24.64    21.32    1%   (2)%
Caballo Blanco Group   10.72    12.58    14.01    18.12    13.78    8.02    9.88    (15)%   (22)%
Zimapan   3.39    12.37    12.03    23.94    13.73    15.85    14.17    (73)%   (75)%
Total   12.72    15.54    18.34    25.30    20.37    13.17    12.80    (18)%   (38)%
                                              

Cash cost per zinc tonne sold (2)

                                             
Bolivar (1)   2,095    1,657    2,089    1,540    1,659    1,216    1,220    26%   26%
Porco (1)   1,272    1,304    1,107    1,644    1,402    1,040    1,107    (2)%   (9)%
Caballo Blanco Group   1,234    1,356    1,454    1,526    1,295    820    1,097    (9)%   (5)%
Zimapan   2,675    2,403    2,508    2,827    2,190    2,394    2,494    11%   22%
Total   1,890    1,746    1,843    2,008    1,700    1,517    1,598    8%   11%

 

Notes:

 

(1) Mining operations includes production volumes extracted from the Company’s Bolivar, Porco, Caballo Blanco, and Zimapan mines. Ore processing operations is production volumes from third-party purchased ore from the Company’s San Lucas ore sourcing and trading business. Readers are cautioned that Bolivar and Porco production figures are presented at 100% however the Company records only its 45% interest in the assets, liabilities, revenues and expenses of the Illapa business in its consolidated financial statements. The Company reports its segment information on a 100% basis with respect to Bolivar and Porco together with an elimination column representing COMIBOL’s 55% interest (refer to segment information note of the condensed interim consolidated financial statements).

 

(2) The Company reports non-GAAP measures, which include: cash cost of production per tonne milled, cash cost per silver ounce and zinc tonne sold, average realized price per silver ounce and zinc tonne sold, all-in sustaining cost per silver ounce, zinc tonne sold, realized mining margin per silver ounce or zinc tonne sold and realized ore processing margin per silver ounce or zinc tonne sold. The Company has adopted the practice of reporting costs on a co-product basis allocating production costs between Silver and Zinc and also records sales revenue from lead and copper as by-product credits to silver costs. These measures are widely used in the mining industry as a benchmark for performance, but do not have a standardized meaning and may differ from methods used by other companies even though the metrics have the same or similar names. Refer to the section titled “Non-GAAP Measures” in this MD&A.

 

- 11 -

 

 

Selected Quarterly Production Results (continued)

 

Mining Operations Results (1)  2026 Q3  

 

 

2026 Q2

  

 

 

2026 Q1

  

 

 

2025 Q4

   2025 Q3   2025 Q2  

 

 

2025 Q1

  

Change

Q3 ‘26 vs Q2 ‘26

  

Change

‘26 Q3

vs ‘25 Q3

 

Average realized price per silver ounce sold (2)

                                             
Bolivar (1)   65.39    76.45    87.76    57.41    40.78    33.88    31.52    (14)%   60%
Porco (1)   58.21    76.79    84.13    54.97    42.43    35.65    40.66    (24)%   37%
Caballo Blanco Group   59.45    77.49    80.54    60.01    41.60    33.94    31.60    (23)%   43%
Zimapan   70.24    66.32    76.60    56.67    40.55    31.00    33.25    6%   73%
Total   64.72    72.17    80.61    57.54    41.14    33.13    33.12    (10)%   57%
                                              

All-in sustaining cost per silver ounce sold (2)

                                             
Bolivar (1)   21.86    25.81    38.79    44.77    57.68    14.57    13.32    (15)%   (62)%
Porco (1)   43.91    43.11    54.12    62.06    44.37    28.22    25.87    2%   (1)%
Caballo Blanco Group   19.08    18.13    20.44    27.94    17.69    11.12    12.01    5%   8%
Zimapan   8.12    15.01    21.88    31.01    20.15    20.55    22.56    (46)%   (60)%
Total   19.73    21.87    28.90    36.37    29.35    17.50    17.91    (10)%   (33)%
                                              

Realized mining margin per silver ounce sold (2)

                                             
Bolivar (1)   43.53    50.64    48.97    12.64    (16.90)   19.32    18.20    (14)%   358%
Porco (1)   14.30    33.69    30.01    (7.08)   (1.94)   7.44    14.79    (58)%   837%
Caballo Blanco Group   40.37    59.36    60.09    32.08    23.91    22.82    19.59    (32)%   69%
Zimapan   62.12    51.32    54.72    25.65    20.40    10.45    10.69    21%   204%
Total   44.99    50.30    51.71    21.17    11.79    15.63    15.22    (11)%   281%
                                              

Average realized price per zinc tonne sold (2)

                                             
Bolivar (1)   4,079    3,530    3,344    3,934    3,506    3,183    3,435    16%   16%
Porco (1)   4,109    3,457    3,042    3,899    3,495    3,236    3,419    19%   18%
Caballo Blanco Group   4,092    3,442    3,186    3,881    3,532    3,172    3,558    19%   16%
Zimapan   3,799    2,969    3,466    3,615    3,012    2,487    3,007    28%   26%
Total   4,011    3,302    3,276    3,801    3,336    2,938    3,319    21%   20%
                                              

All-in sustaining cost per zinc tonne sold (2)

                                             
Bolivar (1)   2,670    2,521    2,861    2,352    2,447    1,436    1,518    6%   9%
Porco (1)   1,528    1,570    1,395    2,047    1,710    1,175    1,309    (3)%   (11)%
Caballo Blanco Group   1,764    1,800    1,946    2,172    1,579    1,048    1,281    (2)%   12%
Zimapan   3,064    2,623    3,380    3,387    2,725    2,810    3,330    17%   12%
Total   2,410    2,219    2,545    2,655    2,247    1,875    2,069    9%   7%
                                              

Realized mining margin per zinc tonne sold (2)

                                             
Bolivar (1)   1,409    1,009    483    1,582    1,059    1,746    1,917    40%   33%
Porco (1)   2,581    1,887    1,647    1,852    1,785    2,060    2,110    37%   45%
Caballo Blanco Group   2,328    1,643    1,240    1,709    1,953    2,124    2,277    42%   19%
Zimapan   735    346    87    228    287    (324)   (323)   112%   156%
Total   1,601    1,083    731    1,146    1,089    1,063    1,250    48%   47%

 

Notes:

 

(1) Mining operations includes production volumes extracted from the Company’s Bolivar, Porco, Caballo Blanco, and Zimapan mines. Ore processing operations is production volumes from third-party purchased ore from the Company’s San Lucas ore sourcing and trading business. Readers are cautioned that Bolivar and Porco production figures are presented at 100% however the Company records only its 45% interest in the assets, liabilities, revenues and expenses of the Illapa business in its consolidated financial statements. The Company reports its segment information on a 100% basis with respect to Bolivar and Porco together with an elimination column representing COMIBOL’s 55% interest (refer to segment information note of the condensed interim consolidated financial statements).

 

(2) The Company reports non-GAAP measures, which include: cash cost of production per tonne milled, cash cost per silver ounce and zinc tonne sold, average realized price per silver ounce and zinc tonne sold, all-in sustaining cost per silver ounce, zinc tonne sold, realized mining margin per silver ounce or zinc tonne sold and realized ore processing margin per silver ounce or zinc tonne sold. The Company has adopted the practice of reporting costs on a co-product basis allocating production costs between Silver and Zinc and also records sales revenue from lead and copper as by-product credits to silver costs. These measures are widely used in the mining industry as a benchmark for performance, but do not have a standardized meaning and may differ from methods used by other companies even though the metrics have the same or similar names. Refer to the section titled “Non-GAAP Measures” in this MD&A.

 

- 12 -

 

 

Selected Quarterly Production Results (continued)

 

Santacruz’s Consolidated Operations Results

 

Q3 2026 vs Q2 2026

 

Consolidated silver production decreased by 5% to 1,500,958 ounces in Q3 2026 compared to Q2 2026 and consolidated zinc production decreased 5% to 22,080 tonnes in Q3 2026 compared to Q2 2026. The decrease was caused by lower head grades of purchased ore from San Lucas that doesn’t affect profitability and re-allocating mill capacity from the San Lucas ore sourcing and trading business to processing ore from the Company’s mine operations which has a significantly higher margin. Silver production from the Company’s mining operations increased 2% to 1,186,507 ounces and zinc production increased 3% to 16,018 tonnes which was driven by the 2% increase in tonnes milled in the quarter. Bolivar’s silver production rose 19% as recovery work advanced into flood-affected areas with higher silver grades, more than offsetting lower silver production at Caballo Blanco, where grades declined as part of the normal mine sequence, and at Porco, where throughput was affected by a 2.5-day plant stoppage. Consolidated lead production increased 5% to 3,316 tonnes, as a result of higher lead grades and recoveries at Zimapan along with a 5% increase in copper production to 355 tonnes.

 

Sales volumes exceeded production during the quarter as concentrate accumulated during the Q2 2026 road blockades in Bolivia was successfully exported. Silver ounces sold from mining operations increased 47% to 1,317,704 ounces while zinc tonnes sold rose 19% to 17,191 tonnes. At San Lucas, silver ounces sold increased 35% while zinc tonnes sold decreased 28%. Inventories decline to $56,976 at September 30, 2026 from $71,876 at June 30, 2026. Accordingly, a portion of the higher Q3 2026 sales volume reflects the release of previously accumulated inventory and the timing of shipments, rather than an equivalent increase in current-quarter production.

 

The average realized price per silver ounce sold from mining operations decreased 10% to $64.72, reflecting lower silver prices. This was partially offset by a 10% reduction in all-in sustaining cost (AISC) to $19.73 per silver ounce sold, driven by higher sales volumes and increased by-product credits from lead and copper. As a result, the realized mining margin was $44.99 per silver ounce sold, compared with $50.30 in Q2 2026.

 

For zinc, the average realized price increased 21% to $4,011 per tonne sold, while all-in sustaining cost (AISC) increased 9% to $2,410 per tonne. The higher realized price more than offset the increase in costs, resulting in a 48% increase in the realized mining margin to $1,601 per tonne sold. Cash cost of production per tonne milled increased 10% to $95.63.

 

Consolidated revenue increased 35% to $153,276, while gross profit rose 18% to $60,107.

 

Q3 2026 vs Q3 2025

 

When compared with Q3 2025, consolidated silver production increased 21% and consolidated zinc production increased 2%, from a 5% increase in tonnes milled. Silver production from mining operations increased 30% year over year, driven by Bolivar, where production more than tripled from 132,146 to 408,087 ounces compared to Q3 2025. The comparability of the current quarter with the third quarter of 2025 is affected by the substantial impact of the May 2025 flooding event which decreased Bolivar’s 2025 production significantly. For further details, please refer to the Company’s news release dated July 29, 2025. Zinc production from mining operations increased 10%, reflecting higher output across all four mines, partially offset by a 14% decrease in zinc production at San Lucas. Consolidated lead and copper production increased 27% and 7%, respectively.

 

Silver ounces sold from mining operations increased 46% while zinc tonnes sold rose 35%, reflecting the continued recovery in production at Bolivar and the export of concentrate accumulated during Q2 2026 road blockades in Bolivia.

 

The average realized price per silver ounce sold increased 57% to $64.72 while all-in sustaining cost (AISC) per silver ounce sold decreased 33% to $19.73, compared with $29.35 in the prior-year period. Consequently, the realized mining margin per silver ounce sold increased significantly to $44.99, compared with $11.79. The realized mining margin per zinc tonne sold also improved substantially, increasing 47% to $1,601. These improvements contributed to a 92% increase in consolidated revenue to $153,276 and a 198% increase in gross profit to $60,107.

 

- 13 -

 

 

Mining Operations - Bolivar Mine Operating Results

 

Bolivar Production Table (1)  2026 Q3   2026 Q2  

Change

Q3 vs Q2

   2025 Q3   Change Q3 vs Q3   2026 YTD   2025 YTD  

Change

‘26 YTD

vs ‘25 YTD

 
Material Processed (tonnes milled)   76,724    72,081    6%   52,023    47%   213,849    169,182    26%
                                         
Production                                        
Silver (ounces)   408,087    343,522    19%   132,146    209%   1,011,244    857,654    18%
Zinc (tonnes)   3,682    3,684    (0)%   3,186    16%   11,022    10,394    6%
Lead (tonnes)   206    233    (12)%   104    98%   637    487    31%
                                         
Average Grade                                        
Silver (g/t)   186    165    13%   89    110%   165    176    (6)%
Zinc (%)   5.21    5.55    (6)%   6.61    (21)%   5.59    6.72    (17)%
Lead (%)   0.36    0.42    (14)%   0.31    15%   0.40    0.41    (2)%
                                         
Metal Recovery                                        
Silver (%)   89    90    (1)%   89    (0)%   89    89    (0)%
Zinc (%)   92    92    0%   93    (1)%   92    91    1%
Lead (%)   74    77    (4)%   64    16%   74    70    6%
                                         
Metals Sold                                        
Silver ounces sold (2)   465,445    218,307    113%   144,016    223%   873,156    1,024,052    (15)%
Zinc tonnes sold (2)   5,134    2,469    108%   2,400    114%   11,258    8,865    27%
                                         
Average realized price per silver ounce sold (3)   65.39    76.45    (14)%   40.78    60%   74.69    33.76    121%
All-in sustaining cost per silver ounce sold (3)   21.86    25.81    (15)%   57.68    (62)%   26.57    20.05    32%
Realized mining margin per silver ounce sold (3)   43.53    50.64    (14)%   (16.90)   358%   48.12    13.71    251%
                                         
Average realized price per zinc tonne sold (3)   4,079    3,530    16%   3,506    16%   3,648    3,374    8%
All-in sustaining cost per zinc tonne sold (3)   2,670    2,521    6%   2,447    9%   2,699    1,744    55%
Realized mining margin per zinc tonne sold (3)   1,409    1,009    40%   1,059    33%   949    1,630    (42)%

 

Notes:

 

(1) Readers are cautioned that Bolivar and Porco production figures are presented at 100% however the Company records only its 45% interest in the assets, liabilities, revenues and expenses of the Illapa business in its consolidated financial statements. The Company reports its segment information on a 100% basis with respect to Bolivar and Porco together with an elimination column representing COMIBOL’s 55% interest (refer to segment information note of the condensed interim consolidated financial statements).

(2) Silver ounces sold and zinc tonnes sold may be lower or higher than the volumes produced in the period due to two effects: (i) timing - concentrates produced in a quarter may be shipped and invoiced in a subsequent period or have been produced in a prior period; and (ii) commercial terms - payable ounces under offtake agreements are lower than produced ounces due to standard treatment and quality deductions applied by the customer.

(3) The Company reports non-GAAP measures, which include: cash cost of production per tonne milled, cash cost per silver ounce and zinc tonne sold, average realized price per silver ounce and zinc tonne sold, all-in sustaining cost per silver ounce, zinc tonne sold, realized mining margin per silver ounce or zinc tonne sold and realized ore processing margin per silver ounce or zinc tonne sold. The Company has adopted the practice of reporting costs on a co-product basis allocating production costs between Silver and Zinc and also records sales revenue from lead and copper as by-product credits to silver costs. These measures are widely used in the mining industry as a benchmark for performance, but do not have a standardized meaning and may differ from methods used by other companies even though the metrics have the same or similar names. Refer to the section titled “Non-GAAP Measures” in this MD&A.

 

Summary

 

The Bolivar Mine has been active for more than 200 years. The current mine complex consists of an underground mine, 1,100 t/d milling facility, tailings storage facility, maintenance workshop, shaft-winder, water treatment plants, supplies warehouse, main office, hospital, and camp.

 

The Bolivar mine operates in two main areas: the Central Zone, an extension of the original ore deposit that runs deeper, and the Rosario Zone, a parallel area with separate access.

 

- 14 -

 

 

Mining Operations - Bolivar Mine Operating Results (continued)

 

Currently the plant processes about 21,000 tonnes of ore per month, and 840 meters of combined primary and secondary development each month. At the same time, ore from the San Lucas feed sourcing business is providing production flexibility and allowing the mill to operate efficiently.

 

The Bolivar mill has operated continuously since 1993, receiving feed from two main sources: the Bolivar Mine, which supplies approximately 70%, and toll feed sourced through the San Lucas feed sourcing business, contributing the remaining 30%. The mill processes each feed type separately, enabling precise analysis and reporting for each. Different reagent strategies are applied to each source due to the presence of pyrrhotite in the San Lucas feed, which is generally absent in the Bolivar mine feed.

 

Q3 2026 vs Q2 2026

 

When compared with Q2 2026, silver production at Bolivar increased 19% from 343,522 ounces to 408,087 ounces. This improvement is from a 13% increase in silver head grades to 186 g/t from 165 g/t, together with a 6% increase in tonnes milled, as recovery operations progressed into higher-grade areas affected by the May 2025 flooding event. Silver recovery remained similar at 89%, compared to 90% in the prior quarter. Zinc production remained stable at 3,682 tonnes, as higher throughput offset a 6% decline in zinc head grades from 5.55% to 5.21%, while zinc recovery remained steady at 92%. Lead production decreased 12% to 206 tonnes, reflecting lower lead grades and recovery. The recovery plan for areas affected by the flooding event remains on schedule, with full recovery expected in Q4 2026.

 

Silver ounces sold increased 113% to 465,445 ounces and zinc tonnes sold increased 108% to 5,134 tonnes, exceeding production as concentrate accumulated during the Q2 2026 blockades was shipped. The average realized price per silver ounce sold decreased 14% to $65.39, broadly matched by a 15% decrease in all-in sustaining cost per silver ounce sold to $21.86 on the higher volumes sold; the realized mining margin per silver ounce sold was $43.53 (Q2 2026 — $50.64). The realized mining margin per zinc tonne sold increased 40% to $1,409, driven by a 16% higher realized zinc price, which more than offset a 6% increase in all-in sustaining cost per zinc tonne sold to $2,670.

 

Q3 2026 vs Q3 2025

 

When compared with Q3 2025, silver production at Bolivar increased 209% from 132,146 ounces to 408,087 ounces, driven by a 47% increase in tonnes milled and a 110% improvement in silver head grades to 186 g/t from 89 g/t. Production in Q3 2025 was significantly affected by the May 2025 flooding event, and the year-over-year increase reflects continued progress in the recovery of the Pomabamba and Nane veins, which contain high-grade silver mineralization. Zinc production increased 16% from 3,186 tonnes to 3,682 tonnes, as higher throughput more than offset a 21% decline in zinc head grades from 6.61% to 5.21%. Lead production rose 98% from 104 tonnes to 206 tonnes, reflecting higher throughput, improved lead grades and an increase in lead recovery from 64% to 74%.

 

Silver ounces sold more than tripled from 144,016 ounces and zinc tonnes sold more than doubled from 2,400 tonnes. The average realized price per silver ounce sold increased 60% to $65.39, while all-in sustaining cost per silver ounce sold decreased 62% to $21.86 from $57.68, when unit costs reflected the low post-flooding volumes; the realized mining margin per silver ounce sold improved to $43.53 from negative $(16.90). The realized mining margin per zinc tonne sold increased 33% to $1,409.

 

- 15 -

 

 

Mining Operations - Porco Mine Operating Results

 

Porco Production Table (1)  2026 Q3   2026 Q2  

Change

Q3 vs Q2

   2025 Q3  

Change

Q3 vs Q3

  

 

2026 YTD

   2025 YTD  

Change

‘26 YTD

vs‘25 YTD

 
Material Processed (tonnes milled)   48,597    52,195    (7)%   49,161    (1)%   146,089    145,814    0%
                                         
Production                                        
Silver (ounces)   89,134    100,875    (12)%   92,001    (3)%   260,717    318,439    (18)%
Zinc (tonnes)   2,963    2,974    (0)%   2,488    19%   8,770    7,948    10%
Lead (tonnes)   101    136    (26)%   103    (2)%   351    396    (11)%
                                         
Average Grade                                        
Silver (g/t)   68    72    (6)%   71    (4)%   67    82    (19)%
Zinc (%)   6.33    5.95    6%   5.43    17%   6.28    5.82    8%
Lead (%)   0.29    0.33    (13)%   0.30    (3)%   0.32    0.39    (18)%
                                         
Metal Recovery                                        
Silver (%)   84    84    1%   82    2%   83    83    1%
Zinc (%)   96    96    1%   93    3%   96    94    2%
Lead (%)   71    79    (10)%   69    2%   75    69    8%
                                         
Metals Sold                                        
Silver ounces sold (2)   113,600    83,629    36%   105,310    8%   263,503    353,098    (25)%
Zinc tonnes sold (2)   2,834    2,894    (2)%   2,318    22%   8,586    6,466    33%
                                         
Average realized price per silver ounce sold (3)   58.21    76.79    (24)%   42.43    37%   71.90    39.71    81%
All-in sustaining cost per silver ounce sold(3)   43.91    43.11    2%   44.37    (1)%   47.36    32.08    48%
Realized mining margin per silver ounce sold(3)   14.30    33.69    (58)%   (1.94)   837%   24.54    7.63    222%
                                         
Average realized price per zinc tonne sold(3)   4,109    3,457    19%   3,495    18%   3,552    3,387    5%
All-in sustaining cost per zinc tonne sold(3)   1,528    1,570    (3)%   1,710    (11)%   1,498    1,410    6%
Realized mining margin per zinc tonne sold(3)   2,581    1,887    37%   1,785    45%   2,054    1,977    4%

 

Notes:

 

(1) Readers are cautioned that Bolivar and Porco production figures are presented at 100% however the Company records only its 45% interest in the assets, liabilities, revenues and expenses of the Illapa business in its consolidated financial statements. The Company reports its segment information on a 100% basis with respect to Bolivar and Porco together with an elimination column representing COMIBOL’s 55% interest (refer to segment information note of the condensed interim consolidated financial statements).

(2) Silver ounces sold and zinc tonnes sold may be lower or higher than the volumes produced in the period due to two effects: (i) timing - concentrates produced in a quarter may be shipped and invoiced in a subsequent period or have been produced in a prior period; and (ii) commercial terms - payable ounces under offtake agreements are lower than produced ounces due to standard treatment and quality deductions applied by the customer.

(3) The Company reports non-GAAP measures, which include: cash cost of production per tonne milled, cash cost per silver ounce and zinc tonne sold, average realized price per silver ounce and zinc tonne sold, all-in sustaining cost per silver ounce, zinc tonne sold, realized mining margin per silver ounce or zinc tonne sold and realized ore processing margin per silver ounce or zinc tonne sold. The Company has adopted the practice of reporting costs on a co-product basis allocating production costs between Silver and Zinc and also records sales revenue from lead and copper as by-product credits to silver costs. These measures are widely used in the mining industry as a benchmark for performance, but do not have a standardized meaning and may differ from methods used by other companies even though the metrics have the same or similar names. Refer to the section titled “Non-GAAP Measures” in this MD&A.

 

Summary

 

The Porco Mine has been in operation for nearly 500 years. The complex consists of an underground mine, milling facility, maintenance workshop, tailing storage facility, water treatment plant, supplies warehouse, main office, two hospitals and Yancaviri Camp.

 

The milling facility processes approximately 17,000 tonnes of ore, and on average realizes 600 meters of total development per month. The mine is comprised of two production areas. Hundimiento uses long hole mechanized mining methods to exploit the deeper extension of the primary vein complex, and the Central zone which is conventionally mined using more selective shrinkage stoping.

 

- 16 -

 

 

Mining Operations - Porco Mine Operating Results (continued)

 

The milling facility is sourced by the mine feed (approximately 60)%, and the toll feed from the San Lucas feed sourcing business (40)%.

 

Q3 2026 vs Q2 2026

 

Porco is a predominantly zinc-focused underground operation, and its performance is best assessed based on zinc production. Compared with Q2 2026, zinc production remained broadly stable at 2,963 tonnes, as a 6% increase in zinc head grades was offset by a 7% decline in tonnes milled, while zinc recovery remained steady at 96%. Throughput was affected by a 2.5-day unscheduled plant stoppage while the power utility carried out repairs to the nearby power grid. Operations have since returned to normal. Silver production decreased 12% from 100,875 ounces to 89,134 ounces, reflecting lower throughput and a 6% decline in silver head grades from 72 g/t to 68 g/t, while silver recovery remained unchanged at 84%. Lead production decreased 26% to 101 tonnes, driven by lower lead grades and recovery.

 

Zinc tonnes sold of 2,834 were in line with production. The average realized price per zinc tonne sold increased 19% to $4,109 and all-in sustaining cost per zinc tonne sold decreased 3% to $1,528, lifting the realized mining margin per zinc tonne sold 37% to $2,581, the highest in the Company’s portfolio. Silver ounces sold increased 36% to 113,600 ounces, while the average realized price per silver ounce sold decreased 24% to $58.21 amid lower silver prices, and the realized mining margin per silver ounce sold decreased to $14.30 from $33.69.

 

Q3 2026 vs Q3 2025

 

Compared with Q3 2025, zinc production at Porco increased 19% from 2,488 tonnes to 2,963 tonnes, driven by a 17% increase in zinc head grades from 5.43% to 6.33% and improved zinc recovery of 96%, compared with 93% in the prior-year quarter, while tonnes milled remained broadly unchanged. Silver production decreased 3% from 92,001 ounces to 89,134 ounces, primarily due to a 4% decline in silver head grades from 71 g/t to 68 g/t, partially offset by improved silver recovery from 82% to 84%. Lead production remained broadly stable at 101 tonnes, compared with 103 tonnes in Q3 2025. The contrasting trends in zinc and silver grades are consistent with Porco’s role as a predominantly zinc-focused operation within the Company’s silver-zinc co-product portfolio.

 

Zinc tonnes sold increased 22% to 2,834 tonnes at an average realized price of $4,109 per tonne, up 18%, and with all-in sustaining cost per zinc tonne sold 11% lower at $1,528, the realized mining margin per zinc tonne sold increased 45% to $2,581. Silver ounces sold increased 8% and the average realized price per silver ounce sold increased 37% to $58.21; the realized mining margin per silver ounce sold turned positive at $14.30, compared with negative $(1.94) in Q3 2025.

 

- 17 -

 

 

Mining Operations - Caballo Blanco Group Operating Results

 

Caballo Blanco Group Production Table  2026 Q3   2026 Q2  

Change

Q3 vs Q2

   2025 Q3  

Change

Q3 vs Q3

   2026 YTD   2025 YTD  

Change

‘26 YTD

vs ‘25 YTD

 
Material Processed (tonnes milled)   68,442    59,997    14%   62,221    10%   187,438    171,642    9%
                                         
Production                                        
Silver (ounces)   287,219    326,215    (12)%   294,524    (2)%   920,322    902,576    2%
Zinc (tonnes)   4,542    4,126    10%   4,131    10%   12,635    11,654    8%
Lead (tonnes)   799    765    4%   722    11%   2,331    1,803    29%
                                         
Average Grade                                        
Silver (g/t)   145    183    (21)%   160    (9)%   167    176    (5)%
Zinc (%)   7.12    7.30    (2)%   7.14    (0)%   7.19    7.24    (1)%
Lead (%)   1.44    1.51    (5)%   1.45    (1)%   1.49    1.28    16%
                                         
Metal Recovery                                        
Silver (%)   90    92    (3)%   92    (2)%   92    93    (2)%
Zinc (%)   93    94    (1)%   93    0%   94    94    0%
Lead (%)   81    84    (4)%   80    1%   83    82    2%
                                         
Metals Sold                                        
Silver ounces sold (1)   338,120    191,707    76%   289,115    17%   754,247    903,554    (17)%
Zinc tonnes sold (1)   4,545    4,252    7%   3,527    29%   12,389    9,545    30%
                                         
Average realized price per silver ounce sold (2)   59.45    77.49    (23)%   41.60    43%   70.71    35.75    98%
All-in sustaining cost per silver ounce sold (2)   19.08    18.13    5%   17.69    8%   19.46    13.47    44%
Realized mining margin per silver ounce sold (2)   40.37    59.36    (32)%   23.91    69%   51.25    22.28    130%
                                         
Average realized price per zinc tonne sold (2)   4,092    3,442    19%   3,532    16%   3,613    3,431    5%
All-in sustaining cost per zinc tonne sold (2)   1,764    1,800    (2)%   1,579    12%   1,829    1,320    39%
Realized mining margin per zinc tonne sold (2)   2,328    1,643    42%   1,953    19%   1,784    2,111    (15)%

 

Notes:

 

(1) Silver ounces sold and zinc tonnes sold may be lower or higher than the volumes produced in the period due to two effects: (i) timing - concentrates produced in a quarter may be shipped and invoiced in a subsequent period or have been produced in a prior period; and (ii) commercial terms - payable ounces under offtake agreements are lower than produced ounces due to standard treatment and quality deductions applied by the customer.

(2) The Company reports non-GAAP measures, which include: cash cost of production per tonne milled, cash cost per silver ounce and zinc tonne sold, average realized price per silver ounce and zinc tonne sold, all-in sustaining cost per silver ounce, zinc tonne sold, realized mining margin per silver ounce or zinc tonne sold and realized ore processing margin per silver ounce or zinc tonne sold. The Company has adopted the practice of reporting costs on a co-product basis allocating production costs between Silver and Zinc and also records sales revenue from lead and copper as by-product credits to silver costs. These measures are widely used in the mining industry as a benchmark for performance, but do not have a standardized meaning and may differ from methods used by other companies even though the metrics have the same or similar names. Refer to the section titled “Non-GAAP Measures” in this MD&A.

 

Summary

 

Following a thorough examination of the Don Diego milling facility processing performance, Caballo Blanco Group made a strategic adjustment in Q3 2024 to improve metal recovery and concentrate value. Previously, the milling facility handled ore from three mines: Colquechaquita, Tres Amigos, and Reserva. A recent evaluation revealed that processing a blend of ores exclusively from Colquechaquita and Tres Amigos at Don Diego significantly improved silver recovery in the lead concentrate. This enhancement adds greater value to the lead concentrate and generates additional revenue for the Company. The process modification is consistent with our goal of enhancing efficiencies by improving metal recoveries and concentrate value.

 

- 18 -

 

 

Mining Operations - Caballo Blanco Group Operating Results (continued)

 

Ore from the Reserva mine is now processed and blended with ore from the San Lucas ore sourcing business to improve overall operating efficiency. The initial results of this adjustment reveal significant gains in silver in lead concentrate recovery, prompting management to adopt this new processing approach as the standard going forward. This revised operational framework will help both Caballo Blanco and San Lucas achieve more consistent recovery performance and maximize the value of its mineral resources.

 

Q3 2026 vs Q2 2026

 

Compared with Q2 2026, silver production at Caballo Blanco decreased 12% from 326,215 ounces to 287,219 ounces. A 14% increase in tonnes milled was more than offset by a 21% decline in silver head grades from 183 g/t to 145 g/t and a decrease in silver recovery from 92% to 90%. The lower silver grades reflect the planned mining sequence, consistent with the budgeted mine block model, with grades expected to improve in Q4 2026. Zinc production increased 10% to 4,542 tonnes, driven by higher throughput, offset by zinc head grades decreasing from 7.30% to 7.12% in Q3 2026 and recovery remaining stable in Q3 2026. Lead production increased 4% to 799 tonnes.

 

Silver ounces sold increased 76% to 338,120 ounces, exceeding production as concentrate accumulated during the Q2 2026 blockades was exported. The average realized price per silver ounce sold decreased 23% to $59.45 amid lower silver prices and, with all-in sustaining cost per silver ounce sold up 5% to $19.08 on higher sustaining capital expenditures, the realized mining margin per silver ounce sold decreased 32% to $40.37. Zinc tonnes sold increased 7% to 4,545 tonnes and the realized mining margin per zinc tonne sold increased 42% to $2,328. Cash cost of production per tonne milled increased 20% to $113.77.

 

Q3 2026 vs Q3 2025

 

Compared with Q3 2025, silver production at Caballo Blanco decreased 2% from 294,524 ounces to 287,219 ounces, as a 10% increase in tonnes milled was offset by a 9% decline in silver head grades from 160 g/t to 145 g/t and lower silver recovery of 90%, compared with 92% in the prior-year quarter. Zinc production increased 10% from 4,131 tonnes to 4,542 tonnes, driven by higher throughput, while zinc head grades and recovery remained broadly unchanged. Lead production increased 11% from 722 tonnes to 799 tonnes, also reflecting higher throughput.

 

Silver ounces sold increased 17% and zinc tonnes sold increased 29%. The average realized price per silver ounce sold increased 43% to $59.45 and, with all-in sustaining cost per silver ounce sold of $19.08 (Q3 2025 — $17.69), the realized mining margin per silver ounce sold expanded 69% to $40.37. The realized mining margin per zinc tonne sold increased 19% to $2,328. Cash cost of production per tonne milled increased 64% to $113.77 from $69.45.

 

- 19 -

 

 

Mining Operations - Zimapan Mine

 

Zimapan Production Table  2026 Q3   2026 Q2  

Change

Q3 vs Q2

   2025 Q3  

Change

Q3 vs Q3

   2026 YTD   2025 YTD  

Change

‘26 YTD

vs ‘25 YTD

 
Material Processed (tonnes milled)   222,424    222,259    0%   222,629    (0)%   668,353    670,364    (0)%
                                         
Production                                        
Silver (ounces)   402,067    391,121    3%   396,385    1%   1,156,051    1,234,876    (6)%
Zinc (tonnes)   4,831    4,764    1%   4,744    2%   13,635    13,763    (1)%
Lead (tonnes)   1,574    1,159    36%   1,099    43%   3,738    3,842    (3)%
Copper (tonnes)   355    337    5%   331    7%   1,000    839    19%
                                         
Average Grade                                        
Silver (g/t)   74    76    (2)%   77    (3)%   76    78    (2)%
Zinc (%)   2.81    2.78    1%   2.90    (3)%   2.71    2.69    1%
Lead (%)   0.85    0.68    26%   0.67    27%   0.72    0.73    (2)%
Copper (%)   0.28    0.27    4%   0.29    (3)%   0.27    0.26    4%
                                         
Metal Recovery                                        
Silver (%)   76    72    4%   72    4%   71    74    (4)%
Zinc (%)   77    77    0%   73    5%   75    76    (2)%
Lead (%)   83    77    8%   74    12%   78    79    (1)%
Copper (%)   57    57    1%   52    10%   56    48    16%
                                         
Metals Sold                                        
Silver ounces sold (1)   400,539    400,524    0%   361,878    11%   1,192,717    1,191,202    0%
Zinc tonnes sold (1)   4,678    4,804    (3)%   4,520    3%   13,403    13,345    0%
                                         
Average realized price per silver ounce sold(2)   70.24    66.32    6%   40.55    73%   69.35    34.70    100%
All-in sustaining cost per silver ounce sold(2)   8.12    15.01    (46)%   20.15    (60)%   17.78    21.14    (16)%
Realized mining margin per silver ounce sold(2)    62.12    51.32    21%   20.40    204%   51.57    13.56    280%
                                         
Average realized price per zinc tonne sold(2)   3,799    2,969    28%   3,012    26%   3,583    2,837    26%
All-in sustaining cost per zinc tonne sold(2)   3,064    2,623    17%   2,725    12%   2,998    2,953    2%
Realized mining margin per zinc tonne sold(2)   735    346    112%   287    156%   585    (116)   602%

 

Notes:

 

(1) Silver ounces sold and zinc tonnes sold may be lower or higher than the volumes produced in the period due to two effects: (i) timing - concentrates produced in a quarter may be shipped and invoiced in a subsequent period or have been produced in a prior period; and (ii) commercial terms - payable ounces under offtake agreements are lower than produced ounces due to standard treatment and quality deductions applied by the customer.

(2) The Company reports non-GAAP measures, which include: cash cost of production per tonne milled, cash cost per silver ounce and zinc tonne sold, average realized price per silver ounce and zinc tonne sold, all-in sustaining cost per silver ounce, zinc tonne sold, realized mining margin per silver ounce or zinc tonne sold and realized ore processing margin per silver ounce or zinc tonne sold. The Company has adopted the practice of reporting costs on a co-product basis allocating production costs between Silver and Zinc and also records sales revenue from lead and copper as by-product credits to silver costs. These measures are widely used in the mining industry as a benchmark for performance, but do not have a standardized meaning and may differ from methods used by other companies even though the metrics have the same or similar names. Refer to the section titled “Non-GAAP Measures” in this MD&A.

 

Summary

 

The Zimapan operation produces feed from the Carrizal and Monte mines, which are connected by a 7.4-kilometre underground access and haulage tunnel which terminates at the San Francisco process plant. Mining methods used include long hole and cut and fill stoping. The plant processes about 72,000 tonnes per month and produces three concentrates using differential flotation. Tailings Storage Facility and other support facilities are located adjacent and downstream of the plant location.

 

- 20 -

 

 

Mining Operations - Zimapan Mine (continued)

 

Q3 2026 vs Q2 2026

 

Compared with Q2 2026, silver production at Zimapan increased 3% from 391,121 ounces to 402,067 ounces. With tonnes milled unchanged and silver head grades decreasing 2% from 76 g/t to 74 g/t, the increase was driven by improved silver recoveries, which rose from 72% to 76%, following enhancements at the processing facility. Zinc production increased 1% to 4,831 tonnes, with zinc grades and recovery remaining broadly stable. Lead production increased 36% to 1,574 tonnes, driven by a 26% increase in lead head grades from 0.68% to 0.85% and improved lead recovery of 83%, compared with 77% in the prior quarter. Copper production increased 5% to 355 tonnes.

 

Silver ounces sold of 400,539 were in line with production and with Q2 2026. The average realized price per silver ounce sold increased 6% to $70.24 and all-in sustaining cost per silver ounce sold decreased 46% to $8.12, reflecting higher by-product lead and copper credits and lower treatment charges allocated to silver; the realized mining margin per silver ounce sold increased 21% to $62.12. For zinc, a 28% higher average realized price of $3,799 per tonne more than offset a 17% higher all-in sustaining cost of $3,064, lifting the realized mining margin per zinc tonne sold to $735 from $346.

 

Q3 2026 vs Q3 2025

 

Compared with Q3 2025, silver production at Zimapan increased 1% from 396,385 ounces to 402,067 ounces, as improved silver recovery (76% in Q3 2026 versus 72% in Q3 2025) offset a 3% decline in silver head grades. Zinc production increased 2% from 4,744 tonnes to 4,831 tonnes, with higher zinc recovery (77% in Q3 2026 versus 73% in Q3 2025) more than offsetting a 3% decline in zinc head grades. Lead production rose 43% from 1,099 tonnes to 1,574 tonnes, driven by a 27% increase in lead head grades and improved lead recovery (83% in Q3 2026 versus 74% in Q3 2025). Copper production increased 7% from 331 tonnes to 355 tonnes, as higher copper recovery (57% in Q3 2026 versus 52% in Q3 2025) more than offset a 3% decline in copper grades. Zimapan remains an important contributor to consolidated production, with ongoing efforts focused on improving recoveries and the quality of its produced concentrates.

 

Silver ounces sold increased 11% and zinc tonnes sold increased 3%. The average realized price per silver ounce sold increased 73% to $70.24, while all-in sustaining cost per silver ounce sold decreased 60% to $8.12 as by-product credits approximately doubled, and the realized mining margin per silver ounce sold increased to $62.12 from $20.40. The realized mining margin per zinc tonne sold increased to $735 from $287.

 

- 21 -

 

 

Ore Processing Operations - San Lucas Group Operating Results

 

San Lucas Production Table 

 

 

2026 Q3

   2026 Q2  

Change

Q3 vs Q2

  

 

 

 

2025 Q3

  

 

 

Change

Q3 vs Q3

   2026 YTD   2025 YTD  

Change

‘26 YTD

vs ‘25 YTD

 
Material Processed (tonnes milled)   92,921    115,424    (19)%   100,550    (8)%   303,112    282,218    7%
                                         
Production                                        
Silver (ounces)   314,451    411,367    (24)%   326,873    (4)%   1,067,223    941,528    13%
Zinc (tonnes)   6,062    7,692    (21)%   7,032    (14)%   20,898    19,690    6%
Lead (tonnes)   636    872    (27)%   575    11%   2,110    1,565    35%
                                         
Metal Recovery                                        
Silver (%)   82    82    0%   80    3%   82    83    (2)%
Zinc (%)   90    89    1%   89    1%   89    90    (1)%
Lead (%)   70    67    6%   63    11%   67    63    6%
                                         
Metals Sold                                        
Silver ounces sold (1)   449,355    333,899    35%   353,965    27%   1,418,129    1,006,827    41%
Zinc tonnes sold (1)   6,362    8,796    (28)%   6,199    3%   22,555    16,591    36%
                                         
Realized ore processing margin per silver ounce sold (2)   21.39    33.42    (36)%   (4.56)   569%   21.14    2.50    746%
Realized ore processing margin per zinc tonne sold (2)   464    819    (43)%   1,306    (64)%   727    1,605    (55)%

 

Notes:

 

(1) Silver ounces sold and zinc tonnes sold may be lower or higher than the volumes produced in the period due to two effects: (i) timing - concentrates produced in a quarter may be shipped and invoiced in a subsequent period or have been produced in a prior period; and (ii) commercial terms - payable ounces under offtake agreements are lower than produced ounces due to standard treatment and quality deductions applied by the customer.

(2) The Company reports non-GAAP measures, which include: cash cost of production per tonne milled, cash cost per silver ounce and zinc tonne sold, average realized price per silver ounce and zinc tonne sold, all-in sustaining cost per silver ounce, zinc tonne sold, realized mining margin per silver ounce or zinc tonne sold and realized ore processing margin per silver ounce or zinc tonne sold. The Company has adopted the practice of reporting costs on a co-product basis allocating production costs between Silver and Zinc and also records sales revenue from lead and copper as by-product credits to silver costs. These measures are widely used in the mining industry as a benchmark for performance, but do not have a standardized meaning and may differ from methods used by other companies even though the metrics have the same or similar names. Refer to the section titled “Non-GAAP Measures” in this MD&A.

 

Summary

 

San Lucas is the Company’s ore sourcing and trading business in Bolivia and should be regarded as a strategic component of the broader Bolivian production portfolio. By procuring ore from third-party suppliers and processing it through the Company’s existing plants, San Lucas supports higher plant utilization, enhances fixed-cost absorption, and increases overall operating flexibility. Given its margin-based structure, purchase prices are aligned to contained metal value. San Lucas is best evaluated on the basis of margin generation and its contribution to overall operating efficiency, rather than on average feed grade alone.

 

Q3 2026 vs Q2 2026

 

Compared with Q2 2026, San Lucas processed 92,921 tonnes of ore, a decrease of 19%, and produced 314,451 ounces of silver, a decrease of 24%, 6,062 tonnes of zinc (down 21)% and 636 tonnes of lead (down 27)%. The lower volumes reflected a strategic allocation of processing capacity, as the Company prioritized higher-margin ore from its own mines reducing the volume of third-party material processed at San Lucas. Silver recovery remained unchanged at 82%, while zinc and lead recoveries improved to 90% and 70%, respectively.

 

As San Lucas currently shares processing capacity with the Company’s mining operations, throughput can be adjusted according to plant availability, allowing the Company to prioritize the highest-margin feed. As announced on September 18, 2026, the Company acquired a 500-tonne-per-day milling facility in Bolivia dedicated exclusively to processing San Lucas ore, with operations expected to commence in Q4 2026. Once operational, the facility will eliminate competition for milling capacity between San Lucas and the Company’s mines, freeing up capacity at the three existing Bolivian processing plants for ore from the Company’s own mines while enabling San Lucas to expand its third-party ore sourcing business. The Reserva mine’s output will continue to be processed together with San Lucas’ purchased ore because its provides optimal recoveries.

 

Compared with Q3 2025, San Lucas silver production decreased 4% to 314,451 ounces from 326,873 ounces, while zinc production declined 14% from 7,032 tonnes to 6,062 tonnes, reflecting an 8% reduction in tonnes processed. Lead production increased 11% from 575 tonnes to 636 tonnes, supported by improved lead recovery of 70%, compared with 63% in the prior-year quarter. Silver and zinc recoveries also improved year over year, increasing from 80% to 82% and from 89% to 90%, respectively.

 

- 22 -

 

 

Other Properties

 

The Soracaya Project is located in the province of Sud-Chicas, in the department of Potosí in Bolivia. The Project has UTM WGS-84 coordinates of 784,896E; 7,645,567N at an elevation of 4,421 meters above sea level (masl). Paved and gravel roads connect the Soracaya Project to the capital city La Paz (676 km), the town of Uyumi (132 km) and the San Vicente mine site (12 km). There are currently six mining concessions at Soracaya which cover 8,325 hectares and are fully owned by Sinchi Wayra, the Company’s wholly owned subsidiary that was acquired in 2021 as part of the acquisition of its Bolivian assets.

 

The Soracaya site is typical for an exploration property with access and drill roads, limited infrastructure which includes offices, living quarters and related facilities, power generation and electrical distribution, water treatment, core logging and temporary warehousing facilities. In addition, an underground exploration drift and portal has been developed, surface exploration trenches have also been developed and remain open and accessible. The Company has commenced metallurgical testing by taking bulk samples from its initial extraction activities.

 

On October 4, 2024 the company published an NI 43-101 technical report of the property. The effective date of the resource estimate is January 1, 2024. Since the publication of the report, the Company has continued to perform exploration activities and is evaluating advancing the project into the development phase. The project is fully permitted for exploration and can currently extract 300 tonnes per month for exploration and metallurgical testing purposes. The Company has applied for an enhanced exploration and production permit which will allow for the extraction of 3,000 tonnes per month and expects to obtain approval before the end of 2026.

 

The mineral resources were estimated in conformity with CIM’s “Estimation of Mineral Resources and Mineral Reserves Best Practices Guidelines” (December 2019) and are reported in accordance with NI 43-101 guidelines.

 

Mineral resources are classified under the inferred category according to CIM guidelines. The author evaluated the resource in order to ensure that it meets the condition of “reasonable prospects of eventual economic extraction” as suggested under NI 43-101. The criteria considered were confidence, continuity and economic cut-off in addition to considering constraining the resources within an underground mining volumes.

 

Using a cut-off grade of 10.0% ZnEq, the Soracaya Project resources are presented in the table below.

 

Tonnes   ZnEq   Zn   Ag   Pb   Cu   NSR
4,137,000   31.62   1.23   259.76   7.23   0.09   248.82

 

Notes:

 

The current Resource Estimate was prepared by Garth Kirkham, P.Geo., of Kirkham Geosystems Ltd.

 

  1) All mineral resources have been estimated in accordance with Canadian Institute of Mining and Metallurgy and Petroleum (“CIM”) definitions, as required under National Instrument 43-101 (“NI43-101”).
  2) The Mineral Resource Estimate was prepared using a 10% zinc equivalent cut-off grade. Cut-off grades were derived from $3.65/lb. copper, $21.00/oz silver, $1.15/lb. zinc and $1.00/lb. lead. This cut-off grade was based on current smelter agreements and total OPEX costs of $156.00/t based on 2023 actual costs derived from the Porco mine data, with process recoveries of 70.0% for copper, 80.0% for zinc, 70.0% for lead, and 85% for silver. All prices are stated in $USD.
  3) An Inferred Mineral Resource has a lower level of confidence than that applying to an Indicated Mineral Resource and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of Inferred Mineral Resources could be upgraded to Indicated Mineral Resources with continued exploration.
  4) Mineral resources are not mineral reserves until they have demonstrated economic viability. Mineral resource estimates do not account for a resource’s mineability, selectivity, mining loss, or dilution. All figures are rounded to reflect the relative accuracy of the estimate and therefore numbers may not appear to add precisely.

 

- 23 -

 

 

Qualified Person and Technical Disclosures

 

All scientific and technical disclosure contained in this MD&A was reviewed and approved by Garth Kirkham P.Geo. an independent consultant to the Company, who is a qualified person under NI 43-101 and has approved the scientific and technical information contained within this news release.

 

Production at the Zimapan Mine is not supported by a feasibility study on mineral reserves demonstrating economic or technical viability or any other independent economic study under NI 43-101. Accordingly, there is increased uncertainty and higher economic and technical risks of failure associated with production operations at the Zimapan Mine. Production and economic variables may vary considerably due to the absence of a complete and detailed site analysis according to and in accordance with NI 43- 101. Project failure may adversely impact the Company’s future profitability.

 

Overview of Financial Results

 

Summary of Quarterly Financial Results

 

The following table presents selected financial information for each of the most recent eight quarters:

 

   2026   2025   2024 
   Q3   Q2   Q1   Q4   Q3   Q2   Q1   Q4 
Revenues   153,276    113,458    127,529    102,784    79,989    73,295    70,314    81,669 
Mine operating costs   93,169    62,319    84,660    66,697    59,823    48,007    42,455    56,419 
Gross profit   60,107    51,139    42,869    36,087    20,166    25,288    27,859    25,250 
Operating expenses   7,441    6,386    8,127    6,749    7,213    5,306    5,079    6,068 
Net income (loss)   37,617    2,005    28,470    (4,550)   16,344    20,977    9,451    12,842 
Net income (loss) per share – basic   0.40    0.02    0.31    (0.05)   0.18    0.24    0.11    0.14 
Net income (loss) per share – diluted (1)   0.40    0.02    0.30    (0.05)   0.18    0.22    0.11    0.14 

 

(1) On December 10, 2025 the Company consolidated its issued and outstanding common shares on the basis of one post-consolidated common share for every four pre-consolidated common shares. The number of issued and outstanding shares and any per share amounts have been retrospectively restated.

 

The Company’s quarterly results vary based on the silver ounces and zinc tonnes sold per period together with the average realized silver and zinc prices for the period.

 

- 24 -

 

 

Overview of Quarterly Financial Results (continued)

 

Financial Results for the Quarters ended September 30, 2026 and 2025

 

           Change 
   2026 Q3   2025 Q3   ‘26 Q3 vs ‘25 Q3 
             
Revenues   153,276    79,989    92%
                
Mine operating costs               
Cost of sales   (85,789)   (54,028)   59%
Depletion, depreciation and amortization   (7,380)   (5,795)   27%
Gross profit   60,107    20,166    198%
                
General and administrative expenses   (6,401)   (6,452)   (1)%
Share-based compensation expense   (1,040)   (761)   37%
Operating income   52,666    12,953    307%
                
Other income   (288)   827    (135)%
Gain (loss) on change in fair value of consideration payable   8,893    (2,283)   (489)%
Foreign exchange gain   7,060    4,119    71%
Income before tax   68,331    15,616    338%
                
Income tax expense   (30,714)   728    (4319)%
Net income for the period   37,617    16,344    130%
                
Other comprehensive income that may be reclassified subsequently to net income or loss:               
Unrealized gain (loss) on marketable securities   (360)   112    (421)%
Currency translation differences   (148)   669    (122)%
Comprehensive income for the period   37,109    17,125    117%
                
Net income per share (1):               
Basic   0.40    0.18    122%
Diluted   0.40    0.18    122%
                
Weighted average number of common shares (1):               
Basic   92,993,277    90,006,111      
Diluted   94,984,980    93,280,260      

 

Notes:

 

(1) On December 10, 2025 the Company consolidated its issued and outstanding common shares on the basis of one post-consolidated common share for every four pre-consolidated common shares. The number of issued and outstanding shares and any per share amounts have been retrospectively restated.

 

Overview of Financial Results for the quarters ended September 30, 2026

 

Revenues for the quarter ended September 30, 2026, were $153,276, an increase of $73,287 as compared to Q3 2025. The increase was driven by an increase in the realized selling price and amount of metal sold for both silver and zinc. The average realized price of silver increased from $41.14 in Q3 2025 to $64.72 in Q3 2026 and the amount of silver ounces sold increased 46%. Zinc tonnes sold increased by 35% and the average realized price of zinc increased from $3,336 to $4,011 per tonne.

 

Cost of sales for the quarter ended September 30, 2026 was $85,789, an increase of $31,761 compared to Q3 2025. The increase was mainly driven by San Lucas, which operates a margin-based sourcing model, as higher silver and zinc prices in the current quarter increased ore purchase costs. Refer to the Cost of Sales note in the consolidated interim financial statements for a breakdown of mining costs versus ore purchasing costs.

 

Depreciation, depletion and amortization for the quarter ended September 30, 2026 was $7,380, an increase of $1,585 compared with Q3 2025. This movement was due to a greater depreciation base arising from the Company’s continued capital expenditures to maintain and expand production.

 

General and administrative expenses for the quarter ended September 30, 2026 were $6,401, a decrease of $51 compared with Q3 2025.

 

Other income (expense) for the quarter ended September 30, 2026 was ($288), a decrease of $1,115 from the gain of $827 in Q3 2025.

 

- 25 -

 

 

Overview of Quarterly Financial Results (continued)

 

Gain (loss) on change in fair value of consideration payable for the three months ended September 30, 2026 was $8,893, an increase of $11,176 from the $2,283 loss recognized in Q3 2025. The $8.9 million gain on revaluation of the consideration payable is a non-cash item, generated by a change of assumptions used in determining the value of the liability.

 

The consideration payable includes a contingent value right (CVR) which generates a monthly $1.3m payment up to December 2032 when the monthly average zinc price exceeds the established base price of $3,850 per tonne and increases by $83 per $100 per tonne increase above the base price. In addition to the right to receive the CVR payments, the holder of the CVR also has the right to exercise a hedging option when the price exceeds $3,850 which could require the Company to hedge 25% to 50% of forecast zinc production from its Bolivian mining operations for 24 months which would guarantee CVR payment for the duration of the hedging option.

 

The Company uses a Monte Carlo simulation prepared by a third-party specialist to estimate the value of the CVR which is based upon several assumptions that are continuously updated each reporting period to reflect market conditions. Up until Q3 2026 the CVR valuation model had an assumption that the CVR holder would immediately exercise the hedging option if the monthly average zinc spot price exceeded $3,850, and would lock-in the hedge for 24 months at the price for the month in which it exceeded the threshold, thereby guaranteeing CVR payments for 24 months.

 

During the third quarter, the average price of zinc exceeded the base price in both August and September triggering two CVR payments totalling $2,750 and it was the first time that the base price had been surpassed since the CVR was issued in October 2024. The holder did not exercise the hedging option even though the base price was exceeded because if metal prices were to decrease, the hedge option could generate losses to the holder that could exceed the value of the CVR payments received. Because the hedging option was not exercised in spite of exceeding the base price, management has revised its estimate to assume a shorter lock-in period for the hedging option of 3 months. Management will reassess this assumption each period taking into account the volatility of metal prices and whether or not the holder exercises the hedging option and the length of the hedging period.

 

If management had not updated its assumption regarding the lock-in period, the CVR liability would have increased because the higher zinc prices in the quarter but by decreasing the lock-in period to reflect the fact that the option was not exercised provides a more fair representation of the current economic reality. Refer to note 3 of the Condensed Interim Consolidated Financial Statements for further details.

 

Foreign exchange gain for the quarter ended September 30, 2026 was $7,060, having increased by $2,941 compared with Q3 2025. This change was primarily attributed to the change in the Boliviano exchange rate, which led to a gain on the revaluation of monetary assets and liabilities.

 

Income tax expense for the quarter ended September 30, 2026 was $30.7 million, an increase of $31.4 million compared to a income tax recovery of $724 in Q3 2025. The significant increase in income tax expense was caused by two factors. The primary driver of the increase was due to the 92% increase in revenues compared to Q3 2025 that was caused by higher metal prices and increased volumes of silver ounces and zinc tonnes sold and increased the Company’s taxable income. The quarter’s income tax expense was also significantly increased by the depreciation of the Boliviano from 9.77 in Q2 2026 to 12.02 in Q3 2026. The higher exchange rate increased the tax basis of foreign-currency-denominated assets which is taxable in the Bolivian tax system. The increase in the exchange rate year over year from 6.96 to 12.02, a 73% increase, also caused taxable income valued in Bolivianos to increase considerably as sales are denominated in $USD.

 

- 26 -

 

 

Overview of Quarterly Financial Results (continued)

 

Financial Results for the nine months ended September 30, 2026 and 2025

 

       Change 
   2026 YTD   2025 YTD   ‘26 YTD vs ‘25 YTD 
             
Revenues   394,263    223,598    76%
                
Mine operating costs               
Cost of sales   (217,675)   (134,474)   62%
Depletion, depreciation and amortization   (22,473)   (15,811)   42%
Gross profit   154,115    73,313    110%
                
General and administrative expenses   (19,766)   (15,329)   29%
Share-based compensation expense   (2,188)   (2,269)   (4)%
Operating income   132,161    55,715    137%
                
Other income   3,172    2,864    11%
Loss on change in fair value of consideration payable   (5,930)   (5,262)   13%
Foreign exchange gain   21,909    13,497    62%
Income before tax   151,312    66,814    126%
                
Income tax expense   (83,220)   (20,042)   315%
Net income for the period   68,092    46,772    46%
                
Other comprehensive income that may be reclassified subsequently to net income or loss:               
Unrealized gain (loss) on marketable securities   (658)   289    (328)%
Currency translation differences   1,455    186    682%
Comprehensive income for the period   68,889    47,247    46%
                
Net income per share (1):               
Basic   0.74    0.52      
Diluted   0.72    0.51      
                
Weighted average number of common shares (1):               
Basic   92,614,861    89,316,277      
Diluted   94,606,564    91,765,426      

 

Notes:

 

(1) On December 10, 2025 the Company consolidated its issued and outstanding common shares on the basis of one post-consolidated common share for every four pre-consolidated common shares. The number of issued and outstanding shares and any per share amounts have been retrospectively restated.

 

Overview of Quarterly YTD Financial Results

 

Revenues for the nine months ended September 30, 2026 was $394,263, an increase of $170,665 compared with the nine months ended September 30, 2025. The increase was primarily due to an increase in the average realized price of silver from $35.21 in 2025 to $71.41 in 2026 and an increase in the average realized price of zinc from $3,203 in 2025 to $3,601 in 2026.

 

Cost of sales for the nine months ended September 30, 2026 was $217,675, an increase of $83,201 compared with the nine months ended September 30, 2025. The increase was primarily driven by San Lucas, which operates a margin-based sourcing model, as higher silver and zinc prices in the current quarter increased ore purchase costs. Refer to the cost of sales note in the consolidated interim financial statements for a breakdown of the ore purchase costs versus mining costs. The increase in costs was offset by an update to the estimate of the future expenditures in Bolivia required for the restoration of mining properties during the second quarter, which resulted in a decrease in the decommissioning and restoration provision exceeding the decommissioning and restoration asset that was recorded as a reduction to cost of sales.

 

Depreciation, depletion and amortization for the nine months ended September 30, 2026 was $22,473, an increase of $6,662 compared with the nine months ended September 30, 2025. The increase is attributed to a greater depreciation basis arising from continued capital expenditures to maintain and increasing production at the Company’s mine properties.

 

General and administrative expenses for the nine months ended September 30, 2026 was $19,766, an increase of $4,437 compared with the nine months ended September 30, 2025. The increase was mainly attributable to an increase in salaries and benefits in Bolivia, which increased as a result of the change in Boliviano exchange rate.

 

- 27 -

 

 

Overview of Quarterly YTD Financial Results (continued)

 

Other income for the nine months ended September 30, 2026 was $3,172, an increase of $308 compared to the nine months ended September 30, 2025. The increase was due to higher interest income on VAT receivable balances which was partially offset by increases in the interest expense from loans payable.

 

Loss on change in fair value of consideration payable for the nine months ended September 30, 2026 was $5,930 an increase of $668 from the $5,262 loss recognized in nine months ended September 30, 2025. The $5,930 loss on revaluation of the consideration payable is a non-cash item, generated by a change of assumptions used in determining the value of the liability.

 

The consideration payable includes a contingent value right (CVR) which generates a monthly $1.3m payment up to December 2032 when the monthly average zinc price exceeds the established base price of $3,850 per tonne and increases by $83 per $100 per tonne increase above the base price. In addition to the right to receive the CVR payments, the holder of the CVR also has the right to exercise a hedging option when the price exceeds $3,850 which could require the Company to hedge 25% to 50% of forecast zinc production from its Bolivian mining operations for 24 months which would guarantee CVR payment for the duration of the hedging option.

 

The Company uses a Monte Carlo simulation prepared by a third-party specialist to estimate the value of the CVR which is based upon several assumptions that are continuously updated each reporting period to reflect market conditions. Up until Q3 2026 the CVR valuation model had an assumption that the CVR holder would immediately exercise the hedging option if the monthly average zinc spot price exceeded $3,850, and would lock-in the hedge for 24 months at the price for the month in which it exceeded the threshold, thereby guaranteeing CVR payments for 24 months.

 

During the third quarter, the average price of zinc exceeded the base price in both August and September triggering two CVR payments totalling $2,750 and it was the first time that the base price had been surpassed since the CVR was issued in October 2024. The holder did not exercise the hedging option even though the base price was exceeded because if metal prices were to decrease, the hedge option could generate losses to the holder that could exceed the value of the CVR payments received. Because the hedging option was not exercised in spite of exceeding the base price, management has revised its estimate to assume a shorter lock-in period for the hedging option of 3 months. Management will reassess this assumption each period taking into account the volatility of metal prices and whether or not the holder exercises the hedging option and the length of the hedging period.

 

If management had not updated its assumption regarding the lock-in period, the CVR liability would have increased because the higher zinc prices in the nine months ended September 30, 2026 compared to the same period in 2025, but by decreasing the lock-in period to reflect the fact that the option was not exercised provides a more fair representation of the current economic reality. Refer to note 3 of the Condensed Interim Consolidated Financial Statements for further details.

 

Foreign exchange gain for the nine months ended September 30, 2026 was $21,909, an increase of $8,412 compared to the nine months ended September 30, 2025. This change was primarily attributed to the change in the Boliviano exchange rate, which led to a gain on the revaluation of monetary assets and liabilities.

 

Income tax expense for the nine-months ended September 30, 2026 was $83,220, an increase of $63,178 compared to the nine months ended September 30, 2025. The primary driver of the increase was due to a 76% increase in revenues compared to the same period in 2025 caused by higher metal prices which increased the Company’s taxable income considerably. Income tax expense for the nine-months ended September 30, 2026 was also increased due to a non-recurring event that in June 2026, Bolivia transitioned from a fixed official exchange rate between the Boliviano and the U.S. dollar to a floating exchange rate. The fixed rate was 6.96 BOB to $USD and the ending exchange rate at period end was 12.02, a 76% increase. The new exchange rate generated a significant increase in the tax basis of foreign-currency-denominated assets, most notably the Company’s cash and marketable securities generated from U.S. dollar-denominated sales. The resulting unrealized foreign exchange gain was recognized as taxable income under the Bolivian tax system. The increase in the exchange rate also caused taxable income to increase as the $USD denominated sales revenue translated to Bolivianos increased taxable income considerably.

 

- 28 -

 

 

Liquidity, Capital Resources and Contractual Obligations

 

Liquidity

 

As at September 30, 2026, the Company had cash and cash equivalents of $102,836 (December 31, 2025 - $44,267). The Company’s cash is not exposed to liquidity risk and there is no restriction on the ability of the Company to use these funds to meet its obligations. The Company also has $21,798 of marketable securities, which consist of liquid holdings of US treasury bills and treasury notes that can be readily sold to be converted into cash. The securities are held with Stifel bank which uses a portion of the holdings as collateral for the Standby Letters of Credit that were issued to Banco BISA and Banco Credito de Bolivia (see note 10(a) of the condensed interim consolidated financial statements). Although the securities held can be readily converted to cash, they are restricted to the extent that the amounts serve as collateral. The Standby Letter of credit issued to Banco BISA is for $10,000 and expires on April 20, 2027. The standby letter of credit issued to Banco Credito de Bolivia is for $5,800 and expires on September 14, 2026, and automatically renews every six months.

 

For the nine months ended September 30, 2026, the Company reported net income of $68,092 (nine months ended September 30, 2025 - net income of $46,772). As at September 30, 2026, the Company had working capital of $113,254 (December 31, 2025 - working capital of $48,352).

 

The Company has a consideration payable balance outstanding for the acquisition of the Sinchi Wayra and Illapa operations which occurred in 2022. The consideration payable consisted of a base purchase price obligation and a contingent value right (the “CVR”). The base purchase price obligation was fully paid in the third quarter of 2025, and only the CVR remains outstanding. Payments related to the CVR are triggered when the price of zinc exceeds $3,850 per tonne in the calendar month. The Company made its first payment under the CVR in September 2026 in the amount of $1,333. An additional payment of $1,417 was made in October.

 

As at September 30, 2026, the Company has non-current loans payable of $162 (December 31, 2025 - $1,344), and non-current consideration payable to Glencore of $23,423 (December 31, 2025 - $20,243). The consideration payable to Glencore is an estimated fair value of CVR payments that will only become payable if zinc price exceeds $3,850.

 

Credit Facilities and Borrowings

 

The Company has a secured credit facility denominated in Bolivian Bolivianos with Banco BISA S.A. of BOB 55,000 ($4,576), which is comprised of 1) a revolving credit facility of BOB 48,800 ($4,060) for the financing of mining operations and working capital with a fixed interest rate of 10.00% per annum; and 2) a “loan guarantee” credit facility of BOB 6,200 ($516) for the purpose of providing collateral to the Bolivian government for VAT refunds collected prior to the completion of the audit process by the Bolivian tax authority.

 

The Company also has an unsecured revolving credit facility for working capital requirements and a loan guarantee with Banco de Crédito de Bolivia S.A. for a total of BOB 48,020 ($3,995). The credit facility has a weighted average fixed interest rate of 10.00% per annum and the weighted average interest rate on the loan guarantee facility is 2.0%.

 

On April 8, 2026, the Company completed an offering of BOB 70,000 ($5,824) under its San Lucas Promissory Notes Issuance program. The notes have an annual interest rate of 11.50%, mature on March 22, 2027, and are unsecured. On August 4, 2026, the Company completed an additional offering of BOB 70,000 ($5,824). The notes have an annual interest rate of 10.9985%, mature on July 18, 2027 and are unsecured.

 

On February 14, 2026 the Company obtained an unsecured 6 month working capital term loan for BOB 17,150 ($1,757) with a fixed interest rate of 10.0% with repayment of interest and principal at the end of the term from Banco Mercantil Santa Cruz S.A. On March 17, 2026, the Company obtained an unsecured 6 month working capital term loan for BOB 14,000 ($1,165) with a fixed interest rate of 10% with repayment of interest and principal at the end of the term from Banco Bisa S.A. Both loans have been paid in full.

 

On March 31, 2026, the Company obtained an additional working capital term loan from Banco BISA S.A. for BOB 69,986 ($5,822). The loan term is 360 calendar days and due on March 26, 2027. The loan is unsecured and has a fixed interest rate of 10%.

 

- 29 -

 

 

Liquidity, Capital Resources and Contractual Obligations (continued)

 

On December 30, 2024, the Financial System Supervisory Authority (ASFI) authorized the San Lucas Bonds Program. The San Lucas Bonds program allows the Company to issue up to $40,000 of unsecured bonds in the Bolivian Stock market (Bolsa Boliviana de Valores), the bonds can be denominated in USD or Bolivian Bolivianos. As at September 30, 2026, no bonds have been issued under the program.

 

Cash Flow

 

The Company’s cash flows from operating, investing, and financing activities during the three and nine months ended September 30, 2026 are summarized as follows:

 

  

Three months ended

September 30,

  

Nine months ended

September 30,

 
   2026   2025   2026   2025 
Cash flow                    
Cash generated by operating activities   65,558    22,821    89,698    61,981 
Cash (used by) provided by investing activities   (10,082)   (30,840)   (26,628)   (77,807)
Cash (used by) provided by financing activities   (2,544)   8,041    (3,969)   20,039 
Increase in cash and cash equivalents   52,932    22    59,101    4,213 
Effect of exchange rate on held in foreign currencies   (494)   (1)   (532)   84 
Cash, beginning of the period   50,398    39,997    44,267    35,721 
Cash, end of period   102,836    40,018    102,836    40,018 

 

Operating Activities

 

Operating cash flow for the period increased by $27,717 compared to 2025. Higher operating cash flow was primarily due to higher revenues, driven by greater sales volumes and greater average realized prices for both silver and zinc.

 

Investing Activities

 

Cash used in investing activities decreased by $51,179 compared to 2025. The decrease was attributed to the full repayment and extinguishment of the base purchase price obligation of the consideration payable to Glencore for the acquisition of Sinchi Wayra in 2025. This was offset by the Company’s first payment under the CVR during September 2026 for $1,333, and an increase in capital expenditures of $6,187 during the current year period.

 

The Company continues to invest in marketable securities that are held with Stifel Bank, which uses a portion of the holdings as collateral for the Standby Letters of Credit that were issued to Banco BISA and Banco Credito de Bolivia. The Company received proceeds of $15,114 from maturities of securities during the current year period, and reinvested the proceeds into purchases of additional securities for $15,108.

 

Financing Activities

 

For the nine months ended September 30, 2026, cash used by financing activities was $3,969, compared to a net amount provided of $20,039 in 2025. During the current period, the Company received $88,717 from the proceeds of loans and repaid $93,786 on those loans and lease liabilities, compared to $58,042 and $40,382 respectively during 2025.

 

Proceeds from the exercise of stock options were $1,100, compared to $2,379 in 2025.

 

Capital Resources

 

The Company’s objective when managing capital is to maintain financial flexibility to continue as a going concern while optimizing growth and maximizing returns of investments from shareholders.

 

The Company monitors its capital structure and based on changes in operations and economic conditions, may from time to time adjust the structure by repurchasing shares, issuing new shares, issuing new debt or retiring existing debt. The Company prepares an annual budget and quarterly forecasts to facilitate the management of its capital requirements. The annual budget is approved by the Company’s Board of Directors.

 

- 30 -

 

 

Liquidity, Capital Resources and Contractual Obligations (continued)

 

The Company is not subject to any externally imposed capital requirements with the exception of compliance with covenants for the San Lucas Promissory Notes Issuance program. The Company is fully compliant with all financial covenants stipulated in the agreement.

 

Contractual Obligations

 

The expected maturity of the Company’s contractual obligations as at September 30, 2026 are outlined below:

 

   <1
year
   1 - 2
years
   2 - 5
years
   >5
years
   Total 
   $   $   $   $   $ 
Trade payables and accrued liabilities   35,436    4,984    -    -    40,420 
Consideration payable - CVR & additional payments   10,632    7,384    8,855    3,068    29,939 
Loans payable   42,451    162    -    -    42,613 
Lease payments   12    10    11    -    33 
    88,531    12,540    8,866    3,068    113,005 

 

Liquidity Outlook

 

The Company believes that the cash on hand, combined with expected operating cash flows, will be sufficient to meet operating requirements as they arise for at least the next 12 months. With respect to longer term capital expenditure funding requirements, the Company believes that cash flow from its existing operations, available credit through existing debt facilities and access to debt and capital markets is adequate and will enable the Company to maintain an appropriate overall liquidity position. The Company continues to assess financing alternatives, including equity or debt or a combination of both, to fund future growth.

 

Off-balance Sheet Arrangements

 

The Company has not entered into any material off-balance sheet arrangement such as guarantee contracts, contingent interests in assets transferred to unconsolidated entities or derivative financial obligations.

 

Transactions with Related Parties

 

During the nine months ended September 30, 2026 and 2025, the Company incurred the following charges for directors, officers, and other members of key management of the Company, as well as for companies controlled by directors and officers of the Company:

 

   Three months ended September 30,   Nine months ended September 30, 
   2026   2025   2026   2025 
Management and consulting fees   731    611    2,090    1,920 
Share-based compensation   882    919    1,597    2,201 
    1,613    1,530    3,687    4,121 

 

Of the $731 and $2,090 in management and consulting fees incurred with related parties during the three and nine months ended September 30, 2026, $55 and $167 (2025 - $53 and $170) was related to directors’ fees and $676 and $1,923 (2025 - $558 and $1,750) was related to management and consulting fees.

 

Key management includes directors of the Company, the CEO, the CFO, the Executive Chairman, and other members of key management. Other than the amounts disclosed above, there was no other compensation paid or payable to key management for employee services for the reported periods.

 

Subsequent Events

 

There are no subsequent events to report up to the date of this MD&A.

 

- 31 -

 

 

Material Accounting Estimates and Judgments

 

The preparation of the financial statements in conformity with IFRS requires management to make estimates and judgments that may have a material impact on the financial statements. Estimates are continuously evaluated and are based on management’s experience and expectations of future events that are believed to be reasonable under the circumstances. Management reviews estimates and their underlying assumptions on an ongoing basis. Revisions to estimates are recognized prospectively. Actual outcomes may differ from these estimates. The Company’s critical accounting judgments and estimates have been consistently applied with those presented in Note 4 of the audited annual consolidated financial statements for the years ended December 31, 2025, and 2024 with the exception of the change in assumption related to the valuation of the consideration payable balance.

 

Consideration Payable – Contingent Value Rights

 

The consideration payable includes a contingent value rights (“CVR”) component which provides the holder with a monthly $1,333 payment up to December 2032 when the monthly average zinc price exceeds the established base price of $3,850 per tonne and increases by $83 per $100 per tonne increase above the base price. In addition to the right to receive the CVR payments, the holder of the CVR also has the right to exercise a hedging option when the price exceeds $3,850 which could require the Company to hedge 25% to 50% of forecast zinc production from its Bolivian mining operations for up to 24 months which would guarantee that the holder receives the CVR payments for the duration of the hedging option.

 

CVR payments are based on the average LME zinc price for each calendar month. Therefore, the payoff on the CVR is “path-dependent”, the ultimate amount paid depends on the price of the underlying over time. Additionally, commodity prices exhibit mean reversion, whereby asset prices tend to move back toward their long-term average over time. A valuation approach capable of capturing the path-dependent and mean reversion feature is therefore required. The Monte Carlo Simulation is a commonly used approach to model securities with path-dependent payoffs and mean reversion features. Monte Carlo Simulation uses random sampling techniques based on continuous time Stochastic processes to generate a large number of possible, but random, asset price paths. In each individual price path, the payoff of the security can be calculated based on the average zinc price relative to a fixed base price of $3,850. These payoffs are then discounted to the reporting date and averaged to determine the fair value of the CVR.

 

The estimated value of the CVR is based upon several assumptions that are continuously updated each reporting period to reflect market conditions. Up until Q3 2026 the valuation model had an assumption that the holder would immediately exercise the hedging option if the monthly average zinc spot price exceeded $3,850, and the holder would lock-in the hedge for 24 months, thereby guaranteeing CVR payments for 24 months.

 

During the third quarter of 2026, the average price of zinc exceeded the base price in both August and September, triggering two CVR payments totaling $2,750 and it was the first time that the base price had been surpassed since the CVR was issued in October 2024. If metal prices were to decrease from the hedge price, the hedge option could generate losses to the holder that could exceed the value of the CVR payments received. Because the hedging option was not exercised in spite of exceeding the base price, management has revised its estimate to assume a shorter lock-in period for the hedging option of 3 months. Management will reassess this assumption each period taking into account whether the holder exercises the hedging option and the length of the hedging period requested.

 

If management had not updated its assumption regarding the lock-in period, the CVR liability would have been $48,008 as at September 30, 2026 because of the increase in zinc prices in the period. By decreasing the lock-in period to 3 months, which is consistent with the counterparty’s behaviour with respect to the CVR, its value was determined to be $24,840, a decrease in the liability of $23,528.

 

  

September 30, 2026

 
   $ 
Consideration payable valuation - 3 month lock-in period assumption (as reported)   24,840 
Consideration payable balance - 24 month lock-in period (previous assumption)   48,008 
Effect of change in management estimate   (23,528)

 

Accounting Policies Including Changes in Accounting Policies and Initial Adoption

 

The accounting policies applied in the preparation of these unaudited condensed interim consolidated financial statements are consistent with those applied and disclosed in the Company’s audited consolidated financial statements for the year ended December 31, 2025 and reflect all the adjustments necessary for fair presentation in accordance with IFRS for the interim periods presented. Refer to Note 3 of the 2025 annual audited consolidated financial statements for a detailed discussion.

 

Financial Instruments and Other Instruments

 

The carrying amounts of the Company’s financial assets and financial liabilities by category are as follows:

 

September 30, 2026  Amortized cost   FVTPL   FVTOCI   Total 
   $   $   $   $ 
Financial assets                    
Cash and cash equivalents   102,836    -    -    102,836 
Marketable securities   -    -    21,798    21,798 
Trade and other receivables   18,244    38,143    -    56,387 
    121,080    38,143    21,798    181,021 
Financial liabilities                    
Trade payables and accrued liabilities   40,420    -    -    40,420 
Consideration payable        24,840    -    24,840 
Loans payable   42,613    -    -    42,613 
Other liabilities   14,910    -    -    14,910 
    97,943    24,840    -    122,783 

 

December 31, 2025  Amortized cost   FVTPL   FVTOCI   Total 
Financial assets                    
Cash and cash equivalents   44,267    -    -    44,267 
Marketable securities   -    -    22,462    22,462 
Trade and other receivables   22,977    20,371    -    43,348 
    67,244    20,371    22,462    110,077 
Financial liabilities                    
Trade payables and accrued liabilities   54,569    -    -    54,569 
Consideration payable   -    20,243    -    20,243 
Loans payable   51,986    -    -    51,986 
Other liabilities   23,598    -    -    23,598 
    130,153    20,243    -    150,396 

 

- 32 -

 

 

Financial Instruments and Other Instruments (continued)

 

The categories of the fair value hierarchy that reflect the inputs to valuation techniques used to measure fair value are as follows:

 

  ● Level 1: Quoted prices in active markets for identical assets or liabilities;
  ● Level 2: Inputs other than quoted prices included within Level 1 that are observable for the asset or liability, either directly or indirectly; and
  ● Level 3: Inputs for the asset or liability based on unobservable market data.

 

The carrying values of cash, other receivables, and trade payables and accrued liabilities approximate their fair values because of their short-term nature.

 

Marketable securities consist of US treasury notes and US treasury bills which are held as part of the Company’s cash position and liquidity management strategy. The marketable securities are measured at fair value using level 1 inputs, the unrealized gain/loss is recorded as other comprehensive income and once the securities are sold or mature the corresponding gain/loss is recorded as other income/expense.

 

The securities are held with Stifel bank which uses a portion of the holdings as collateral for the Standby Letters of Credit that were issued to Banco BISA and Banco Credito de Bolivia (see note 10(a) of the condensed interim consolidated financial statements). Although the securities held can be readily converted to cash they are restricted to the extent that the amounts serve as collateral. The Standby Letter of credit issued to Banco BISA is for $10,000 and expires on May 26, 2026. The standby letter of credit issued to Banco Credito de Bolivia is for $5,800 and expires on March 26, 2026, and automatically renews each year. Since the standby letter of credit to Banco Credito de Bolivia will renew indefinitely, the amount held as collateral has been classified as non-current.

 

Trade receivables are measured at fair value using Level 2 inputs. The fair value of trade receivables is measured based on inputs other than quoted prices for the underlying commodity prices (silver, lead, zinc, copper) to which the receivable relates as the trade receivables are provisionally priced at the time of sale.

 

The fair value of the loans payable for disclosure purposes is determined using discounted cash flows based on the expected amounts and timing of future cash flows discounted using a market rate of interest adjusted for appropriate credit risk.

 

The levels in the fair value hierarchy into which the Company’s financial assets and liabilities that are measured and recognized on the consolidated statements of financial position at fair value on a recurring basis were categorized as follows:

 

   September 30, 2026   December 31, 2025 
   Level 1   Level 2   Level 3   Level 1   Level 2   Level 3 
    $    $    $    $    $    $ 
Assets                              
Marketable securities   21,798    -         22,462    -    - 
Trade and other receivables   -    38,143    -    -    20,371    - 
    21,798    38,143    -    22,462    20,371    - 
                               
Liabilities                              
Consideration payable   -    -    24,840    -    -    20,243 
    -    -    24,840    -    -    20,243 

 

The majority of the Company’s trade receivables arose from provisional concentrate sales and are valued using quoted market prices based on the forward London Metal Exchange for silver, zinc and lead and the London Bullion Market Association P.M. fix for silver.

 

The methodology and assessment of inputs for determining the fair value of financial assets and liabilities as well as the levels of hierarchy for the Company’s financial assets and liabilities measured at fair value remains unchanged from that as at December 31, 2025.

 

- 33 -

 

 

Risk Factors

 

The Company has exposure to risks of varying degrees of significance which could affect its ability to achieve its strategic objectives for growth and shareholder returns. The Company’s Board of Directors has overall responsibility for the establishment and oversight of the Company’s risk management framework and reviews the Company’s policies on an ongoing basis. For a comprehensive list of the Company’s risks and uncertainties, see the Company’s most recently filed AIF and Annual MD&A under the heading “Risk Factors”. The 2025 AIF and December 31, 2025 annual MD&A is available under the Company’s SEDAR+ profile at www.sedarplus.ca, and on EDGAR as an exhibit to the Company’s recently filed Form 40-F. Management has not identified any significant new or additional risk factors to those described in the AIF and December 31, 2025 annual MD&A.

 

The Company thoroughly examines the various financial instruments and risks to which it is exposed and assesses the impact and likelihood of those risks. These risks may include credit risk, liquidity risk, currency risk, commodity price risk, and interest rate risk. Where material, these risks are reviewed and monitored by the Board of Directors. Some of these risks and uncertainties are detailed below.

 

Credit risk

 

Credit risk is the risk of financial loss to the Company if a customer or counterparty to a financial instrument fails to meet its contractual obligations and arises principally from the Company’s trade receivables.

 

The Company has concentrate contracts to sell the zinc and lead concentrates produced by all of the Company’s mines and the San Lucas trading business. Concentrate contracts are a common business practice in the mining industry. The terms of the concentrate contracts may require the Company to deliver concentrate that has a value greater than the payment received at the time of delivery, thereby introducing the Company to credit risk of the buyers of concentrates. Should any of these counterparties not honour purchase arrangements, or should any of them become insolvent, the Company may incur losses for products already shipped and be forced to sell its concentrates on the spot market or it may not have a market for its concentrates and therefore its future operating results may be materially adversely impacted. At September 30, 2026, the Company had receivable balances associated with buyers of its concentrates of $38,143 (December 31, 2025 - $20,371). The Company’s concentrate is sold to well-known concentrate buyers.

 

The following financial assets represent the maximum credit risk to the Company:

 

  

September 30, 2026

   December 31, 2025 
    $    $ 
Cash   102,836    44,267 
Marketable securities   21,798    22,462 
Trade and other receivables   56,387    43,348 

 

Management constantly monitors and assesses the credit risk resulting from its concentrate sales, trading counterparties and customers. Other than as set out in the above table, the Company believes it is not exposed to significant credit risk.

 

Liquidity risk

 

Liquidity risk is the risk that the Company will not be able to meet its financial obligations as they come due. The Company manages its liquidity risk by continuously monitoring forecasted and actual cash flows. The Company has in place a rigorous planning and budgeting process to help determine the funds required to support the Company’s normal operating requirements on an ongoing basis and its expansion plans. The Company strives to maintain sufficient liquidity to meet its short-term business requirements, taking into account its anticipated cash flows from operations, its holdings of cash and short-term investments, and its committed loan facilities.

 

- 34 -

 

 

Financial Instruments and Other Instruments (continued)

 

In the normal course of business, the Company enters into contracts that give rise to commitments for future minimum payments. The following tables summarize the remaining contractual maturities of the Company’s financial liabilities and operating and capital commitments on an undiscounted basis:

 

   <1
year
   1 - 2
years
   2 - 5
years
   >5
years
   Total 
   $   $   $   $   $ 
Trade payables and accrued liabilities   35,436    4,984    -    -    40,420 
Consideration payable - CVR & additional payments   10,632    7,384    8,855    3,068    29,939 
Loans payable   42,451    162    -    -    42,613 
Lease payments   12    10    11    -    33 
    88,531    12,540    8,866    3,068    113,005 

 

Currency risk

 

The Company reports its financial statements in USD; however, the Company operates in jurisdictions that utilize other currencies. As a consequence, the financial results of the Company’s operations as reported in USD are subject to changes in the value of the USD relative to local currencies. Since the Company’s sales are denominated in USD and a portion of the Company’s operating costs and capital spending are in local currencies, the Company is negatively impacted by strengthening local currencies relative to the USD and positively impacted by the inverse.

 

The sensitivity of the Company’s net income to changes in the exchange rate between the US dollar and the Bolivian boliviano, the US dollar and the Mexican peso and the US dollar and the Canadian dollar, respectively, would be as follows: a 1% change in the US dollar exchange rate relative to the Bolivian boliviano would change the Company’s net income by approximately $581, a 1% change in the US dollar exchange rate relative to the Mexican peso would change the Company’s net income by approximately $357, and a 1% change in the US dollar exchange rate relative to the Canadian dollar would change the Company’s net income by approximately $(100).

 

The Company’s financial assets and liabilities as at September 30, 2026 are denominated in Canadian dollars, US dollars, Bolivian bolivianos and Mexican pesos and translated to US dollars as follows:

 

   CAD   BOB   USD   MXN   Total 
   $   $   $   $   $ 
Financial assets                         
Cash and cash equivalents   292    11,167    91,248    129    102,836 
Marketable securities   -    -    21,798    -    21,798 
Trade and other receivables   23    4,394    51,727    243    56,387 
    315    15,561    164,773    372    181,021 
                          
Financial liabilities                         
Trade payables and accrued liabilities   421    22,594    13,871    3,534    40,420 
Consideration payable   -    -    24,840    -    24,840 
Loans payable   -    42,613    -    -    42,613 
Other liabilities   -    8,168    4,513    2,229    14,910 
    421    73,375    43,224    5,763    122,783 
Net financial assets (liabilities)   (106)   (57,814)   121,549    (5,391)   58,238 

 

- 35 -

 

 

Financial Instruments and Other Instruments (continued)

 

Interest rate risk

 

The fair values and future cash flows of the Company will fluctuate because of changes in market interest rates generating interest rate risk. The Company monitors its exposure to interest rates and has not entered into any derivative contracts to manage this risk. As at September 30, 2026, the Company’s exposure to interest rate risk on interest bearing liabilities is limited to its consideration payable, debt facilities and lease liabilities. Based on the Company’s interest rate exposure at September 30, 2026, a change of 1% increase or decrease of market interest rate would impact the Company’s income or loss by approximately $426.

 

Price risk

 

Metal price risk is the risk that changes in metal prices will affect the Company’s income or the value of its related financial instruments. The Company derives its revenue from the sale of silver, zinc, lead and copper. The Company’s sales are directly dependent on metal prices that have shown significant volatility and are beyond the Company’s control. Consistent with the Company’s mission to provide equity investors with exposure to changes in precious metal prices, the Company’s current policy is to not hedge the price of precious metal.

 

Outstanding Share Data

 

As at the date of this report, the Company has 92,994,586 common shares issued and outstanding, 1,031,456 common shares issuable under stock options, 479,997 common shares issuable under restricted share units, 296,500 common shares issuable under performance share units, 228,750 common shares issuable under deferred share units.

 

On December 10, 2025 the Company consolidated its issued and outstanding common shares on the basis of one post-consolidated common share for every four pre-consolidated common shares. The number of issued and outstanding shares, options, warrants, DSUs, RSUs and PSUs, and any per share amounts in the consolidated financial statements have been retrospectively restated in notes 10, 13, and 23 for all periods presented unless otherwise stated.

 

Internal Controls over Financial Reporting and Disclosure Controls and Procedures

 

The Company has disclosure controls and procedures in place to provide reasonable assurance that any information required to be disclosed by the Company under securities legislation is recorded, processed, summarized and reported within the applicable time periods and that required information is gathered and communicated to the Company’s management so that decisions can be made about the timely disclosure of that information.

 

The Company’s management is responsible for establishing and maintaining adequate internal controls over financial reporting. Any system of internal controls over financial reporting, no matter how well designed, has inherent limitations. Therefore, even those systems determined to be effective can provide only reasonable assurance with respect to financial statement preparation and presentation.

 

The Company’s management, including the Chief Executive Officer and the Chief Financial Officer, believe that any disclosure controls and procedures or internal controls over financial reporting, no matter how well conceived and operated, can provide only reasonable, not absolute, assurance that the objectives of the control system are met. Further, the design of a control system must reflect the fact that there are resource constraints, and the benefits of controls must be considered relative to their costs. Because of the inherent limitations in all control systems, the Company’s management cannot provide absolute assurance that all control issues and instances of fraud, if any, within the Company have been prevented or detected. These inherent limitations include the realities that judgements in decision-making can be faulty, and that breakdowns can occur because of a simple error or mistake. Additionally, controls can be circumvented by the individual acts of some persons, by collusion of two or more people, or by unauthorized override of the control. The design of any control system is also based in part upon certain assumptions about the likelihood of future events, and there can be no assurance that any design will succeed in achieving its stated goals under all potential future conditions. Accordingly, because of the inherent limitations in a cost- effective control system, misstatements due to error or fraud may occur and not be detected.

 

- 36 -

 

 

Non-GAAP Measures

 

Silver and Zinc Equivalent Production Figures

 

The Company considers silver equivalent (“AgEq”) ounces and zinc equivalent (“ZnEq”) tonnes to be useful production metrics for evaluating its multi-metal production profile but they should be considered only supplemental. These measures are commonly used in the mining industry as reference metrics to facilitate period-over-period comparisons and, where relevant, benchmarking against industry peers. The metrics should be viewed as supplemental to, and not a substitute for the actual metal production volumes disclosed for each metal.

 

AgEq ounces and ZnEq tonnes are calculated by applying conversion factors that normalize the value of each non-reference metal to the selected reference metal. For AgEq ounces, the values of zinc, lead, and copper are converted into silver equivalent ounces. For ZnEq tonnes, the values of silver, lead, and copper are converted into zinc equivalent tonnes. Each conversion factor is derived from the ratio of the in-situ metal value of the contained fine metal to the price of the reference metal used in the equivalency calculation. The denominator used to calculate silver equivalent ounces is the silver price, while the denominator used to calculate zinc equivalent tonnes is the zinc price. This methodology expresses multi-metal production in a common unit of measure. Since the silver price and zinc price are the denominators in each metric, price variations of these metals can significantly affect the result, especially when one metal price changes significantly relative to the other metal prices.

 

The metal prices used in the calculation of AgEq and ZnEq are based on the average quarterly prices quoted on the London Metal Exchange (“LME”).

 

Metal Prices  Silver Ounces   Zinc Tonnes   Lead Tonnes   Copper Tonnes 
   $   $   $   $ 
Average Q3-LME - 2026   62.73    3,830    1,857    14,121 
Average Q2-LME - 2026   73.44    3,463    1,955    13,324 
Average Q1-LME - 2026   84.39    3,243    1,931    12,852 
Average Q4-LME - 2025   54.83    3,165    1,971    11,100 
Average Q1-LME - 2025   31.91    2,838    1,970    9,346 

 

The methods used by the Company to calculate these equivalencies may differ from those used by other companies reporting similar metrics and may not be directly comparable. These measures are intended to provide additional information and should not be considered in isolation or as a substitute for performance measures prepared in accordance with IFRS.

 

Costs per tonne milled, silver ounce sold or zinc tonne sold

 

The Company has included certain non-GAAP performance measures throughout this MD&A including cash cost per tonne milled, cash cost per silver ounce sold, cash cost per zinc tonne sold, all-in sustaining cost (“AISC”) per silver ounce sold, all-in sustaining cost (“AISC”) per zinc tonne sold, average realized price per silver ounce sold, average realized price per zinc tonne sold, mining/ore processing margin per silver ounce sold, mining/ore processing margin per zinc tonne sold, and adjusted EBITDA each as defined in this section.

 

These performance measures are employed by the Company to measure its operating and financial performance internally, to assist in business decision-making, and provide key performance information to senior management. The Company believes that, in addition to conventional measures prepared in accordance with IFRS, certain investors and other stakeholders also use these non-GAAP measures as information to evaluate the Company’s operating and financial performance. As there are no standardized methods of calculating these non-GAAP measures, the Company’s methods may differ from those used by others and, accordingly, the Company’s use of these measures may not be directly comparable to similarly titled measures used by others. Accordingly, these non-GAAP measures are intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS.

 

- 37 -

 

 

Non-GAAP Measures (continued)

 

Cash cost of production per tonne milled, cash cost per silver ounce and zinc tonne sold, all-in sustaining cost (“AISC”) per silver ounce and zinc tonne sold

 

The non-GAAP measures of cash cost per silver ounce sold and cash cost per zinc tonne sold and cash cost of production per tonne milled are used by the Company to manage and evaluate operating performance at respective mining operations and are widely reported in the silver mining industry as benchmarks for performance, but do not have a standardized meaning. cash costs are calculated based on the cash operating costs at the respective mining operations and, in the case of cash cost per silver ounce sold and cash cost per zinc tonne sold, also include the third party concentrate treatment, smelting and refining cost.

 

Management of the Company believes that the Company’s ability to control the cash cost per silver ounce and zinc tonne sold and cash cost of production per tonne milled are three of its key performance drivers impacting both the Company’s financial condition and results of operations. Having a low cash cost of production per tonne milled, when taken in connection with effective management of mining dilution, will improve the cash cost per silver ounce and zinc tonne produced. Having a low-cost base per silver ounce and zinc tonne of production allows the Company to continue operating during times of declining commodity prices and provides more flexibility in responding to changing market conditions. In addition, low-cost operations offer a better opportunity to generate positive cash-flows, which improves the Company’s financial condition. The Company believes these measures provide investors and analysts with useful information about the Company’s underlying cash costs of operations and are relevant metrics used to understand the Company’s operating profitability and ability to generate cash-flow.

 

To facilitate a better understanding of these measures as calculated by the Company, the following tables provides a detailed reconciliation between the cash cost per silver ounce sold, cash cost per zinc tonne sold and the cash cost of production per tonne milled, and the Company’s operating expenses as reported in the Company’s consolidated statements of income (loss) and comprehensive income (loss) contained in the respective financial statements for the referenced periods.

 

The Company’s operations are poly-metallic whereby each tonne of ore milled generates primarily payable ounces of silver and tonnes of zinc but also generates payable tonnes of lead and copper. The combined revenues of lead and copper are incidental to our primary metal production of silver and zinc because they generate less than 10% of total revenues. Lead and copper concentrate is produced primarily to obtain the silver contained within so the Company has adopted the practice of calculating the net cost of producing an ounce of silver, after deducting revenues gained from incidental by-product production of lead and copper. This performance measurement has been commonly used in the mining industry for many years and was developed as a relatively simple way of comparing the net production costs of the primary metal for a specific period against the prevailing market price of that metal.

 

The Company’s primary payable metals are silver ounces and zinc tonnes, the revenue generated by each metal varies depending on prevailing metal prices but because each metal generates greater than 30% of the total revenues, the Company has concluded that reporting costs as co-products by silver ounces sold and zinc tonnes sold is the most appropriate way to assess the performance of its operations. The total tonnes of ore milled in the period generates silver and zinc payable metals, the ratio of payable silver and zinc produced from each tonne milled is used to allocate each period’s production costs between silver ounces sold and zinc tonnes sold. The Company calculates the tonnes milled to payable silver and zinc for each operation and for each period separately in order to most appropriately allocate costs between each primary metal for the purposes of determining the cash cost per silver ounce and zinc tonne sold.

 

AISC is a non-GAAP measure and was calculated based on guidance provided by the World Gold Council (“WGC”) in September 2013. WGC is not a regulatory industry organization and does not have the authority to develop accounting standards for disclosure requirements. Other mining companies may calculate AISC differently as a result of differences in underlying accounting principles and policies applied, as well as differences in definitions of sustaining versus development capital expenditures.

 

- 38 -

 

 

Non-GAAP Measures (continued)

 

AISC is a more comprehensive measure than cash cost per ounce for the Company’s operating performance by providing greater visibility, comparability and representation of the total costs associated with producing silver from its mining operations.

 

Consolidated AISC includes total production cash costs incurred at the Company’s mining operations, which forms the basis of the Company’s total cash costs. Additionally, the Company includes sustaining capital expenditures, corporate general and administrative expense, sustaining share-based payments, and reclamation cost accretion. The Company defines sustaining capital expenditures as, “costs incurred to sustain and maintain existing assets at current productive capacity and constant planned levels of productive output without resulting in an increase in the life of assets, future earnings, or improvements in recovery or grade. Sustaining capital includes costs required to improve/enhance assets to minimum standards for reliability, environmental or safety requirements.”

 

The Company believes that the AISC measure represents the total sustainable costs of producing silver and zinc from current operations and provides the Company and other stakeholders of the Company with additional information of the Company’s operational performance and ability to generate cash flows. As the measure seeks to reflect the full cost of silver and zinc production from current operations, new project capital and expansionary capital at current operations are not included. Certain other cash expenditures, including tax payments, dividends and financing costs are also not included.

 

- 39 -

 

 

Cash cost of production per tonne milled, cash cost per silver ounce or zinc tonne sold, all-in sustaining cost (“AISC”) per silver ounce or zinc tonne sold - Mining operations

 

Cost of sales includes transportation and other selling costs, royalties and inventory changes which are excluded from the calculation of cash costs per silver ounce or zinc tonne sold, all-in sustaining cost (“AISC”) per silver ounce or zinc tonne sold, and cash cost of production per tonne milled. The following tables provide a detailed reconciliation of these measures to our cost of sales, as reported in the condensed interim consolidated financial statements.

 

Consolidated - Cash costs per ounce and tonne – Mining operations

 

   Three months ended September 30, 2026 
   Silver   Zinc   Total 
Cost of sales   27,911    27,432    55,343 
Transportation and other selling cost   (4,095)   (3,896)   (7,991)
Royalty   (3,227)   (3,148)   (6,374)
Inventory change   (335)   (842)   (1,177)
Cash cost of production (A)   20,253    19,546    39,800 
Cost of sales   27,911    27,432    55,343 
Concentrate treatment, smelting and refining cost   420    5,051    5,472 
By-product lead revenue   (5,991)   -    (5,991)
By-product copper revenue   (5,573)   -    (5,573)
Cash cost of silver ounce or zinc tonne sold (B)   16,767    32,483    49,250 
Sustaining capital expenditures   5,587    5,559    11,146 
General and administrative expenses   3,263    3,047    6,310 
Accretion of decommissioning and restoration provision   380    345    725 
All-in sustaining cost (C)   25,997    41,433    67,431 
Material processed (tonnes milled) (D)             416,187 
Silver ounces or zinc tonnes sold (E)   1,317,704    17,191      
Cash cost per silver ounce or zinc tonne sold (B/E)   12.72    1,890      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   19.73    2,410      
Cash cost of production per tonne milled (A/D)             95.63 

 

   Three months ended September 30, 2025 
   Silver   Zinc   Total 
Cost of sales   21,334    18,808    40,142 
Transportation and other selling cost   (2,651)   (2,287)   (4,938)
Royalty   (1,378)   (1,134)   (2,512)
Inventory change   (1,683)   (1,508)   (3,191)
Cash cost of production (A)   15,623    13,878    29,501 
Cost of sales   21,334    18,808    40,142 
Concentrate treatment, smelting and refining cost   3,030    2,891    5,921 
By-product lead revenue   (3,258)   -    (3,258)
By-product copper revenue   (2,764)   -    (2,764)
Cash cost of silver ounce or zinc tonne sold (B)   18,342    21,699    40,041 
Sustaining capital expenditures   4,647    3,937    8,584 
General and administrative expenses   2,983    2,664    5,647 
Accretion of decommissioning and restoration provision   453    381    834 
All-in sustaining cost (C)   26,425    28,681    55,106 
Material processed (tonnes milled) (D)             386,035 
Silver ounces or zinc tonnes sold (E)   900,319    12,765      
Cash cost per silver ounce or zinc tonne sold (B/E)   20.37    1,700      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   29.35    2,247      
Cash cost of production per tonne milled (A/D)             76.42 

 

- 40 -

 

 

Non-GAAP Measures (continued)

 

Consolidated - Cash costs per ounce or tonne – Mining operations

 

   Nine months ended September 30, 2026 
   Silver   Zinc   Total 
Cost of sales   66,720    71,152    137,872 
Transportation and other selling cost   (9,046)   (9,791)   (18,837)
Royalty   (6,874)   (7,688)   (14,562)
Inventory change   2,567    2,324    4,891 
Cash cost of production (A)   53,367    55,997    109,364 
Cost of sales   66,720    71,152    137,872 
Concentrate treatment, smelting and refining cost   7,350    12,355    19,705 
By-product lead revenue   (10,786)   -    (10,786)
By-product copper revenue   (12,757)   -    (12,757)
Cash cost of silver ounce or zinc tonne sold (B)   50,527    83,507    134,034 
Sustaining capital expenditures   14,458    15,637    30,095 
General and administrative expenses   8,276    8,485    16,761 
Accretion of decommissioning and restoration provision   1,359    1,501    2,860 
All-in sustaining cost (C)   74,620    109,131    183,750 
Material processed (tonnes milled) (D)             1,215,729 
Silver ounces or zinc tonnes sold (E)   3,083,623    45,636      
Cash cost per silver ounce or zinc tonne sold (B/E)   16.39    1,830      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   24.20    2,391      
Cash cost of production per tonne milled (A/D)             89.96 

 

   Nine months ended September 30, 2025 
   Silver   Zinc   Total 
Cost of sales   58,604    50,755    109,359 
Transportation and other selling cost   (8,260)   (6,811)   (15,071)
Royalty   (3,306)   (2,626)   (5,932)
Inventory change   (3,283)   (2,861)   (6,144)
Cash cost of production (A)   43,754    38,458    82,212 
Cost of sales   58,604    50,755    109,359 
Concentrate treatment, smelting and refining cost   11,777    10,634    22,411 
By-product lead revenue   (11,547)   -    (11,547)
By-product copper revenue   (7,111)   -    (7,111)
Cash cost of silver ounce or zinc tonne sold (B)   51,723    61,389    113,112 
Sustaining capital expenditures   11,416    10,003    21,419 
General and administrative expenses   7,812    6,767    14,579 
Accretion of decommissioning and restoration provision   1,008    816    1,824 
All-in sustaining cost (C)   71,958    78,976    150,934 
Material processed (tonnes milled) (D)             1,157,003 
Silver ounces or zinc tonnes sold (E)   3,471,906    38,221      
Cash cost per silver ounce or zinc tonne sold (B/E)   14.90    1,606      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   20.73    2,066      
Cash cost of production per tonne milled (A/D)             71.06 

 

- 41 -

 

 

Non-GAAP Measures (continued)

 

Bolivar Mine (1) - Cash cost per silver ounce or zinc tonne sold, all-in sustaining cost (“AISC”) per silver ounce or zinc tonne sold, and cash cost of production per tonne milled

 

   Three months ended September 30, 2026 
   Silver   Zinc   Total 
Cost of sales   8,042    9,829    17,872 
Transportation and other selling cost   (1,089)   (1,332)   (2,421)
Royalty   (1,184)   (1,447)   (2,631)
Inventory change   (1,446)   (1,768)   (3,214)
Cash cost of production (A)   4,323    5,283    9,606 
Cost of sales   8,042    9,829    17,872 
Concentrate treatment, smelting and refining cost   24    926    950 
By-product lead revenue   (306)   -    (306)
By-product copper revenue   -    -    - 
Cash cost of silver ounce or zinc tonne sold (B)   7,761    10,755    18,516 
Sustaining capital expenditures   1,885    2,303    4,188 
General and administrative expenses   449    548    997 
Accretion of decommissioning and restoration provision   82    100    182 
All-in sustaining cost (C)   10,176    13,707    23,883 
Material processed (tonnes milled) (D)             76,724 
Silver ounces or zinc tonnes sold (E)   465,445    5,134      
Cash cost per silver ounce or zinc tonne sold (B/E)   16.67    2,095      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   21.86    2,670      
Cash cost of production per tonne milled (A/D)             125.20 

 

   Three months ended September 30, 2025 
   Silver   Zinc   Total 
Cost of sales   5,374    3,734    9,108 
Transportation and other selling cost   (609)   (423)   (1,032)
Royalty   (378)   (262)   (640)
Inventory change   (93)   (64)   (157)
Cash cost of production (A)   4,295    2,984    7,279 
Cost of sales   5,374    3,734    9,108 
Concentrate treatment, smelting and refining cost   357    248    605 
By-product lead revenue   (142)   -    (142)
By-product copper revenue   -    -    - 
Cash cost of silver ounce or zinc tonne sold (B)   5,589    3,982    9,571 
Sustaining capital expenditures   2,112    1,467    3,579 
General and administrative expenses   510    354    864 
Accretion of decommissioning and restoration provision   97    68    165 
All-in sustaining cost (C)   8,307    5,872    14,179 
Material processed (tonnes milled) (D)             52,023 
Silver ounces or zinc tonnes sold (E)   144,016    2,400      
Cash cost per silver ounce or zinc tonne sold (B/E)   38.81    1,659      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   57.68    2,447      
Cash cost of production per tonne milled (A/D)             139.92 

 

Note:

 

(1) Information for Bolivar and Porco is presented at 100% and financial information will not tie to the consolidated financial statements as the Company records 45% of Bolivar and Porco.

 

- 42 -

 

 

Non-GAAP Measures (continued)

 

Bolivar Mine (1) - Cash cost per silver ounce or zinc tonne sold, all-in sustaining cost (“AISC”) per silver ounce or zinc tonne sold, and cash cost of production per tonne milled

 

   Nine months ended September 30, 2026 
   Silver   Zinc   Total 
Cost of sales   16,719    20,595    37,313 
Transportation and other selling cost   (2,317)   (2,812)   (5,129)
Royalty   (2,695)   (3,303)   (5,998)
Inventory change   80    (202)   (122)
Cash cost of production (A)   11,787    14,277    26,064 
Cost of sales   16,719    20,595    37,313 
Concentrate treatment, smelting and refining cost   805    1,885    2,690 
By-product lead revenue   (837)   -    (837)
By-product copper revenue   -    -    - 
Cash cost of silver ounce or zinc tonne sold (B)   16,687    22,479    39,166 
Sustaining capital expenditures   5,111    6,210    11,321 
General and administrative expenses   1,079    1,311    2,390 
Accretion of decommissioning and restoration provision   319    387    706 
All-in sustaining cost (C)   23,196    30,387    53,584 
Material processed (tonnes milled) (D)             213,849 
Silver ounces or zinc tonnes sold (E)   873,156    11,258      
Cash cost per silver ounce or zinc tonne sold (B/E)   19.11    1,997      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   26.57    2,699      
Cash cost of production per tonne milled (A/D)             121.88 

 

   Nine months ended September 30, 2025 
   Silver   Zinc   Total 
Cost of sales   14,378    10,279    24,657 
Transportation and other selling cost   (2,281)   (1,660)   (3,941)
Royalty   (1,144)   (828)   (1,972)
Inventory change   (700)   (498)   (1,198)
Cash cost of production (A)   10,254    7,292    17,546 
Cost of sales   14,378    10,279    24,657 
Concentrate treatment, smelting and refining cost   2,140    1,578    3,718 
By-product lead revenue   (1,001)   -    (1,001)
By-product copper revenue   -    -    - 
Cash cost of silver ounce or zinc tonne sold (B)   15,517    11,857    27,374 
Sustaining capital expenditures   3,597    2,584    6,181 
General and administrative expenses   1,207    861    2,068 
Accretion of decommissioning and restoration provision   216    154    370 
All-in sustaining cost (C)   20,537    15,456    35,993 
Material processed (tonnes milled) (D)             169,181 
Silver ounces or zinc tonnes sold (E)   1,024,052    8,865      
Cash cost per silver ounce or zinc tonne sold (B/E)   15.15    1,338      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   20.05    1,744      
Cash cost of production per tonne milled (A/D)             103.71 

 

Note:

 

(1) Information for Bolivar and Porco is presented at 100% and financial information will not tie to the consolidated financial statements as the Company records 45% of Bolivar and Porco.

 

- 43 -

 

 

Non-GAAP Measures (continued)

 

Porco Mine (1) - Cash cost per silver ounce or zinc tonne sold, all-in sustaining cost (“AISC”) per silver ounce or zinc tonne sold, and cash cost of production per tonne milled

 

   Three months ended September 30, 2026 
   Silver   Zinc   Total 
Cost of sales   4,161    3,139    7,300 
Transportation and other selling cost   (885)   (668)   (1,553)
Royalty   (558)   (421)   (979)
Inventory change   116    88    204 
Cash cost of production (A)   2,834    2,138    4,972 
Cost of sales   4,161    3,139    7,300 
Concentrate treatment, smelting and refining cost   6    466    472 
By-product lead revenue   (141)   -    (141)
By-product copper revenue   -    -    - 
Cash cost of silver ounce or zinc tonne sold (B)   4,026    3,605    7,631 
Sustaining capital expenditures   307    231    538 
General and administrative expenses   485    366    851 
Accretion of decommissioning and restoration provision   170    128    299 
All-in sustaining cost (C)   4,988    4,331    9,319 
Material processed (tonnes milled) (D)             48,597 
Silver ounces or zinc tonnes sold (E)   113,600    2,834      
Cash cost per silver ounce or zinc tonne sold (B/E)   35.44    1,272      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   43.91    1,528      
Cash cost of production per tonne milled (A/D)             102.31 

 

   Three months ended September 30, 2025 
   Silver   Zinc   Total 
Cost of sales   3,663    2,997    6,660 
Transportation and other selling cost   (595)   (486)   (1,081)
Royalty   (359)   (294)   (653)
Inventory change   (268)   (220)   (488)
Cash cost of production (A)   2,441    1,997    4,438 
Cost of sales   3,663    2,997    6,660 
Concentrate treatment, smelting and refining cost   309    253    562 
By-product lead revenue   (173)   -    (173)
By-product copper revenue   -    -    - 
Cash cost of silver ounce or zinc tonne sold (B)   3,799    3,250    7,049 
Sustaining capital expenditures   447    365    812 
General and administrative expenses   271    222    493 
Accretion of decommissioning and restoration provision   156    127    283 
All-in sustaining cost (C)   4,673    3,965    8,637 
Material processed (tonnes milled) (D)             49,161 
Silver ounces or zinc tonnes sold (E)   105,310    2,318      
Cash cost per silver ounce or zinc tonne sold (B/E)   36.08    1,402      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   44.37    1,710      
Cash cost of production per tonne milled (A/D)             90.27 

 

Note:

 

(1) Information for Bolivar and Porco is presented at 100% and financial information will not tie to the consolidated financial statements as the Company records 45% of Bolivar and Porco.

 

- 44 -

 

 

Non-GAAP Measures (continued)

 

Porco Mine (1) - Cash cost per silver ounce or zinc tonne sold, all-in sustaining cost (“AISC”) per silver ounce or zinc tonne sold, and cash cost of production per tonne milled

 

   Nine months ended September 30, 2026 
   Silver   Zinc   Total 
Cost of sales   9,624    9,318    18,942 
Transportation and other selling cost   (1,946)   (1,869)   (3,815)
Royalty   (1,265)   (1,216)   (2,482)
Inventory change   1,122    1,201    2,323 
Cash cost of production (A)   7,535    7,433    14,968 
Cost of sales   9,624    9,318    18,942 
Concentrate treatment, smelting and refining cost   677    1,224    1,901 
By-product lead revenue   (200)   -    (200)
By-product copper revenue   -    -    - 
Cash cost of silver ounce or zinc tonne sold (B)   10,101    10,541    20,642 
Sustaining capital expenditures   763    744    1,507 
General and administrative expenses   1,041    992    2,033 
Accretion of decommissioning and restoration provision   575    583    1,158 
All-in sustaining cost (C)   12,480    12,861    25,340 
Material processed (tonnes milled) (D)             146,089 
Silver ounces or zinc tonnes sold (E)   263,503    8,586      
Cash cost per silver ounce or zinc tonne sold (B/E)   38.33    1,228      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   47.36    1,498      
Cash cost of production per tonne milled (A/D)             102.46 

 

   Nine months ended September 30, 2025 
   Silver   Zinc   Total 
Cost of sales   9,052    6,721    15,773 
Transportation and other selling cost   (1,765)   (1,294)   (3,059)
Royalty   (724)   (544)   (1,268)
Inventory change   (263)   (204)   (467)
Cash cost of production (A)   6,301    4,678    10,979 
Cost of sales   9,052    6,721    15,773 
Concentrate treatment, smelting and refining cost   1,369    982    2,350 
By-product lead revenue   (993)   -    (993)
By-product copper revenue   -    -    - 
Cash cost of silver ounce or zinc tonne sold (B)   9,428    7,702    17,130 
Sustaining capital expenditures   784    586    1,370 
General and administrative expenses   754    557    1,311 
Accretion of decommissioning and restoration provision   363    270    633 
All-in sustaining cost (C)   11,328    9,116    20,444 
Material processed (tonnes milled) (D)             145,815 
Silver ounces or zinc tonnes sold (E)   353,098    6,466      
Cash cost per silver ounce or zinc tonne sold (B/E)   26.70    1,191      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   32.08    1,410      
Cash cost of production per tonne milled (A/D)             75.29 

 

Note:

 

(1) Information for Bolivar and Porco is presented at 100% and financial information will not tie to the consolidated financial statements as the Company records 45% of Bolivar and Porco.

 

- 45 -

 

 

Non-GAAP Measures (continued)

 

Caballo Blanco Group - Cash cost per silver ounce or zinc tonne sold, all-in sustaining cost (“AISC”) per silver ounce or zinc tonne sold, and cash cost of production per tonne milled

 

   Three months ended September 30, 2026 
   Silver   Zinc   Total 
Cost of sales   5,770    4,915    10,685 
Transportation and other selling cost   (1,294)   (1,103)   (2,397)
Royalty   (1,345)   (1,146)   (2,491)
Inventory change   1,075    915    1,990 
Cash cost of production (A)   4,205    3,582    7,787 
Cost of sales   5,770    4,915    10,685 
Concentrate treatment, smelting and refining cost   25    693    718 
By-product lead revenue   (2,171)   -    (2,171)
By-product copper revenue   -    -    - 
Cash cost of silver ounce or zinc tonne sold (B)   3,624    5,608    9,232 
Sustaining capital expenditures   2,189    1,864    4,053 
General and administrative expenses   583    497    1,080 
Accretion of decommissioning and restoration provision   56    48    104 
All-in sustaining cost (C)   6,452    8,017    14,469 
Material processed (tonnes milled) (D)             68,442 
Silver ounces or zinc tonnes sold (E)   338,120    4,545      
Cash cost per silver ounce or zinc tonne sold (B/E)   10.72    1,234      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   19.08    1,764      
Cash cost of production per tonne milled (A/D)             113.77 

 

   Three months ended September 30, 2025 
   Silver   Zinc   Total 
Cost of sales   4,688    4,158    8,846 
Transportation and other selling cost   (835)   (740)   (1,575)
Royalty   (582)   (517)   (1,099)
Inventory change   (981)   (870)   (1,851)
Cash cost of production (A)   2,290    2,031    4,321 
Cost of sales   4,688    4,158    8,846 
Concentrate treatment, smelting and refining cost   461    408    869 
By-product lead revenue   (1,165)   -    (1,165)
By-product copper revenue   -    -    - 
Cash cost of silver ounce or zinc tonne sold (B)   3,984    4,566    8,550 
Sustaining capital expenditures   460    407    867 
General and administrative expenses   532    472    1,004 
Accretion of decommissioning and restoration provision   140    124    264 
All-in sustaining cost (C)   5,116    5,570    10,685 
Material processed (tonnes milled) (D)             62,221 
Silver ounces or zinc tonnes sold (E)   289,115    3,527      
Cash cost per silver ounce or zinc tonne sold (B/E)   13.78    1,295      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   17.69    1,579      
Cash cost of production per tonne milled (A/D)             69.45 

 

- 46 -

 

 

Non-GAAP Measures (continued)

 

Caballo Blanco Group - Cash cost per silver ounce or zinc tonne sold, all-in sustaining cost (“AISC”) per silver ounce or zinc tonne sold, and cash cost of production per tonne milled

 

   Nine months ended September 30, 2026 
   Silver   Zinc   Total 
Cost of sales   12,522    14,784    27,306 
Transportation and other selling cost   (2,534)   (2,963)   (5,498)
Royalty   (2,493)   (2,767)   (5,260)
Inventory change   1,166    1,110    2,276 
Cash cost of production (A)   8,662    10,163    18,825 
Cost of sales   12,522    14,784    27,306 
Concentrate treatment, smelting and refining cost   788    1,812    2,600 
By-product lead revenue   (3,971)   -    (3,971)
By-product copper revenue   -    -    - 
Cash cost of silver ounce or zinc tonne sold (B)   9,339    16,596    25,935 
Sustaining capital expenditures   3,900    4,362    8,262 
General and administrative expenses   1,185    1,374    2,560 
Accretion of decommissioning and restoration provision   250    327    577 
All-in sustaining cost (C)   14,675    22,659    37,334 
Material processed (tonnes milled) (D)             187,438 
Silver ounces or zinc tonnes sold (E)   754,247    12,389      
Cash cost per silver ounce or zinc tonne sold (B/E)   12.38    1,340      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   19.46    1,829      
Cash cost of production per tonne milled (A/D)             100.43 

 

   Nine months ended September 30, 2025 
   Silver   Zinc   Total 
Cost of sales   10,477    8,759    19,236 
Transportation and other selling cost   (2,443)   (2,061)   (4,504)
Royalty   (1,300)   (1,112)   (2,412)
Inventory change   (1,058)   (875)   (1,933)
Cash cost of production (A)   5,676    4,711    10,387 
Cost of sales   10,477    8,759    19,236 
Concentrate treatment, smelting and refining cost   1,884    1,600    3,484 
By-product lead revenue   (2,988)   -    (2,988)
By-product copper revenue   -    -    - 
Cash cost of silver ounce or zinc tonne sold (B)   9,373    10,359    19,732 
Sustaining capital expenditures   1,284    962    2,246 
General and administrative expenses   1,262    1,072    2,334 
Accretion of decommissioning and restoration provision   248    207    455 
All-in sustaining cost (C)   12,167    12,600    24,767 
Material processed (tonnes milled) (D)             171,643 
Silver ounces or zinc tonnes sold (E)   903,554    9,545      
Cash cost per silver ounce or zinc tonne sold (B/E)   10.37    1,085      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   13.47    1,320      
Cash cost of production per tonne milled (A/D)             60.52 

 

- 47 -

 

 

Non-GAAP Measures (continued)

 

Zimapan Mine - Cash cost per silver ounce or zinc tonne sold, all-in sustaining cost (“AISC”) per silver ounce or zinc tonne sold, and cash cost of production per tonne milled

 

   Three months ended September 30, 2026 
   Silver   Zinc   Total 
Cost of sales   9,938    9,548    19,486 
Transportation and other selling cost   (826)   (794)   (1,620)
Royalty   (139)   (134)   (273)
Inventory change   (80)   (77)   (157)
Cash cost of production (A)   8,892    8,543    17,435 
Cost of sales   9,938    9,548    19,486 
Concentrate treatment, smelting and refining cost   365    2,966    3,332 
By-product lead revenue   (3,373)   -    (3,373)
By-product copper revenue   (5,573)   -    (5,573)
Cash cost of silver ounce or zinc tonne sold (B)   1,356    12,514    13,871 
Sustaining capital expenditures   1,207    1,160    2,367 
General and administrative expenses   616    592    1,208 
Accretion of decommissioning and restoration provision   71    69    140 
All-in sustaining cost (C)   3,251    14,335    17,586 
Material processed (tonnes milled) (D)             222,424 
Silver ounces or zinc tonnes sold (E)   400,539    4,678      
Cash cost per silver ounce or zinc tonne sold (B/E)   3.39    2,675      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   8.12    3,064      
Cash cost of production per tonne milled (A/D)             78.39 

 

   Three Months Ended September 30, 2025 
   Silver   Zinc   Total 
Cost of sales   7,609    7,919    15,528 
Transportation and other selling cost   (613)   (638)   (1,250)
Royalty   (59)   (61)   (120)
Inventory change   (341)   (354)   (695)
Cash cost of production (A)   6,597    6,866    13,463 
Cost of sales   7,609    7,919    15,528 
Concentrate treatment, smelting and refining cost   1,904    1,981    3,885 
By-product lead revenue   (1,778)   -    (1,778)
By-product copper revenue   (2,764)   -    (2,764)
Cash cost of silver ounce or zinc tonne sold (B)   4,970    9,901    14,871 
Sustaining capital expenditures   1,630    1,696    3,326 
General and administrative expenses   631    656    1,287 
Accretion of decommissioning and restoration provision   60    62    122 
All-in sustaining cost (C)   7,291    12,315    19,606 
Material processed (tonnes milled) (D)             222,629 
Silver ounces or zinc tonnes sold (E)   361,878    4,520      
Cash cost per silver ounce or zinc tonne sold (B/E)   13.73    2,190      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   20.15    2,725      
Cash cost of production per tonne milled (A/D)             60.47 

 

- 48 -

 

 

Non-GAAP Measures (continued)

 

Zimapan Mine - Cash cost per silver ounce or zinc tonne sold, all-in sustaining cost (“AISC”) per silver ounce or zinc tonne sold, and cash cost of production per tonne milled

 

   Nine months ended September 30, 2026 
   Silver   Zinc   Total 
Cost of sales   27,855    26,456    54,311 
Transportation and other selling cost   (2,249)   (2,146)   (4,395)
Royalty   (421)   (402)   (823)
Inventory change   199    215    414 
Cash cost of production (A)   25,384    24,123    49,507 
Cost of sales   27,855    26,456    54,311 
Concentrate treatment, smelting and refining cost   5,080    7,435    12,515 
By-product lead revenue   (5,778)   -    (5,778)
By-product copper revenue   (12,757)   -    (12,757)
Cash cost of silver ounce or zinc tonne sold (B)   14,400    33,891    48,291 
Sustaining capital expenditures   4,684    4,321    9,005 
General and administrative expenses   1,905    1,770    3,675 
Accretion of decommissioning and restoration provision   215    204    419 
All-in sustaining cost (C)   21,205    40,185    61,390 
Material processed (tonnes milled) (D)             668,353 
Silver ounces or zinc tonnes sold (E)   1,192,717    13,403      
Cash cost per silver ounce or zinc tonne sold (B/E)   12.07    2,529      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   17.78    2,998      
Cash cost of production per tonne milled (A/D)             74.07 

 

   Nine months ended September 30, 2025 
   Silver   Zinc   Total 
Cost of sales   24,697    24,996    49,693 
Transportation and other selling cost   (1,772)   (1,795)   (3,567)
Royalty   (138)   (142)   (280)
Inventory change   (1,262)   (1,284)   (2,546)
Cash cost of production (A)   21,524    21,776    43,300 
Cost of sales   24,697    24,996    49,693 
Concentrate treatment, smelting and refining cost   6,385    6,474    12,859 
By-product lead revenue   (6,565)   -    (6,565)
By-product copper revenue   (7,111)   -    (7,111)
Cash cost of silver ounce or zinc tonne sold (B)   17,405    31,471    48,876 
Sustaining capital expenditures   5,751    5,871    11,622 
General and administrative expenses   1,845    1,886    3,731 
Accretion of decommissioning and restoration provision   182    184    366 
All-in sustaining cost (C)   25,182    39,413    64,595 
Material processed (tonnes milled) (D)             670,364 
Silver ounces or zinc tonnes sold (E)   1,191,202    13,345      
Cash cost per silver ounce or zinc tonne sold (B/E)   14.61    2,358      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   21.14    2,953      
Cash cost of production per tonne milled (A/D)             64.59 

 

- 49 -

 

 

Non-GAAP Measures (continued)

 

Average realized price per silver ounce and zinc tonne sold – Mining operations

 

Revenues are presented as the sum of invoiced revenues related to delivered shipments of zinc, lead and copper concentrates, after having deducted treatment, smelting and refining charges made by the customer. The average realized price per silver ounce and zinc tonne sold is an analysis of the gross revenues prior to the treatment, smelting, refining and metallurgical deduction charges which is then divided by silver ounces and zinc tonnes sold. The following tables show a detailed reconciliation of average realized price per silver ounce or zinc tonne sold to our revenues as reported in the condensed interim consolidated financial statements.

 

Consolidated (1) Average realized price per silver ounce or zinc tonne sold – Mining operations

 

   Three months ended September 30, 2026 
   Silver   Zinc 
Revenues   70,838    52,594 
Add back: Treatment, smelting and refining charges   420    5,051 
Add back: Metallurgical deductions   14,026    11,310 
Gross Revenues   85,284    68,956 
Silver Ounces or Zinc Tonnes Sold   1,317,704    17,191 
Average realized price per silver ounce or zinc tonne sold (2)   64.72    4,011 
Average market price per ounce of silver / zinc tonne   62.74    3,825 

 

   Three months ended September 30, 2025 
   Silver   Zinc 
Revenues   27,545    33,210 
Add back: Treatment, smelting and refining charges   2,906    2,762 
Add back: Metallurgical deductions   6,592    6,612 
Gross Revenues   37,044    42,584 
Silver Ounces or Zinc Tonnes Sold   900,319    12,765 
Average realized price per silver ounce or zinc tonne sold (2)   41.14    3,336 
Average market price per ounce of silver / zinc tonne   39.40    2,824 

 

   Nine months ended September 30, 2026 
   Silver   Zinc 
Revenues   175,941    123,541 
Add back: Treatment, smelting and refining charges   2,265    14,149 
Add back: Metallurgical deductions   41,994    26,654 
Gross Revenues   220,199    164,344 
Silver Ounces or Zinc Tonnes Sold   3,083,623    45,636 
Average realized price per silver ounce or zinc tonne sold (2)   71.41    3,601 
Average market price per ounce of silver / zinc tonne   73.09    3,514 

 

   Nine months ended September 30, 2025 
   Silver   Zinc 
Revenues   91,267    92,780 
Add back: Treatment, smelting and refining charges   11,403    10,265 
Add back: Metallurgical deductions   19,561    19,373 
Gross Revenues   122,231    122,418 
Silver Ounces or Zinc Tonnes Sold   3,471,906    38,221 
Average realized price per silver ounce or zinc tonne sold (2)   35.21    3,203 
Average market price per ounce of silver / zinc tonne   35.05    2,790 

 

(1) Information for Bolivar and Porco is presented at 100% and financial information will not tie to the consolidated financial statements as the Company records 45% of Bolivar and Porco.
(2) Average realized price per ounce of silver ounce or zinc tonne sold in each reporting period is affected by mark-to-market adjustments and final settlements on concentrate shipments in prior periods. Concentrates sold to third-party smelters are provisionally priced and the price is not settled until a predetermined future date, typically one to four months after delivery to the customer, based on the market price at that time.

 

- 50 -

 

 

Non-GAAP Measures (continued)

 

Bolivar (1) Average realized price per silver ounce or zinc tonne sold

 

   Three months ended September 30, 2026 
   Silver   Zinc 
Revenues   24,498    16,705 
Add back: Treatment, smelting and refining charges   24    926 
Add back: Metallurgical deductions   5,912    3,310 
Gross Revenues   30,434    20,941 
Silver Ounces or Zinc Tonnes Sold   465,445    5,134 
Average realized price per silver ounce or zinc tonne sold (2)   65.39    4,079 
Average market price per ounce of silver / zinc tonne   62.74    3,825 

 

   Three months ended September 30, 2025 
   Silver   Zinc 
Revenues   3,965    6,818 
Add back: Treatment, smelting and refining charges   357    248 
Add back: Metallurgical deductions   1,551    1,347 
Gross Revenues   5,873    8,413 
Silver Ounces or Zinc Tonnes Sold   144,016    2,400 
Average realized price per silver ounce or zinc tonne sold (2)   40.78    3,506 
Average market price per ounce of silver / zinc tonne   39.4    2,824 

 

   Nine months ended September 30, 2026 
   Silver   Zinc 
Revenues   49,601    32,181 
Add back: Treatment, smelting and refining charges   71    2,218 
Add back: Metallurgical deductions   15,542    6,671 
Gross Revenues   65,214    41,070 
Silver Ounces or Zinc Tonnes Sold   873,156    11,258 
Average realized price per silver ounce or zinc tonne sold (2)   74.69    3,648 
Average market price per ounce of silver / zinc tonne   73.09    3,514 

 

   Nine months ended September 30, 2025 
   Silver   Zinc 
Revenues   25,927    23,545 
Add back: Treatment, smelting and refining charges   2,140    1,578 
Add back: Metallurgical deductions   6,504    4,791 
Gross Revenues   34,571    29,914 
Silver Ounces or Zinc Tonnes Sold   1,024,052    8,865 
Average realized price per silver ounce or zinc tonne sold (2)   33.76    3,374 
Average market price per ounce of silver / zinc tonne   35.05    2,790 

 

(1) Information for Bolivar and Porco is presented at 100% and financial information will not tie to the consolidated financial statements as the Company records 45% of Bolivar and Porco.
(2) Average realized price per ounce of silver ounce or zinc tonne sold in each reporting period is affected by mark-to-market adjustments and final settlements on concentrate shipments in prior periods. Concentrates sold to third-party smelters are provisionally priced and the price is not settled until a predetermined future date, typically one to four months after delivery to the customer, based on the market price at that time.

 

- 51 -

 

 

Non-GAAP Measures (continued)

 

Porco (1) Average realized price per silver ounce or zinc tonne sold

 

   Three months ended September 30, 2026 
   Silver   Zinc 
Revenues   4,812    9,179 
Add back: Treatment, smelting and refining charges   6    466 
Add back: Metallurgical deductions   1,795    2,000 
Gross Revenues   6,613    11,645 
Silver Ounces or Zinc Tonnes Sold   113,600    2,834 
Average realized price per silver ounce or zinc tonne sold (2)   58.21    4,109 
Average market price per ounce of silver / zinc tonne   62.74    3,825 

 

   Three months ended September 30, 2025 
   Silver   Zinc 
Revenues   2,786    6,508 
Add back: Treatment, smelting and refining charges   309    253 
Add back: Metallurgical deductions   1,374    1,340 
Gross Revenues   4,468    8,101 
Silver Ounces or Zinc Tonnes Sold   105,310    2,318 
Average realized price per silver ounce or zinc tonne sold (2)   42.43    3,495 
Average market price per ounce of silver / zinc tonne   39.4    2,824 

 

   Nine months ended September 30, 2026 
   Silver   Zinc 
Revenues   12,412    23,723 
Add back: Treatment, smelting and refining charges   22    1,663 
Add back: Metallurgical deductions   6,512    5,112 
Gross Revenues   18,946    30,498 
Silver Ounces or Zinc Tonnes Sold   263,503    8,586 
Average realized price per silver ounce or zinc tonne sold (2)   71.90    3,552 
Average market price per ounce of silver / zinc tonne   73.09    3,514 

 

   Nine months ended September 30, 2025 
   Silver   Zinc 
Revenues   9,210    17,321 
Add back: Treatment, smelting and refining charges   1,368    982 
Add back: Metallurgical deductions   3,444    3,599 
Gross Revenues   14,022    21,902 
Silver Ounces or Zinc Tonnes Sold   353,098    6,466 
Average realized price per silver ounce or zinc tonne sold (2)   39.71    3,387 
Average market price per ounce of silver / zinc tonne   35.05    2,790 

 

(1) Information for Bolivar and Porco is presented at 100% and financial information will not tie to the consolidated financial statements as the Company records 45% of Bolivar and Porco.
(2) Average realized price per ounce of silver ounce or zinc tonne sold in each reporting period is affected by mark-to-market adjustments and final settlements on concentrate shipments in prior periods. Concentrates sold to third-party smelters are provisionally priced and the price is not settled until a predetermined future date, typically one to four months after delivery to the customer, based on the market price at that time.

 

- 52 -

 

 

Non-GAAP Measures (continued)

 

Caballo Blanco Group Average realized price per silver ounce or zinc tonne sold

 

   Three months ended September 30, 2026 
   Silver   Zinc 
Revenues   17,051    14,924 
Add back: Treatment, smelting and refining charges   25    693 
Add back: Metallurgical deductions   3,027    2,983 
Gross Revenues   20,103    18,600 
Silver Ounces or Zinc Tonnes Sold   338,120    4,545 
Average realized price per silver ounce or zinc tonne sold (1)   59.45    4,092 
Average market price per ounce of silver / zinc tonne   62.74    3,825 

 

   Three months ended September 30, 2025 
   Silver   Zinc 
Revenues   9,771    10,177 
Add back: Treatment, smelting and refining charges   460    408 
Add back: Metallurgical deductions   1,797    1,872 
Gross Revenues   12,028    12,457 
Silver Ounces or Zinc Tonnes Sold   289,115    3,527 
Average realized price per silver ounce or zinc tonne sold (1)   41.60    3,532 
Average market price per ounce of silver / zinc tonne   39.4    2,824 

 

   Nine months ended September 30, 2026 
   Silver   Zinc 
Revenues   43,420    35,544 
Add back: Treatment, smelting and refining charges   113    2,137 
Add back: Metallurgical deductions   9,797    7,076 
Gross Revenues   53,330    44,757 
Silver Ounces or Zinc Tonnes Sold   754,247    12,389 
Average realized price per silver ounce or zinc tonne sold (1)   70.71    3,613 
Average market price per ounce of silver / zinc tonne   73.09    3,514 

 

   Nine months ended September 30, 2025 
   Silver   Zinc 
Revenues   25,988    26,145 
Add back: Treatment, smelting and refining charges   1,883    1,600 
Add back: Metallurgical deductions   4,431    5,000 
Gross Revenues   32,302    32,744 
Silver Ounces or Zinc Tonnes Sold   903,554    9,545 
Average realized price per silver ounce or zinc tonne sold (1)   35.75    3,431 
Average market price per ounce of silver / zinc tonne   35.05    2,790 

 

(1) Average realized price per ounce of silver ounce or zinc tonne sold in each reporting period is affected by mark-to-market adjustments and final settlements on concentrate shipments in prior periods. Concentrates sold to third-party smelters are provisionally priced and the price is not settled until a predetermined future date, typically one to four months after delivery to the customer, based on the market price at that time.

 

- 53 -

 

 

Non-GAAP Measures (continued)

 

Zimapan Mine Average realized price per silver ounce or zinc tonne sold

 

   Three months ended September 30, 2026 
   Silver   Zinc 
Revenues   24,477    11,786 
Add back: Treatment, smelting and refining charges   365    2,966 
Add back: Metallurgical deductions   3,292    3,017 
Gross Revenues   28,134    17,770 
Silver Ounces or Zinc Tonnes Sold   400,539    4,678 
Average realized price per silver ounce or zinc tonne sold (1)   70.24    3,799 
Average market price per ounce of silver / zinc tonne   62.74    3,825 

 

   Three months ended September 30, 2025 
   Silver   Zinc 
Revenues   11,024    9,706 
Add back: Treatment, smelting and refining charges   1,780    1,853 
Add back: Metallurgical deductions   1,870    2,053 
Gross Revenues   14,674    13,612 
Silver Ounces or Zinc Tonnes Sold   361,878    4,520 
Average realized price per silver ounce or zinc tonne sold (1)   40.55    3,012 
Average market price per ounce of silver / zinc tonne   39.4    2,824 

 

   Nine months ended September 30, 2026 
   Silver   Zinc 
Revenues   70,508    32,093 
Add back: Treatment, smelting and refining charges   2,059    8,131 
Add back: Metallurgical deductions   10,143    7,795 
Gross Revenues   82,709    48,019 
Silver Ounces or Zinc Tonnes Sold   1,192,717    13,403 
Average realized price per silver ounce or zinc tonne sold (1)   69.35    3,583 
Average market price per ounce of silver / zinc tonne   73.09    3,514 

 

   Nine months ended September 30, 2025 
   Silver   Zinc 
Revenues   30,142    25,769 
Add back: Treatment, smelting and refining charges   6,011    6,106 
Add back: Metallurgical deductions   5,182    5,983 
Gross Revenues   41,336    37,858 
Silver Ounces or Zinc Tonnes Sold   1,191,202    13,345 
Average realized price per silver ounce or zinc tonne sold (1)   34.70    2,837 
Average market price per ounce of silver / zinc tonne   35.05    2,790 

 

(1) Average realized price per ounce of silver ounce or zinc tonne sold in each reporting period is affected by mark-to-market adjustments and final settlements on concentrate shipments in prior periods. Concentrates sold to third-party smelters are provisionally priced and the price is not settled until a predetermined future date, typically one to four months after delivery to the customer, based on the market price at that time.

 

- 54 -

 

 

Non-GAAP Measures (continued)

 

Realized mining margin for silver ounces and zinc tonnes sold – Mining operations

 

The realized mining margin is used to evaluate the profitability of the Company’s operations. The realized mining margin is calculated by subtracting the All-in sustaining cost (“AISC”) per silver ounce or zinc tonne sold from the Average realized price per silver ounce or zinc tonne sold.

 

   Three months ended September 30, 2026 
   Bolivar   Porco   Caballo Blanco Group   Zimapan   Consolidated 
Average realized price per silver ounce sold   65.39    58.21    59.45    70.24    64.72 
All-in sustaining cost per silver ounce sold   21.86    43.91    19.08    8.12    19.73 
Realized margin per silver ounce sold   43.53    14.30    40.37    62.12    44.99 
                          
Average realized price per zinc tonne sold   4,079    4,109    4,092    3,799    4,011 
All-in sustaining cost per zinc tonne sold   2,670    1,528    1,764    3,064    2,410 
Realized margin per zinc tonne sold   1,409    2,581    2,328    735    1,601 

 

   Three months ended September 30, 2025 
   Bolivar   Porco   Caballo Blanco Group   Zimapan   Consolidated 
Average realized price per silver ounce sold   40.78    42.43    41.60    40.55    41.14 
All-in sustaining cost per silver ounce sold   57.68    44.37    17.69    20.15    29.35 
Realized margin per silver ounce sold   (16.90)   (1.94)   23.91    20.40    11.79 
                          
Average realized price per zinc tonne sold   3,506    3,495    3,532    3,012    3,336 
All-in sustaining cost per zinc tonne sold   2,447    1,710    1,579    2,725    2,247 
Realized margin per zinc tonne sold   1,059    1,785    1,953    287    1,089 

 

   Nine months ended September 30, 2026 
   Bolivar   Porco   Caballo Blanco Group   Zimapan   Consolidated 
Average realized price per silver ounce sold   74.69    71.90    70.71    69.35    71.41 
All-in sustaining cost per silver ounce sold   26.57    47.36    19.46    17.78    24.20 
Realized margin per silver ounce sold   48.12    24.54    51.25    51.57    47.21 
                          
Average realized price per zinc tonne sold   3,648    3,552    3,613    3,583    3,601 
All-in sustaining cost per zinc tonne sold   2,699    1,498    1,829    2,998    2,391 
Realized margin per zinc tonne sold   949    2,054    1,784    585    1,210 

 

   Nine months ended September 30, 2025 
   Bolivar   Porco   Caballo Blanco Group   Zimapan   Consolidated 
Average realized price per silver ounce sold   33.76    39.71    35.75    34.70    35.21 
All-in sustaining cost per silver ounce sold   20.05    32.08    13.47    21.14    20.73 
Realized margin per silver ounce sold   13.71    7.63    22.28    13.56    14.48 
                          
Average realized price per zinc tonne sold   3,374    3,387    3,431    2,837    3,203 
All-in sustaining cost per zinc tonne sold   1,744    1,410    1,320    2,953    2,066 
Realized margin per zinc tonne sold   1,630    1,977    2,111    (116)   1,137 

 

- 55 -

 

 

Non-GAAP Measures (continued)

 

Cash cost of production per tonne milled, cash cost per silver ounce or zinc tonne sold, all-in sustaining cost (“AISC”) per silver ounce or zinc tonne sold – Ore processing

 

The following tables provide a detailed reconciliation of these measures to our operating expenses, as reported in our condensed interim consolidated financial statements. Readers should be cautioned that the cash cost, AISC and cash cost per tonne milled are not key metrics for evaluating the performance of our ore processing operations because ore is purchased from third-party miners who are paid based upon the metal content and prevailing market prices at the time of purchase. The cash cost per silver ounce sold and zinc tonne sold and the AISC per silver ounce or zinc tonne sold should not be compared to or consolidated with the results from the Mining operations because of the different nature of the businesses.

 

San Lucas ore processing cash cost

 

   Three months ended September 30, 2026 
   Silver   Zinc   Total 
Cost of sales   25,584    18,526    44,110 
Transportation and other selling cost   (1,401)   (1,015)   (2,416)
Royalty   (1,161)   (841)   (2,002)
Inventory change   5,588    4,047    9,635 
Cash cost of production (A)   28,610    20,717    49,327 
Cost of sales   25,584    18,526    44,110 
Concentrate treatment, smelting and refining cost   122    1,115    1,237 
By-product lead revenue   (1,730)   -    (1,730)
By-product copper revenue   -    -    - 
Cash cost of silver ounce or zinc tonne sold (B)   23,976    19,641    43,617 
Sustaining capital expenditures   270    195    465 
General and administrative expenses   723    524    1,247 
Accretion of decommissioning and restoration provision   28    20    49 
All-in sustaining cost (C)   24,997    20,381    45,378 
Material processed (tonnes milled) (D)             92,921 
Silver ounces or zinc tonnes sold (E)   449,355    6,362      
Cash cost per silver ounce or zinc tonne sold (B/E)   53.36    3,087      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   55.63    3,204      
Cash cost of production per tonne milled (A/D)             530.85 

 

   Three months ended September 30, 2025 
   Silver   Zinc   Total 
Cost of sales   12,431    10,171    22,602 
Transportation and other selling cost   (1,267)   (1,036)   (2,303)
Royalty   (554)   (453)   (1,007)
Inventory change   (45)   (37)   (82)
Cash cost of production (A)   10,566    8,645    19,210 
Cost of sales   12,431    10,171    22,602 
Concentrate treatment, smelting and refining cost   1,185    969    2,154 
By-product lead revenue   (692)   -    (692)
By-product copper revenue   -    -    - 
Cash cost of silver ounce or zinc tonne sold (B)   12,924    11,140    24,064 
Sustaining capital expenditures   519    424    943 
General and administrative expenses   1,080    883    1,963 
Accretion of decommissioning and restoration provision   55    45    100 
All-in sustaining cost (C)   14,577    12,493    27,070 
Material processed (tonnes milled) (D)             100,550 
Silver ounces or zinc tonnes sold (E)   353,965    6,199      
Cash cost per silver ounce or zinc tonne sold (B/E)   36.51    1,797      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   41.18    2,015      
Cash cost of production per tonne milled (A/D)             191.05 

 

- 56 -

 

 

Non-GAAP Measures (continued)

 

San Lucas ore processing cash cost

 

   Nine months ended September 30, 2026 
   Silver   Zinc   Total 
Cost of sales   65,977    51,222    117,198 
Transportation and other selling cost   (4,052)   (3,285)   (7,337)
Royalty   (3,714)   (2,800)   (6,514)
Inventory change   15,047    12,016    27,063 
Cash cost of production (A)   73,257    57,153    130,410 
Cost of sales   65,977    51,222    117,198 
Concentrate treatment, smelting and refining cost   2,868    3,371    6,239 
By-product lead revenue   (5,314)   -    (5,314)
By-product copper revenue   -    -    - 
Cash cost of silver ounce or zinc tonne sold (B)   63,531    54,592    118,123 
Sustaining capital expenditures   1,157    1,187    2,344 
General and administrative expenses   2,968    2,501    5,469 
Accretion of decommissioning and restoration provision   137    113    249 
All-in sustaining cost (C)   67,792    58,393    126,185 
Material processed (tonnes milled) (D)             303,112 
Silver ounces or zinc tonnes sold (E)   1,418,129    22,555      
Cash cost per silver ounce or zinc tonne sold (B/E)   44.80    2,420      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   47.80    2,589      
Cash cost of production per tonne milled (A/D)             430.24 

 

   Nine months ended September 30, 2025 
   Silver   Zinc   Total 
Cost of sales   26,340    20,902    47,242 
Transportation and other selling cost   (3,113)   (2,466)   (5,579)
Royalty   (1,022)   (818)   (1,840)
Inventory change   359    266    625 
Cash cost of production (A)   22,563    17,885    40,448 
Cost of sales   26,340    20,902    47,242 
Concentrate treatment, smelting and refining cost   2,586    2,099    4,685 
By-product lead revenue   (2,513)   -    (2,513)
By-product copper revenue   -    -    - 
Cash cost of silver ounce or zinc tonne sold (B)   26,412    23,002    49,414 
Sustaining capital expenditures   983    804    1,787 
General and administrative expenses   2,243    1,691    3,934 
Accretion of decommissioning and restoration provision   108    83    191 
All-in sustaining cost (C)   29,746    25,580    55,326 
Material processed (tonnes milled) (D)             282,218 
Silver ounces or zinc tonnes sold (E)   1,006,827    16,591      
Cash cost per silver ounce or zinc tonne sold (B/E)   26.23    1,386      
All-in sustaining cost per silver ounce or zinc tonne sold (C/E)   29.54    1,542      
Cash cost of production per tonne milled (A/D)             143.32 

 

- 57 -

 

 

Non-GAAP Measures (continued)

 

Average realized price per silver ounce and zinc tonne sold - Ore processing

 

Revenues are presented as the sum of invoiced revenues related to delivered shipments of zinc and lead concentrates, after having deducted treatment, smelting and refining charges made by the customer.

 

The average realized price per silver ounce and zinc tonne sold is an analysis of the gross revenues prior to the treatment, smelting, refining and metallurgical deduction charges which is then divided by silver ounces and zinc tonnes sold. The following tables show a detailed reconciliation of average realized price per silver ounce or zinc tonne sold to our revenues as reported in the condensed interim consolidated financial statements.

 

San Lucas ore processing average realized prices per silver ounce and zinc tonne sold

 

   Three months ended September 30, 2026 
   Silver   Zinc 
Revenues   27,769    18,242 
Add back: Treatment, smelting and refining charges   122    1,115 
Add back: Metallurgical deductions   6,718    3,980 
Gross Revenues   34,609    23,337 
Silver Ounces or Zinc Tonnes Sold   449,355    6,362 
Average realized price per silver ounce or zinc tonne sold (1)   77.02    3,668 
Average market price per ounce of silver / lead tonne   62.74    3,825 

 

   Three months ended September 30, 2025 
   Silver   Zinc 
Revenues   7,964    16,068 
Add back: Treatment, smelting and refining charges   1,184    969 
Add back: Metallurgical deductions   3,814    3,551 
Gross Revenues   12,962    20,587 
Silver Ounces or Zinc Tonnes Sold   353,965    6,199 
Average realized price per silver ounce or zinc tonne sold (1)   36.62    3,321 
Average market price per ounce of silver / lead tonne   39.4    2,824 

 

   Nine months ended September 30, 2026 
   Silver   Zinc 
Revenues   74,903    56,491 
Add back: Treatment, smelting and refining charges   567    5,564 
Add back: Metallurgical deductions   22,292    12,742 
Gross Revenues   97,762    74,797 
Silver Ounces or Zinc Tonnes Sold   1,418,129    22,555 
Average realized price per silver ounce or zinc tonne sold (1)   68.94    3,316 
Average market price per ounce of silver / lead tonne   73.09    3,514 

 

   Nine months ended September 30, 2025 
   Silver   Zinc 
Revenues   20,864    41,241 
Add back: Treatment, smelting and refining charges   2,585    2,099 
Add back: Metallurgical deductions   8,812    8,866 
Gross Revenues   32,261    52,205 
Silver Ounces or Zinc Tonnes Sold   1,006,827    16,591 
Average realized price per silver ounce or zinc tonne sold (1)   32.04    3,147 
Average market price per ounce of silver / lead tonne   35.05    2,790 

 

(1) Average realized price per ounce of silver ounce or zinc tonne sold in each reporting period is affected by mark-to-market adjustments and final settlements on concentrate shipments in prior periods. Concentrates sold to third-party smelters are provisionally priced and the price is not settled until a predetermined future date, typically one to four months after delivery to the customer, based on the market price at that time.

 

- 58 -

 

 

Non-GAAP Measures (continued)

 

Realized ore processing margin for silver ounces and zinc tonnes sold

 

The key metric for evaluating the performance and profitability of ore processing operations is the realized ore processing margin. The realized ore processing margin is calculated by subtracting the All-in sustaining cost (“AISC”) per silver ounce or zinc tonne sold from the Average realized price per silver ounce or zinc tonne sold. The non-GAAP measures of cash cost per silver ounce sold and zinc tonne sold and the AISC per silver ounce or zinc tonne sold for Ore Processing operations are calculated based upon the same basis as those used to calculate the same metrics for mining operations.

 

The realized ore processing margin should not be compared with the realized mining margin because of the differences in the nature of the business. Ore processing operations operate with a much lower margin because ore is purchased from third-party miners instead of being extracted from the Company own mine properties.

 

San Lucas provides Santacruz with an important strategic advantage by supplying third-party ore feed to existing processing plants, helping maintain high plant utilization and support more stable operating performance. By keeping processing facilities closer to full capacity, San Lucas contributes to better absorption of fixed costs across the production base, which can improve unit cost efficiency and strengthen margins. In addition, the business provides operational flexibility by allowing the Company to supplement mine production with externally sourced material when appropriate, while generating margin-based returns tied to processing capacity, metallurgical recoveries, and disciplined ore purchasing. This model enhances the overall resilience of the Company’s operating platform and supports a more efficient use of existing infrastructure.

 

The Company believes the realized ore processing margin provides investors and analysts with useful information about the Company’s underlying operating performance from its Ore processing operations.

 

San Lucas realized ore processing margin

 

   Three months ended September 30,   Nine months ended September 30, 
   2026   2025   2026   2025 
Average realized price per silver ounce sold   77.02    36.62    68.94    32.04 
All-in sustaining cost per silver ounce sold   55.63    41.18    47.80    29.54 
Realized ore processing margin per silver ounce sold   21.39    (4.56)   21.14    2.50 
                     
Average realized price per zinc tonne sold   3,668    3,321    3,316    3,147 
All-in sustaining cost per zinc tonne sold   3,204    2,015    2,589    1,542 
Realized margin per zinc tonne sold   464    1,306    727    1,605 

 

- 59 -

 

 

Non-GAAP Measures (continued)

 

Adjusted EBITDA

 

Adjusted EBITDA is a non-GAAP measure in which net income is adjusted for income tax expense, interest income, interest expense, amortization and depletion, and impairment charges, foreign exchange gains or losses, unrealized losses or gains on marketable securities, share-based payments expense, accretion expense, changes in fair value of consideration payable and other non-recurring items. Foreign exchange gains or losses may consist of both realized and unrealized losses.

 

Under IFRS, entities must reflect in compensation expense the cost of share-based payments. In the Company’s circumstances, share-based payments can involve a significant accrual of amounts that will not be settled in cash but are settled by the issuance of shares in exchange.

 

The Company discloses Adjusted EBITDA to aid in understanding of the results of the Company and is meant to provide further information about the Company’s financial results to investors.

 

The following table provides a reconciliation of Adjusted EBITDA for the three and nine months ended September 30, 2026 and 2025.

 

   Three months ended September 30,   Nine months ended September 30, 
   2026   2025   2026   2025 
                 
Net income for the period   37,617    16,344    68,092    46,772 
Income tax expense   30,714    (728)   83,220    20,042 
Depreciation, depletion and amortization   7,380    5,795    22,473    15,811 
Change in estimate of decommissioning provisions   -    -    (6,505)   - 
Foreign exchange gain   (7,060)   (4,119)   (21,909)   (13,497)
Share-based compensation expense   1,040    761    2,188    2,269 
Loss on change in fair value of consideration payable   (8,893)   2,283    5,930    5,262 
Accretion of decommissioning provisions   510    687    2,099    1,462 
Accretion of receivable from COMIBOL   (385)   (350)   (1,362)   (790)
Financing charge on leases   -    155    28    451 
Interest expense, carrying and finance charges   1,033    661    3,093    1,261 
Interest income on VAT receivable   (2,648)   (964)   (7,606)   (3,351)
Interest income   (647)   (486)   (1,541)   (1,093)
Other income   2,425    (530)   2,117    (804)
Adjusted EBITDA   61,086    19,509    150,317    73,795 

 

- 60 -

 

 

Cautionary Note to United States Investors Concerning Estimates of Mineral Reserves & Resources

 

This MD&A has been prepared in accordance with the requirements of Canadian provincial securities laws, which differ from the requirements of U.S. securities laws. As a result, the Company reports the mineral reserves and resources of the projects it has an interest in according to Canadian standards. Canadian reporting requirements for disclosure of mineral properties are governed by National Instrument 43-101 - Standards of Disclosure for Mineral Projects (“NI 43-101”). NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. These standards differ from the requirements of the SEC that are applicable to domestic United States reporting companies under subpart 1300 of Regulation S-K (“S-K 1300”) under the Exchange Act. As an issuer that prepares and files its reports with the SEC pursuant to the Multijurisdictional Disclosure System, the Company is not subject to the requirements of S-K 1300. Any mineral reserves and mineral resources reported by the Company in accordance with NI 43-101 may not qualify as such under or differ from those prepared in accordance with S-K 1300. Accordingly, information included or incorporated by reference in this MD&A concerning descriptions of mineralization and estimates of mineral reserves and resources under Canadian standards may not be comparable to similar information made public by United States companies subject to the reporting and disclosure requirements of S-K 1300.

 

Cautionary Note Regarding Forward-looking Information

 

Certain of the statements and information in this MD&A constitute “forward-looking information” within the meaning of applicable Canadian provincial securities laws relating to the Company and its operations. All statements, other than statements of historical fact, are forward-looking statements. When used in this MD&A, the words, “will”, “believes”, “expects”, “intends”, “plans”, “forecast”, “objective”, “guidance”, “outlook”, “potential”, “anticipated”, “budget”, and other similar words and expressions, identify forward-looking statements or information. These forward-looking statements or information relate to, among other things: future financial or operational performance; the expected timing for release of forecasts for 2026, including our estimated production of silver, zinc, lead and copper, and for our estimated Cash Costs, AISC, capital and exploration, mine operation, general and administrative, care and maintenance expenditures; future anticipated prices for silver, zinc, lead and copper and other metals and assumed foreign exchange rates; the impacts of inflation on the Company and its operations; whether the Company is able to maintain a strong financial condition and have sufficient capital, or have access to capital, to sustain our business and operations; the timing and outcome with respect to the Company’s environmental, social and governance activities, and the Company’s corporate social responsibility activities and our reporting in respect thereof; the ability of the Company to successfully complete any capital projects, the expected economic or operational results derived from those projects, and the impacts of any such projects on the Company; the potential maximum consideration payable to Glencore pursuant to the Term Sheet; the future results of our exploration activities, anticipated mineral reserves and mineral resources; the costs associated with the Company’s decommissioning obligations; the Company’s plans and expectations for its properties and operations; and expectations with respect to the future anticipated impact of pandemics on our operations.

 

These forward-looking statements and information reflect the Company’s current views with respect to future events and are necessarily based upon a number of assumptions and estimates that, while considered reasonable by the Company, are inherently subject to significant operational, business, economic, competitive, political, regulatory, and social uncertainties and contingencies. These assumptions, include: our ability to implement environmental, social and governance activities; tonnage of ore to be mined and processed; ore grades and recoveries; that the Company will receive all required regulatory approvals to operate; that the market price of zinc may be above certain minimum thresholds for the payment of the CVR Payments and Additional Payments; prices for silver, zinc, lead, copper remaining as estimated; currency exchange rates remaining as estimated; capital, decommissioning and reclamation estimates; our mineral reserve and mineral resource estimates and the assumptions upon which they are based; prices for energy inputs, labour, materials, supplies and services (including transportation); no labour-related disruptions at any of our operations; no unplanned delays or interruptions in scheduled production; protection of our interests against claims and legal proceedings; all necessary permits, licenses and regulatory approvals for our operations are received in a timely manner and can be maintained. The foregoing list of assumptions is not exhaustive.

 

- 61 -

 

 

Cautionary Note Regarding Forward-looking information (continued)

 

The Company cautions the reader that forward-looking statements and information involve known and unknown risks, uncertainties and other factors that may cause actual results and developments to differ materially from those expressed or implied by such forward-looking statements or information contained in this MD&A and the Company has made assumptions and estimates based on or related to many of these factors. Such factors include, some of which are described in the “Risks Factors” section of this MD&A without limitation: fluctuations in silver, zinc, lead and copper prices; fluctuations in prices for energy inputs; fluctuations in currency markets (such as the MXN, BOB and CAD versus the USD); risks related to the technological and operational nature of the Company’s business; required regulatory approvals; changes in national and local government, legislation, taxation, controls or regulations and political, legal or economic developments in Canada, the United States, Mexico, Bolivia or other countries where the Company may carry on business, some of which might prevent or cause the suspension or discontinuation of mining activities, including the risk of expropriation related to certain of our operations, particularly in Bolivia; risks and hazards associated with the business of mineral exploration, development and mining (including environmental hazards, industrial accidents, unusual or unexpected geological or structural formations, pressures, cave-ins and flooding); risks relating to the credit worthiness or financial condition of suppliers, refiners and other parties with whom the Company does business; inadequate insurance, or inability to obtain insurance, to cover these risks and hazards; employee relations; relationships with and claims by the local communities and indigenous populations; availability and increasing costs associated with mining inputs and labour; the Company’s ability to secure our mine sites or maintain access to our mine sites due to criminal activity, violence, or civil and labour unrest; that changes to the market price of zinc may affect the total consideration payable to Glencore pursuant to the omnibus agreement; the speculative nature of mineral exploration and development, including the risk of obtaining or retaining necessary licenses and permits; challenges to, or difficulty in maintaining, the Company’s title to properties and continued ownership thereof; diminishing quantities or grades of mineral reserves as properties are mined; global financial conditions; the Company’s ability to complete and successfully integrate acquisitions, and to mitigate other business combination risks; the actual results of current exploration activities, conclusions of economic evaluations, and changes in project parameters to deal with unanticipated economic or other factors; increased competition in the mining industry for properties, equipment, qualified personnel, and their costs; having sufficient cash to pay obligations as they come due; the duration and effects of the coronavirus and COVID-19 variants, and any other epidemics or pandemics on our operations and workforce, and their effects on global economies and society. Although the Company has attempted to identify important factors that could cause actual results to differ materially, there may be other factors that cause results not to be as anticipated, estimated, described, or intended. Investors are cautioned against attributing undue certainty or reliance on forward-looking statements or information. Forward-looking statements and information are designed to help readers understand Management’s current views of our near- and longer-term prospects and may not be appropriate for other purposes. The Company does not intend, and does not assume any obligation, to update or revise forward-looking statements or information to reflect changes in assumptions or in circumstances or any other events affecting such statements or information, other than as required by applicable law.

 

Additional Information

 

Additional information relating to the Company is on SEDAR+ at www.sedarplus.ca.

 

- 62 -