UNITED STATES

SECURITIES AND EXCHANGE COMMISSION

Washington, D.C. 20549

 

 

Form 6-K

 

 

REPORT OF FOREIGN PRIVATE ISSUER

PURSUANT TO RULE 13a-16 OR 15d-16

UNDER THE SECURITIES EXCHANGE ACT OF 1934

23 November 2026

 

 

BHP GROUP LIMITED

(ABN 49 004 028 077)

(Exact name of Registrant as specified in its charter)

VICTORIA, AUSTRALIA

(Jurisdiction of incorporation or organisation)

171 COLLINS STREET, MELBOURNE, VICTORIA 3000 AUSTRALIA

(Address of principal executive offices)

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F: ☒

Form 20-F ☐ Form 40-F

Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(1): ☐

Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(7): ☐

Indicate by check mark whether the registrant by furnishing the information contained in this Form is also thereby furnishing the information to the Commission pursuant to Rule 12g3-2(b) under the Securities Exchange Act of 1934: ☐ Yes ☒ No

If “Yes” is marked, indicate below the file number assigned to the registrant in connection with Rule 12g3-2(b): n/a

 

 
 


LOGO

Exchange release

23 November 2026

2026 Copper South Australia Site Tour

 

BHP will be hosting an investor and analyst site tour on 23 November 2026 – 24 November 2026 to provide an update on our Copper South Australia business and growth strategy.

A copy of the presentation materials is attached.

The presentation slides will be available on BHP’s website at: https://www.bhp.com/investor-centre/reports-and-presentations/presentations-and-briefings

Further information on BHP can be found at: bhp.com

Authorised for release by Stefanie Wilkinson, Group Company Secretary

BHP Group Limited ABN 49 004 028 077


LOGO

Contacts

 
Media    Investor Relations
media.relations@bhp.com    investor.relations@bhp.com
Australia and Asia    Australia and Asia
Gabrielle Notley    John-Paul Santamaria
+61 411 071 715    +61 499 006 018
Europe, Middle East and Africa    Europe, Middle East and Africa
Sinead Keller    Adam Sanderson
+44 7816 826 169    +44 7884 735 515
Americas    Americas
Renata Fernandez    Li Hua
+56 9 8229 5357    +1 647 828 9830
BHP Group Limited   
ABN 49 004 028 077   
LEI WZE1WSENV6JSZFK0JC28   
Registered in Australia   
Level 18, 171 Collins Street   
Melbourne   
Victoria 3000 Australia   
Tel: +61 1300 55 4757 Fax: +61 3 9609 3015   
BHP Group is headquartered in Australia   
bhp.com   
BHP Group Limited ABN 49 004 028 077   


LOGO

Copper South Australia: Unlocking a world—class copper province Olympic Dam November 2026


LOGO

Disclaimer 2 Copper South Australia site tour | November 2026 The information in this presentation is current as at 23 November 2026 . It is in summary form and is not necessarily complete . It should be read together with the BHP Results for the year ended 30 June 2026 . Forward—looking statements This presentation contains forward—looking statements, which involve risks and uncertainties . Forward—looking statements include all statements other than statements of historical or present facts, including : statements regarding : trends in commodity prices and currency exchange rates ; demand for commodities ; global market conditions ; reserves and resources estimates ; recoveries, mine plans, processing performance and other technical assumptions ; development and production forecasts ; guidance ; expectations, plans, strategies and objectives of management ; climate scenarios ; sustainability, decarbonisation, social value and other targets, goals, pathways and related assumptions ; approval of projects and consummation of transactions ; closure, divestment, acquisition or integration of certain assets, ventures, operations or facilities (including associated costs or benefits) ; commodity streaming, offtake, infrastructure, funding, capital release or similar arrangements (including associated costs or benefits) ; anticipated production or construction commencement dates ; capital costs and scheduling ; operating costs, and availability of materials and skilled employees ; anticipated productive lives of projects, mines and facilities ; the availability, implementation and adoption of new technologies, including artificial intelligence ; provisions and contingent liabilities ; and tax, legal and other regulatory developments . Forward—looking statements may be identified by the use of terminology, including, but not limited to, ‘aim’, ‘ambition’, ‘anticipate’, ‘aspiration’, ‘believe’, ‘commit’, ‘continue’, ‘could’, ‘desire’, ‘ensure’, ‘estimate’, ‘expect’, ‘forecast’, ‘goal’, ‘guidance’, ‘intend’, ‘likely’, ‘may’, ‘milestone’, ‘must’, ‘need’, ‘objective’, ‘outlook’, ‘pathways’, ‘plan’, ‘project’, ‘schedule’, ‘seek’, ‘should’, ‘strategy’, ‘target’, ‘trend’, ‘will’, ‘would’ or similar words . These statements discuss future expectations or performance, or provide other forward—looking information . Forward—looking statements are based on management’s expectations and reflect judgements, assumptions, estimates and other information available as at the date of this presentation . These statements do not represent guarantees or predictions of future financial or operational performance, and involve known and unknown risks, uncertainties and other factors, many of which are beyond our control, and which may cause actual results to differ materially from those expressed in the statements contained in this presentation . BHP cautions against reliance on any forward—looking statements . For example, our future revenues from our assets, projects or mines described in this presentation will be based, in part, on the market price of the commodities produced, which may vary significantly from current levels or those reflected in our reserves and resources estimates . These variations, if materially adverse, may affect the timing or the feasibility of the development of a particular project, the expansion of certain facilities or mines, or the continuation of existing assets . Other factors that may affect our future operations and performance, including the actual construction or production commencement dates, revenues, costs or production output and anticipated lives of assets, mines or facilities include our ability to profitably produce and deliver the products extracted to applicable markets ; the development and use of new technologies and related risks ; the impact of economic and geopolitical factors, including foreign currency exchange rates on the market prices of the commodities we produce and competition in the markets in which we operate ; activities of government authorities in or impacting the countries where we sell our products and in the countries where we are exploring or developing projects, facilities or mines identified in the risk factors discussed , including increases in taxes and royalties or implementation or expansion of trade or export restrictions ; changes in environmental and other regulations ; political or geopolitical uncertainty and conflicts ; labour unrest ; weather, climate variability or other manifestations of climate change ; and other factors in section 6 of the Operating and Financial Review (OFR) in the BHP Annual Report 2026 and BHP’s filings with the U . S . Securities and Exchange Commission (the ‘SEC’) (including in Annual Reports on Form 20—F) which are available on the SEC’s website at sec . gov . Except as required by applicable regulations or by law, BHP does not undertake to publicly update or review any forward—looking statements, whether as a result of new information or future events . Past performance cannot be relied on as a guide to future performance . Emissions and energy consumption data Due to the inherent uncertainty and limitations in measuring greenhouse gas (GHG) emissions and operational energy consumption under the calculation methodologies used in the preparation of such data, all GHG emissions and operational energy consumption data or references to GHG emissions and operational energy consumption volumes (including ratios or percentages) in this presentation are estimates . There may also be differences in the manner that third parties calculate or report GHG emissions or operational energy consumption data compared to BHP, which means third—party data may not be comparable to our data . For information on how we calculate our GHG emissions, refer to BHP Annual Report 2026 , Sustainability Report 7 . 6 Methodology for calculating Scopes 1 , 2 and 3 GHG emissions available at bhp . com . Numbers presented may not add up precisely to the totals provided due to rounding . Presentation of data Unless expressly stated otherwise : variance analysis relates to the relative performance of BHP and/or its operations during the year ended 30 June 2026 compared with the year ended 30 June 2025 ; references to Underlying EBITDA margin excludes third—party products ; production volumes, sales volumes and capital and exploration expenditure for subsidiaries are presented on a 100 % basis unless otherwise stated ; production and sales volumes from equity—accounted investments and other operations are presented on a BHP—attributable basis . Financial information for equity—accounted investments is presented as BHP’s share, except for net operating assets, and Group and segment statutory results reflect the application of equity accounting under IFRS ; medium—term refers to a five—year horizon, unless otherwise noted . Numbers presented may not add up precisely to the totals provided due to rounding . Unless expressly stated otherwise, for information and data in this presentation related to BHP’s social value or sustainability position or performance : former OZL operations that form part of BHP’s Copper South Australia asset and the West Musgrave Project are included for FY 24 and FY 25 but excluded for prior financial years ; former OZL Brazil assets are excluded ; and all such information and data excludes BHP’s interest in non—operated assets . Ore Reserves and Mineral Resource are presented in this presentation in accordance with ASX Listing Rules . U . S . investors are advised to refer to the mineral resources and mineral reserves presented in the BHP annual report on Form 20—F, filed with the U . S . Securities and Exchange Commission (SEC), which presents estimates prepared in accordance with SEC regulations Subpart 1300 of Regulation S—K . All footnote content (except in the Annexures) is contained on slides 70—73 . Non—IFRS information We use various Non—IFRS information to reflect our underlying performance. For further information, the reconciliation of non—IF RS financial information to our statutory measures, reasons for usefulness and calculation methodology, please refer to ‘Non—IFR S financial information’ in the BHP Financial Results for the year ended 30 June 2026 . No offer of securities Nothing in this presentation should be construed as either an offer or a solicitation of an offer to buy or sell BHP securiti es, in any jurisdiction, or be treated or relied upon as a recommendation or advice by BHP. Reliance on third party information The views expressed in this presentation contain information that has been derived from publicly available sources that have not been independently verified . No representation or warranty is made as to the accuracy, completeness or reliability of the information . This presentation should not be relied upon as a recommendation or forecast by BHP . No financial or investment advice – South Africa BHP does not provide any financial or investment ‘advice’ as that term is defined in the South African Financial Advisory and Intermediary Services Act, 37 of 2002 , and we strongly recommend that you seek professional advice . BHP and its subsidiaries In this presentation, the terms ‘BHP’, the ‘Company, the ‘Group’, ‘BHP Group’, ‘our business’, ‘organisation’, ‘we’, ‘us’, ‘our’ and ourselves’ refer to BHP Group Limited and, except where the context otherwise requires, our subsidiaries . Refer to Note 28 ‘Subsidiaries’ of the Financial Statements in the BHP Annual Report 2026 for a list of our significant subsidiaries . Those terms do not include non—operated assets . Our non—operated assets include Antamina, Samarco, Resolution and Vicuña . This presentation covers BHP’s functions and assets (including those under exploration, projects in development or execution phases, sites and operations that are closed or in the closure phase) that have been wholly owned and operated by BHP or that have been owned as a joint venture 1 operated by BHP (referred to in this presentation as ‘operated assets’ or ‘operations’) from 1 July 2025 to 30 June 2026 unless otherwise stated . BHP also holds interests in assets that are owned as a joint venture but not operated by BHP (referred to in this presentation as ‘non—operated joint ventures’ or ‘non—operated assets’) . Notwithstanding that this presentation may include production, financial and other information from non—operated assets, non—operated assets are not included in the BHP Group and, as a result, statements regarding our operations, assets and values apply only to our operated assets unless stated otherwise . 1. References in this presentation to a ‘joint venture’ are used for convenience to collectively describe assets that are not wholly owned by BHP . Such references are not intended to characterise the legal relationship between the owners of the asset .


LOGO

Acknowledgement of Kokatha Country 3 A New Chapter Presten Warren


LOGO

The attractiveness of copper and BHP’s tier 1 copper portfolio T he people, communities and partnerships that we rely on Copper SA’s evolution into an integrated and high—performing asset Our approach to delivering on our strategy The strategy and projects that will deliver Copper SA’s potential Copper South Australia site tour: Day 1 at a glance 4 Copper South Australia site tour | November 2026 Meet the team Jim McCluskey General Manager Planning, Technical & Environment Mitch Parton General Manager Olympic Dam Mine (Acting) Jacinta Parsons General Manager Surface Execution Pedram Ittehadi Head of Major Projects Copper SA Anna Wiley President Copper SA What you are going to see What we’ll cover Geraldine Slattery President Minerals Australia Tour: Olympic Dam mine Deep dive: Two—stage smelting Tour: Olympic Dam surface Copper and BHP Intro. to Copper SA Connections Growth Project execution Carrapateena Olympic Dam Ankata Adelaide Prominent Hill 1 2 3 Jane Kuang VP Finance Minerals Australia


LOGO

Copper South Australia site tour: Day 2 at a glance 5 Copper South Australia site tour | November 2026 Kirsty Liddicoat General Manager Prominent Hill Vinod Perera General Manager Carrapateena Jim McCluskey General Manager Planning, Technical & Environment Meet the team Carrapateena Olympic Dam Ankata Adelaide Prominent Hill 1 2 3 What you are going to see What we’ll cover The journey to the first block cave at Copper SA Tour: Carrapateena surface Carrapateena Block caving Block caving 101 Snapshot of Prominent Hill operations and PHOX Introduction to Ankata Prominent Hill Ankata


LOGO

Copper and its place within BHP Geraldine Slattery Minerals Australia President Olympic Dam


LOGO

Jansen Vicuña JV Chilean copper Resolution JV Samarco JV Antamina JV BHP’s portfolio sits within attractive mining jurisdictions 7 Copper South Australia site tour | November 2026 Australia Copper South Australia Building a world class copper province Western Australia Iron Ore World’s lowest cost major iron ore producer 5 BMA World’s leading steelmaking coal business 6 Copper Potash Iron ore Steelmaking coal Jansen Canada’s largest potash project 1 Resolution JV One of the largest high—grade copper resources globally 2 Chile copper Escondida, world’s largest copper mine + Spence 3 Antamina JV Top 10 global copper producer 3 Vicuña JV Potential top—5 global copper and gold producer 4 Samarco JV Premium iron ore product North America South America Copper SA WAIO BMA A focused, tier 1 portfolio of attractive assets designed to deliver value for decades to come


LOGO

Commodity attractiveness Steep cost curve 1 Scale / size (US$) 2 Demand drivers Copper Copper SA Chile Copper ~300 bn Electrification Digitisation / data Increasing living standards Population growth Iron ore WAIO ~180 bn Urbanisation Population growth Steelmaking coal BMA ~65 bn Urbanisation Population growth Potash Jansen ~30 bn Population growth Increasing living standards Commodity selection drives value in mining 8 Copper South Australia site tour | November 2026 Scale, steep cost curves and exposure to demand drivers linked to today’s mega trends drives commodity attractiveness 3.3x 2.2x 1 .6x 27x


LOGO

0 10 20 30 40 50 2001 2006 2011 2016 2021 2026 2031 2036 Existing mines and expansions Copper scrap Total demand 0 10 20 30 40 50 2001 2006 2011 2016 2021 2026 2031 2036 Traditional end uses Non-traditional Total demand 2040 Accelerating demand and declining production from existing mines are expected to drive a copper supply deficit in coming years Forecast copper demand growth requires new supply… 9 Copper South Australia site tour | November 2026 Population growth Living standards Urbanisation Electrification Renewable generation Grid resilience Connectivity Compute Artificial intelligence Total copper demand 1 (M t ) Total copper demand vs total copper supply (M t ) Up to ~10 Mtpa of new primary copper supply needed by late next decade ~3.0% Growth rate 4 ~6.9% Growth rate 4 ~1.6% Growth rate 4 Traditional economic growth Energy transition Digital 2 3 2040


LOGO

…and new mine supply is becoming more challenging 10 Copper South Australia site tour | November 2026 Capital cost inflation, grade decline, increasing complexity and resource nationalisation are contributing to an increase in the cost of new supply Capital intensity of copper projects 1 (US$k/t Cu, real 2026 terms ) Global copper growth capex 3 (US$ bn, real 2025 terms ) 0 10 20 30 40 50 2001 2005 2009 2013 2017 2021 2025 Milled head grade 2 (% copper ) > Trend towards more regulatory and social scrutiny of projects Geopolitical instability and resource nationalism introduces new complexities > Long term grade decline is expected to continue Depth and/or altitude of new projects present new challenges 0.0 0.2 0.4 0.6 0.8 1.0 06 12 18 24 30 2001-2005 2006-2010 2011-2015 2016-2020 2021-2025 2026-2035 Capital Intensity ($/t ktpa Cu) Global copper grade


LOGO

0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 First Quantum KGHM Antofogasta Rio Tinto Southern Copper Zijin Glencore Anglo Teck Freeport McMoran BHP todayBHP FY35 BHP FY35 1 BHP today BHP is already the world’s largest listed copper producer… 11 Copper South Australia site tour | November 2026 BHP produces ~1.4 Mtpa of attributable copper — more than any other company – and has a pathway to increase by a further 40% 1 Copper production 2 (Mtpa, attributable) +40%


LOGO

0.0 0.5 1.0 1.5 2.0 2.5 3.0 FY26 Vicuña Stages I+II Copper SA Phase 1 (~500 ktpa Cu) Escondida New Concentrator SCPY, ripios and Cerro Colorado Others net of grade decline Mid 2030s Copper SA Phase 2 (up to 650 ktpa Cu) Vicuña Stage III Additional options Resolution 5 Antamina Life Extension Increased gold, uranium, silver …with an attractive pathway to grow to 2 Mtpa Cu by 2035… 12 Copper South Australia site tour | November 2026 Attributable copper equivalent production (Mtpa) Copper SA is core to BHP’s pathway to increase its attributable copper production by ~40% by mid 2030s 1 ~2.0 Mtpa Cu ~2.5 Mtpa CuEq* 1.4 Mtpa Cu >1.7 Mtpa CuEq* Copper By—products FY35 FY26 * FY26 attributable copper production is based on FY26 actuals, includes 310 kt CuEq from by—products. 2.5 Mtpa CuEq includes 570 ktpa CuEq from by—products of the copper segment by mid 2030s. See ‘Forward—looking production information: assumptions and copper equivalent methodology’ on slide 73. 2 3 4


LOGO

…and funded entirely from Copper’s operating cash flows 13 Copper South Australia site tour | November 2026 Tier 1 asset scale and high margin performance means our copper business break—even is forecast to be below long run consensus p rice Free cash flow (FCF 3 ) break—even copper price 4 (US$/lb) Source: Scotiabank, company reports, copper producers include Antofagasta, Capstone, First Quantum, Freeport—McMoRan and Hudbay. 0.00 1.00 2.00 3.00 4.00 5.00 6.00 Cu producer #1 Cu producer #2 Cu producer #3 Average Cu producer #4 Cu producer #5 BHP copper only BHP full portfolio Long run consensus 5 = $5/lb $3.10/lb $1.70/lb ~US$5 bn attributable free cash flow 1 Over the period to 2035 our copper business is expected to generate 2 : In FY26, our copper business delivered: Positive attributable free cash flow every year ~US$35 bn positive attributable cumulative free cash flow 6


LOGO

Key takeaways 14 Copper South Australia site tour | November 2026 BHP is the largest copper producer 1 , with a pathway to increase attributable copper production to 2 Mt by 2035 2 We have plans to double copper production at Copper SA to 650ktpa by 2040 2 Supply from existing copper mines is expected to be insufficient to meet demand We expect Copper SA to generate ~1/3 of our copper growth to 2035 3 at competitive capital intensities Our copper business’s cumulative operating cash flow can more than entirely fund its growth capex


LOGO

Introduction to Copper South Australia Olympic Dam Anna Wiley Copper South Australia Asset President


LOGO

Escondida Los Bronces Underground La Granja Buenavista Vicuña BHP Peers Copper SA Kamoa—Kakula Pebble Morenci Oyu Tolgoi Tenke Fungurume Polar Division Grasberg Collahuasi Quebrada Blanca Copper SA: A world class copper, gold and uranium asset 16 Copper South Australia site tour | November 2026 A wholly owned polymetallic resource with ~80 years of mine life 1 Copper SA has the world’s 2nd largest contained copper resource 3 … Olympic Dam 2% to 88.1 Mt 2 Carrapateena 5.0 Mt Prominent Hill 1.5 Mt Ankata 8.8 Mt …with by—products adding resilience and diversification World’s 2 nd largest gold asset 3 World’s largest uranium asset 3 Potential for additional critical minerals Map represents top 15 contained copper resources not owned by a state—owned entity 4 Size of bubble represents reserves and resources 3 Resolution


LOGO

A uniquely OECD—located, fully integrated facility… 17 Copper South Australia site tour | November 2026 C opper SA has three operating sites including an integrated smelter and refinery located within a stable region (i) Figures represent the approximate distance of each power transmission line. BHP tenements Major road Power transmission (i) Ankata Olympic Dam ~180km ~180km Prominent Hill Carrapateena Producing asset Project 0 km 50 Province map Flowsheet Concentrator Smelting Refinery Secondary circuit Underground development Underground load & haul Hoisting, crush & convey Sales product: Uranium Sales products: Copper cathode, g old and silver Sales product: Copper concentrate


LOGO

…with a locally based workforce with deep expertise 18 Copper South Australia site tour | November 2026 A highly skilled, diverse local workforce collaboratively developing exciting future pathways in our region • ~8,000 employees and contractors • ~1.1% of South Australia’s workforce 1 • ~40% contractors Local • ~35% female representation • ~26% female leadership • ~7% Indigenous representation Inclusive 2 • Operating underground + smelter for > 30 years • Deep, broad technical capability across fully integrated value chain • Leveraging BHP’s global capability Depth of knowledge • ~200 apprentices and graduates • Port Augusta Technical College • Regional pathways to industry Talent development


LOGO

Our approach: Build capable people, engineer risk out of work, and simplify how safety is managed Success is everyone going home safe and well 19 Copper South Australia site tour | November 2026 Our people Empower capability • “Safety Starts with Me” program • BOS continuous improvement • Leaders visible in field • Collaborating with our contractors 30% YoY Field Leader ship activities Our controls Engineer out risk • Automation and technology • Frontline exposure reduction • Process safety c ontrols • Investigation learning >1,000 Vehicles with proximity detection alerts Our systems Strengthen consistency • Integrated Management System • Standardised C ritical Controls • Industry leading risk processes 76% YoY hazard identification Zero high potential injuries in FY26 1 3000 5000 7000 9000 11000 13000 350 850 1350 1850 Hazard identification and Field Leadership Hazard identification Field Leadership


LOGO

We have integrated Carrapateena and Prominent Hill 20 Copper South Australia site tour | November 2026 Carrapateena and Prominent Hill provide scale and improved operating flexibility EBITDA synergies of >US$130 m per annum through: Realised synergies are 2.5x original estimate 1 Additional integration benefits Centralised concentrate processing at Olympic Dam Integrated supply chain and procurement scale Simplified corporate structures and processes Bulk mining capability: sub—level and block caving E xpanded sales of concentrates to new customers Prominent Hill Carrapateena Executed declines and crushers – the templates of future growth projects


LOGO

Diversified markets for copper and by—products 21 Copper South Australia site tour | November 2026 We sell a range of high—quality products providing optionality in terms of product strategy Copper concentrate Copper cathode Uranium oxide Refined precious metals • High grade Cu content: 30 — 50% 1 • High precious metals content: 10—50 g/t Au 1 • Uranium content managed via technical marketing • Olympic Dam premium cathode – 99.999% Cu • Copper Mark certified Product • High U content combined with low impurity content • Gold bullion • Silver bullion • Fabricators and OEMs • Global customer base Customers • Direct sales to smelter customers • Upside blending potential • Global power utilities • Compliant with Australian safeguard standards • Established bullion markets (e.g. Perth Mint)


LOGO

Our growth strategy for Copper SA reflects a better understanding of the asset and a focus on long term value creation Our vision for Copper SA has evolved 22 Copper South Australia site tour | November 2026 A staged growth program creates optionality Bulk mining will unlock substantial incremental value A d eeper market for concentrate creates product flexibility Copper SA needs a two—stage smelter ... have informed our asset strategy for Copper SA Large open pit and concentrator 2005 – 2012 Expanded selective mining and flow—sheet debottlenecking 2013 – 2020 Resource drilling; Bulk mining and smelting studies 2021 – today Successive development concepts and studies …


LOGO

We have already made several strategic development decisions 1 , with two key decisions under study and yet to be made A number of strategic decisions have already been made 23 Copper South Australia site tour | November 2026 Mining Open—cut Underground Selective only Selective + bulk mining Processing Single—stage smelting Tw o—stage smelting Cathode only product Cathode + concentrate sales Increased uranium circuit OD block cave size Ultimate smelter capacity Ongoing study Locked decision


LOGO

Copper SA’s development is aligned with BHP’s strategy 24 Copper South Australia site tour | November 2026 Copper SA’s growth strategy is key to BHP’s commitment to winning the next decade... and beyond Delivering disciplined programmatic growth Leverage the resource Accelerating performance Deliver margin resilience and asset stability Strengthening our foundations Build enduring connections Grow production to ~500 ktpa of copper Establish platform for future expansion Eliminate fatalities Improve productivity Reduce costs Deliver by—products Traditional Owners Governments Suppliers Local communities and regions BHP Copper SA


LOGO

Improving operational and financial performance Jane Kuang Minerals Australia Vice President Finance Olympic Dam


LOGO

BOS and technology are improving operational stability… 26 Copper South Australia site tour | November 2026 BOS integration is well advanced at Copper SA and we are leveraging technology to accelerate performance improvement Operational Excellence Index (OEI) 1 0 10 20 30 40 50 60 70FY20 FY21 FY22 FY23 FY24 FY25 FY26 McKinsey’s definition of world leading 2 Olympic Dam Surface Olympic Dam Mine Carrapateena 3 Prominent Hill 3 BHP Operating System Technology Olympic Dam Carrapateena Prominent Hill Semi—autonomous underground drilling Increased mill throughput and improved flotation recoveries (e.g. HydroFloat) Trialling robotic explosive charging Semi—autonomous loaders improve productivity Real—time mineralogy assessment for higher recoveries, lower reagents Underground material movement optimisation Real—time monitoring of surface operations AI enabled decision making from mine to smelter


LOGO

Olympic Dam mine Carrapateena Olympic Dam surface …a nd recent investment has lifted capacity 27 Copper South Australia site tour | November 2026 Investment to improve performance at Copper SA has been across the value chain Smelter Campaign Maintenance (2021) Refinery Crane & Capacity (2022) 0 80 160 240 FY19-21 (pre-SCM21) FY23-26 (post-SCM21) OD cathode production ( ktpa ) +20% Crusher 2 (2024) HydroFloat & Jameson cells (2025) Carrapateena copper production (ktpa) Kalta Decline (2018) Hoist and Rail asset integrity (2021) 0 25 50 75 FY23 FY24-26 OD ore to surface (Mtpa) 05 10 15 FY16-19 FY20-23 FY24-26 +26% +10%


LOGO

01.00 2.00 3.00 4.00 5.00 6.00 0 100 200 300 400 500 600 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 Olympic Dam (Cu) Carrapateena (Cu) Prominent Hill (Cu) By-products (CuEq) Copper price (RHS) Production is now more stable and at record levels… 28 Copper South Australia site tour | November 2026 Year—on—year operational consistency culminated in record FY26 performance Copper SA production 1 (kt) Record material mined and ore milled Record 20—year production in Olympic Dam Record concentrate production Record total gold production Record concentrate smelted FY26 production records SCM21 SCM17 Copper price 2 (US$/lb) Acquisition of Carrapateena and Prominent Hill


LOGO

…and cost performance has beaten inflation 29 Copper South Australia site tour | November 2026 Integration and productivity improvement has enabled Copper SA to deliver real cost decline, with by—products enhancing margin r esilience Unit costs (US$/lb) 0.00 1.25 2.50 3.75 5.00 FY20 FY21 FY22 FY23 FY24 FY25 FY26 Unit costs (excl by-products) FY20 Unit costs (excl by-products)—inflated by CPI Acquisition of Carrapateena and Prominent Hill SCM21 Reported unit costs (incl by—product credits) US$0.32/lb Record by—product revenue US$2.3 bn FY26 unit cost US$0.32/lb


LOGO

A strong foundation for investment 30 Copper South Australia site tour | November 2026 Copper SA’s renewed operational stability provides confidence to support increased capital investment Operating productivity Capital productivity Net operating cash flow Excess cash Portfolio Buy—backs Acquisitions/ (Divestments) Balance sheet Organic development Additional dividends Maintenance and decarbonisation capital Minimum 50% payout ratio dividend Strong balance sheet The Capital Allocation Framework sits at the core of BHP Operating productivity Focus on capital productivity Record EBITDA in FY26 of US$3.2 bn Record FCF in FY26 of ~US$1.0 bn Program—view supports optimisation of overall value Each project then assessed individually against a range of metrics


LOGO

Enduring connections Anna Wiley Copper South Australia Asset President


LOGO

Creating shared value across South Australia 32 Copper South Australia site tour | November 2026 Building trusted partnerships and regional capability that support Copper SA today and into the future • >A$100 m spend with 47 Indigenous suppliers, incl A$65 m with 17 Traditional Owner suppliers ~A$300 m spend with local & Indigenous suppliers ~A$450 m SA royalties and taxes • ~72% of state royalty revenue • ~3% of gross state product 1 • Largest driver of SA export revenue 1 Strong regional supply chains Community contribution ~A$10 m social investments • Working with community partners to support health, education and community wellbeing • Key partnerships with RFDS, Roxby Downs childcare, AFLW, Foodbank Major economic driver Note: All figures (except social investments) based on FY26 data.


LOGO

Strengthening relationships with Traditional Owners 33 Copper South Australia site tour | November 2026 Building enduring partnerships and supporting connection to Country and culture Negotiating contemporary agreements across 6 Traditional Owner groups Partnerships and participation BHP’s ‘Healthy Environment’ nature project: ‘Jackboot’ in partnership with Arabana Culture and connection Renamed Oak Dam as ‘Ankata’ recognising Kokatha connection to Country 9 community partnerships i ncluding ‘ She Leads, We Rise’ Indigenous women’s leadership development 4 culture capture programs enabling groups to preserve cultural knowledge A$60 m contract with AMY Nominees BHP’s largest Traditional Owner contract in SA Supporting on—country management through Ranger programs


LOGO

Partnering for the state’s future 34 Copper South Australia site tour | November 2026 Modernised regulatory framework for Olympic Dam • Updated Olympic Dam Indenture • Fit—for—purpose regulatory framework within integrated copper province • Greater certainty for long—term investment and development • M ore streamlined approval pathways for major growth projects • More contemporary environmental, heritage and rehabilitation standards Northern Water – nationally strategic infrastructure to enable significant economic uplift • Planned multi—user facility being led by government • BHP will be a foundational long—term offtake customer • Reliable water source that de—risks growth • Reduced reliance on Great Artesian Basin and Murray River • FID scheduled for 2027 and first water targeted for FY32 South Australia is a stable jurisdiction with an established regulatory framework , fiscal stability and enabling infrastructure


LOGO

Renewable electricity and more efficient material movement support lower operational GHG emissions as the province grows Operational emissions 1.32 Mt CO 2 Renewable electricity Outcome Pathway to 100% renewable electricity from FY30 Structurally abating scope 2 emissions while supporting growth in electricity demand Electrification Material moved by electric conveyors and hoists Outcome Lowering GHG emissions intensity and reducing future diesel requirements Infrastructure supports both scalable growth and decarbonisation Note: Emissions and material hoist data is FY26. FY26 emissions split sourced from BHP ESG Standards and Databook 2026. Renew abl e electricity evidenced through surrendered renewable energy certificates (RECs). 0% 42% 100% FY20 FY26 FY30 Well positioned to further decarbonise our operations 35 Copper South Australia site tour | November 2026 14% of BHP’s operational GHG emissions 26% 74% Scope 2 emissions Scope 1 emissions Emissions source ~80% 1


LOGO

Doubling production by 2040 Anna Wiley Copper South Australia Asset President Olympic Dam


LOGO

0 200 400 600 800 1,000 FY26 PHOX CXP MCG Carra SLC ramp down By 2035 Phase 2 By 2040 Copper By-product (CuEq) Our strategy to double copper production… 37 Copper South Australia site tour | November 2026 We are advancing our strategy to grow Copper SA’s production to ~500 ktpa (~800 ktpa CuEq ) by 2035 and up to 650 ktpa (~1 Mtpa CuEq ) by 2040 1 Copper South Australia production (ktpa) 14 – 17% Internal rate of return 2 US$18 – 23 k/t Capital intensity ( CuEq ) 3 Attractive indicative IRR Competitive capital intensity Phase 1 Growth Program (0.2) – 0.0 (US$/lb real) 4 Indicative FY35 unit cost +10 ktpa Cu +120 ktpa Cu +100 ktpa Cu +150 ktpa Cu Note: FY26 Copper SA production is based on FY26 actuals. See ‘Forward—looking production information: assumptions and copper eq uivalent methodology’ on slide 73. — 50 ktpa Cu Phase 1


LOGO

…through a program of integrated projects… 38 Copper South Australia site tour | November 2026 A series of complementary projects which have the potential to deliver more value than the sum of their parts CXP Carrapateena Expansion MCG OD Mine & Concentrator Growth Mines and concentrators AKO Ankata ODD Future Olympic Dam block caves (incl. OD Deeps) Mines and concentrators Enabled by Northern Water Project and upgrades to power and non—processing infrastructure SRE SRE Stage 1 ~1,100 ktpa concentrate Smelter and refinery SCM Smelter Campaign Maintenance ~360 kt cathode ~140 kt copper in concentrate SRE SRE Stage 2 Expand to between 1,400 ktpa and 1,700 ktpa concentrate Smelter and refinery ~460 kt cathode ~190 kt copper in concentrate Phase 1: Unlocking and growing to ~500 ktpa by 2035 1 Phase 2: Expanding to ~650 ktpa 1 Prominent Hill Expansion (Commissioning) PHOX Product sales Product sales Projects are at different levels of study maturity and remain subject to further study and decision .


LOGO

We are transforming the way we mine and the way we process to capture full value from Copper SA …enabled by block caving and two—stage smelting 39 Copper South Australia site tour | November 2026 • Enables large—scale mining • Maximises recovery of the mineral resource • Lowers mining unit costs • Future block caves benefit from installed infrastructure • Embeds in—house block caving capability Structurally lowers mining costs Facilitates larger scale, longer life operation • Optimised for Olympic Dam’s future mineralogy • Unlocks growth opportunities from bulk mining • Improves operational flexibility • Allows for reduced downtime during SCMs • Global standard copper smelting process • Expansion builds on existing smelting infrastructure Two—stage smelting Block caving


LOGO

Block caving drives structural mining cost improvement 40 Copper South Australia site tour | November 2026 Indicative p roduction by mining method ( ktpa ) Transition to block caving increases production while structurally lowering unit costs A structurally more productive operating model Greater fixed—cost dilution as production scales Less labour intensive than underground selective mining (SLOS) 1.6 1.0 1.7 0.7 0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 Sub—Level Cave Block Cave Sub—Level Open Stoping SLOS + Block Cave —55% —35% Carrapateena Olympic Dam More opportunity to deploy automation 256 280 280 65 220 370 321 500 650 0 200 400 600 FY26 FY35 FY40 SLOS SLC BC Mining operating cost (US$/lb Cu produced) 1 2 2


LOGO

Olympic Dam needs a two—stage smelter 41 Copper South Australia site tour | November 2026 Converting to two—stage smelting is essential to unlocking Olympic Dam’s current reserves Olympic Dam SLOS grade and Cu:S ratio (Stoping Cu:S ratio) (OD stoping copper grade) 1.0% 1.5% 2.0% 2.5% 3.0% 3.5% 1.0 1.5 2.0 2.5 3.01990 2000 2010 2020 2030 2040 2050 Cu:S ratio SLOS grade Single—stage smelter optimal economic range Northern Mining area Southern Mining Area Cu:S ratio < 1.5x Two stage required Single—stage acceptable 3.7 7.6 11.3 Planned mine production (>1.5 Cu:S Ratio) Mine production post TSS (< 1.5 Cu:S ratio) Indicative total mine production Olympic Dam ( Contained copper Reserves, Mt)


LOGO

Olympic Dam’s smelter: strategic and economic benefits 42 Copper South Australia site tour | November 2026 Presence of radionuclides requires onsite smelting, and the smelter ensures we unlock the full potential of Olympic Dam’s unique resource Economic benefits Strategic benefits T wo—stage smelting amplifies the benefits of block caving through scale and better resource utilisation Uranium and refined metal revenue adds higher margins and resilience ( FY26 by—product revenue of US$2.3 bn) Processing facilitates potentially higher value capture of the resource’s inherent commodity value: reduced uranium penalties, better copper, gold and silver payabilities, lower freight costs Processing generates sulphur/sulphuric acid products, for asset use and potential for additional revenue streams Increases BHP’s commodity diversification through increasing Copper SA’s byproduct revenue Ability to sell both cathode and concentrate Scarcity value: OECD critical minerals downstream processing infrastructure and capability


LOGO

Phased approach to growth provides flexibility 43 Copper South Australia site tour | November 2026 Copper SA can fully fund Phase 1, reducing its reliance on BHP’s iron ore cash flows and increasing BHP’s capital flexibility 1 Cumulative free cash flow (Phase 1) (US$ bn, real) 2 A lower risk Copper SA growth program which increases BHP’s capital flexibility Phase 1 capital peak ~US$3 bn (growth + sustaining) Average annual Phase 1 growth capital ~US$1.3 bn Cumulative free cash flow to 2035 ~US$9 bn (consensus price) 0 2.0 4.0 6.0 8.0 10.0 FY27 FY28 FY29 FY30 FY31 FY32 FY33 FY34 FY35


LOGO

Delivering on Copper SA’s potential 44 Copper South Australia site tour | November 2026 An opportunity to expand Copper SA’s production and lower its costs Copper production Copper cost curve 2 (C1, US$/lb, real) Copper equivalent production 1 (kt CuEq) 0 200 400 600 800 1,000 1,200 1,400 1,600 Copper SA 2040 Copper SA 2035 Escondida Grasberg KGHM Polska Tenke Fungurume Copper SA today Buenavista Oyu Tolgoi Las Bambas Cerro Verde Escondida Copper SA 2040 2 Copper SA today Antamina Copper SA 2035 2 Peers Copper SA 6.00 —1.00 —5.00 —4.00 —3.00 —2.00 0.00 2.00 3.00 4.00 5.00 1.00 100% 75% 50% 25% Copper SA future 1 st quartile cost position 3


LOGO

A growth program that leverages prior learnings 45 Copper South Australia site tour | November 2026 We are applying the lessons of the past to deliver the next stage of Copper SA’s growth Deep market for concentrate creates product flexibility : Strong concentrate sales enables capital efficient expansion of smelter in multiple phases Copper SA needs a two—stage smelter : Smelter expansion project FID in CY27 Staged growth program creates optionality : Sequenced projects with program—level and project level capital discipline Bulk mining will unlock substantial incremental value : Commencing block caving at Carrapateena and Olympic Dam Identified critical enablers and the actions we are taking


LOGO

A phased and integrated series of investments Carrapateena Jim McCluskey Copper South Australia General Manager Planning, Technical & Environment


LOGO

CXP Carrapateena Expansion MCG OD Mine & Concentrator Growth Mines and concentrators AKO Ankata ODD Future Olympic Dam block caves (incl. OD Deeps) Mines and concentrators Enabled by Northern Water Project and upgrades to power and non—processing infrastructure SRE SRE Stage 1 ~1,100 ktpa concentrate Smelter and refinery SCM Smelter Campaign Maintenance ~360 kt cathode ~140 kt copper in concentrate SRE SRE Stage 2 Expand to between 1,400 ktpa and 1,700 ktpa concentrate Smelter and refinery ~460 kt cathode ~190 kt copper in concentrate Phase 1: Unlocking and growing to ~500 ktpa by 2035 1 Phase 2: Expanding to ~650 ktpa 1 Prominent Hill Expansion (Commissioning) PHOX Product sales Product sales Phase 1: Growing to ~500 ktpa Cu and ~800 ktpa CuEq 47 Copper South Australia site tour | November 2026 A series of complementary projects which deliver more value than the sum of their parts Projects are at different levels of study maturity and remain subject to further study and decision .


LOGO

Phase 1: Prominent Hill Expansion (PHOX) 48 Copper South Australia site tour | November 2026 FY26 actual Post ramp up Mine production (Mtpa) 4.4 7.5 Concentrator capacity (Mtpa) 11 11 Avg mining costs (US$/lb Cu produced) 2 2.8 2.3 Avg copper feed grade (% Cu) 2 0.8% 0.9% Mine life (years) 9 ~20 3 P HOX extends mine life by 10 years more than original expansion plan, increases production and provides additional smelter fee d o ptionality Project overview 1 • Execution complete. Commissioning in December 2026 • Includes electrical hoisting shaft, underground crusher and materials handling system • Transforms Prominent Hill from a truck haulage to shaft hoisting – Increases annual mine production – Extends mine life – Lower operating costs due to hoisting – Reduction in carbon emissions from lower truck movements Capex (US$ bn, real) Total Cu / CuEq production 1 (ktpa) First production $0.9 ( forecast final cost ) ~60 / 100 H 2 CY26 Note : Cu / CuEq production relate to 10 year averages post ramp up .


LOGO

Phase 1: Carrapateena Expansion (CXP) 49 Copper South Australia site tour | November 2026 FY26 actual Post ramp up Mine production (Mtpa) 6.4 12 Concentrator capacity (Mtpa) 7 12 Avg mining costs ( US$/lb Cu produced ) 3 1.7 0.7 Avg copper feed grade (% Cu) 3 1.2% 1.1% Mine life (years) 16 ~30 4 Project overview 1 • Mining : Block cave ~450 m below existing Sub Level Cave – Completed decline to ~1,400 m extraction level – First drawbell targeted for early FY30; ~3 year ramp up • Processing : New materials handling, underground crusher and concentrator – New 5 Mtpa concentrator design replicates existing 7 Mtpa concentrator; commissioning targeted FY31 • US$366 m pre — commitment funding approved for mine development works and enabling infrastructure • Future options : Second block cave; Carrapateena Deeps The blueprint for block caving at BHP, extends life and lowers mining costs Capex (US$ bn, real) Capex intensity (US$k/CuEq t) IRR 2 (%) Total Cu / CuEq 1 (ktpa) FID First production $1.8 – 2.1 13 – 15 19 – 22 ~100 / 140 H1 CY28 FY30 Note : Cu / CuEq production relate to 10 year averages post ramp up .


LOGO

Olympic Dam: Mine & Concentrator Growth Phase 1: Olympic Dam Mine & Concentrator Growth (MCG) 50 Copper South Australia site tour | November 2026 FY26 actual Post ramp up OD mine production (Mtpa) ~11 ~21 OD concentrator capacity (Mtpa) ~11 ~22 OD avg mining cost ( US$/lb Cu produced ) 3 1.6 1.0 OD avg copper feed grade (% Cu) 4 2.0% 1.6% OD mine life (years) 40 ~80 5 Unlocking the full potential of the Mineral Resource through a low — cost mining method Project overview 1 • Southern Mine Area Decline already in execution • 11 Mtpa SLOS mining @ 1.9% Cu head — grade will continue as per existing operations • Hydromet expansion increases U 3 O 8 production capacity by ~50% • Scalable block — cave mining structurally reduces mining costs and leverages the resource • We are continuing to study the optimal size for the MCG block cave – Option 1: 10 Mtpa block cave with FY34 cave and concentrator ramp up – Option 2: Bigger cave with earlier concentrator ramp up • Crush — convey, concentrator and non — process infrastructure benefits future block caves, enabling longer — term growth Capex (US$ bn, real) Capex intensity (US$k/CuEq t) IRR 2 (%) Project Cu / CuEq (ktpa) 2 FID First production $4.1 – 5.4 22 – 28 13 – 15 ~120 / 190 CY29 FY34 Southern Mine Area Decline + Ore — to — surface extension Current SLOS operation MCG Block Cave Potential future block caves Note: Operational and financial metrics relate to the MCG block cave Option 1 and are subject to further studies . Cu / CuEq figures relate to 10 year averages post ramp up.


LOGO

FY26 results basis 1 Current focus of studies 1 We are continuing to study the optimal size for the MCG block cave — a preferred alternative is expected to be determined in the next 12 months Phase 1: Olympic Dam Mine & Concentrator Growth (MCG) 51 Copper South Australia site tour | November 2026 Scale Production (Mtpa) 10 Up to 15 New Concentrator capacity (Mtpa) ~11 Up to 16 Hydromet uranium processing Potential cave expansion (%) ~ +35% Production Concentrator first production FY34 FY32 – FY33 Cave first production FY34 FY33 – FY 34 Copper SA Phase 1 production: 450 ktpa copper FY35 FY33 500 ktpa copper FY35 FY35 Cave production profile (Cu ktpa) 2 (CuEq ktpa) 120 (190) Up to 140 (Up to 230) Economics Capex (US$ bn) 3 ~4.7 ~5.6 Capital intensity (US$k/t CuEq) ~25 ~24


LOGO

Project overview 1 • Build new primary flash smelting furnace and acid plant • Convert existing direct — to — blister furnace to become secondary flash converting furnace • Expand capacity of electrolytic refinery and precious metals refinery • Low — capital, future expansion scope included • ~3 years smelter construction period; <1 month connection downtime Phase 2: Potential expansion to 1,400 ktpa is low capital (~US$0.7 bn) Phase 1: Smelter and Refinery expansion (SRE) 52 Copper South Australia site tour | November 2026 Brownfield, modular expansion of the smelter and refinery has been sized to maximise value and lower upfront capital Capex (US$ bn, real) FID First production $3.2 – 4.1 bn H2 CY27 FY32 Two — stage smelter sizing (Copper SA c oncentrate production, ktpa) 0 500 1,000 1,500 2,000 FY27—FY31 Average Post Phase 1 ramp up Post Phase 2 ramp up OD SLOS OD MCG Phase 2 PHOX CXP 1,400 1,100 ~ 550 (Current) 1,700 Phase 2 range Phase 1 Sold in market 1 1


LOGO

Growing gold, uranium and silver 53 Copper South Australia site tour | November 2026 By — products will increase by ~50% to 300 ktpa CuEq by 2035, improving economics and enhancing margin resilience 1 0 50 100 150 200 250 300 350 400 FY26 FY35 ~FY40 Gold Silver Uranium Copper equivalent production 2 (ktpa) +50% Total by — product copper equivalent production to increase 50% by 2035: – Gold production to increase 45% to >570 ktozpa – Uranium production to increase 65% to ~6 ktpa – Silver production to increase 40% to >2,800 ktozpa Copper SA’s 300 ktpa CuEq production of by — products by 2035 would make it a mid — sized global copper mine Aspiration to increase by — product production to ~350 ktpa CuEq by 2040 — increase of ~150 ktpa CuEq which is more than many peers’ total copper growth ambition 1 2 3


LOGO

CXP Carrapateena Expansion MCG OD Mine & Concentrator Growth Mines and concentrators SRE SRE Stage 1 ~1,100 ktpa concentrate Smelter and refinery SCM Smelter Campaign Maintenance ~360 kt cathode ~140 kt copper in concentrate Prominent Hill Expansion (Commissioning) PHOX Product sales Phase 1: Unlocking and growing to ~500 ktpa by 2035 1 AKO Ankata ODD Future Olympic Dam block caves (incl. OD Deeps) Mines and concentrators Enabled by Northern Water Project and upgrades to power and non — processing infrastructure SRE SRE Stage 2 Expand to between 1,400 ktpa and 1,700 ktpa concentrate Smelter and refinery ~460 kt cathode ~190 kt copper in concentrate Phase 2: Expanding to ~650 ktpa 1 Product sales Phase 2: Growing to 650 ktpa copper and 1 Mt CuEq 54 Copper South Australia site tour | November 2026 A series of complementary projects which deliver more value than the sum of their parts Projects are at different levels of study maturity and remain subject to further study and decision .


LOGO

Phase 2: Growth potential at Olympic Dam 55 Copper South Australia site tour | November 2026 Project overview • Stoping (SLOS) can be sustained at 11 Mtpa until 2050+ • Subsequent increase up to 40 Mtpa from underground bulk mining methods are being assessed once SLOS inventories are depleted Potential for multiple cave options leverage the resource to sustain up to 40 Mtpa mine production at Olympic Dam 1 Potential future block caves based on declared Mineral Resources Indicative mine production 2 (Mtpa) Southern Mine Area Decline + Ore — to — surface extension Current SLOS operation MCG Block Cave Potential future block caves Olympic Dam: Indicative Block Cave Development Potential Potential block cave 1 Potential block cave 2 Potential block cave 3 MCG block cave Current SLOS operation 2026 2030 2040 2050 2060 2070 2080 2090 2100


LOGO

Phase 2: Growth potential at Ankata (formerly Oak Dam) 56 Copper South Australia site tour | November 2026 Project overview 1 • 8.8 Mt contained copper Mineral Resource assumes bulk underground mining (such as block caving); • 49% larger resource tonnage than Carrapateena • Drilling programs have focused on two areas: – Infill existing mineral resource – Extensional drilling in the northern areas • ~173 km of drilling since resource released in 2024 • Updated resource expected in CY27 • Retention Lease granted; Progressing toward FID for UG Access (Decline) in CY27 Ankata provides high grade growth optionality, at depth A’ A Z X Y ISOMETRIC VIEW NEW DRILLING SINCE INITIAL RESOURCE EXISTING INFERRED RESOURCE EXISTING DRILLING (CURRENT REPORTED RESOURCE) INTERNAL HEMATITE CORE Capex (US$ bn, real) Capex intensity (US$k/CuEq t) IRR (%) Total Cu / CuEq 2 (ktpa) FID First production $4.5 – 5.8 20 — 26 N/A ~190 / 230 CY32 CY38 Potential Phase 2 (ODD or Ankata) Note: Financial metrics relate to the bulk underground mining subject to further studies .


LOGO

0 200 400 600 800 1,000 1,200 1,400 1,600 Copper 2035 Escondida Grasberg KGHM Polska Miedz Tenke Fungurume Antamina SA today Buenavista Oyu Tolgoi Las Bambas Cerro Verde Phase 2: Creating one of the world’s premier copper assets 57 Copper South Australia site tour | November 2026 Our development plan for Copper SA will create an asset o f Escondida’s relevance to BHP, and a platform for decades of value Copper SA today Copper equivalent production 1 (kt CuEq ) Copper SA 2040 2


LOGO

Project execution Pedram Ittehadi Copper South Australia Head of Major Projects Prominent Hill


LOGO

0% 20% 40% 60% 80% 100%0% 20% 40% 60% 80% 100% BHP’s project execution track record is solid… 59 Copper South Australia site tour | November 2026 • BHP’s project delivery track record is strong – 80% of projects on time and on budget since 2016 – Best of diversified miners • Project execution is increasingly complex – New geographies and higher elevation present new challenges – Increasing competition for scarce expertise – Additional headwinds: inflation, freight, approvals, extended procurement lead times We are building from a solid foundation of project delivery Project delivery track record 1 (2016 – 2026) Source: Bloomberg Intelligence Unit. Peers include Anglo American, Glencore, Rio Tinto and Vale. Considers projects with disclosed ca pit al expenditures above US$300 m. 1 BHP Peers % of projects on budget % of projects on time 5 20 10 Combined projects capex (US$ bn) 2 Mostly on time Mostly on budget Including Jansen 3


LOGO

…and we are improving our delivery of major projects 60 Copper South Australia site tour | November 2026 While many issues with Jansen were unique to that project, there are valuable lessons for major project delivery What we are doing differently in South Australia Challenges at Jansen • Ineffective contract management • Design development and scope changes during execution • Optimistic productivity and quantity estimates • Inflationary and real cost pressure • EPCM model suited to Copper SA projects • Proven designs and modularisation techniques from leading OEMs • Regular independent reviews of execution against plan • Embedding BHP’s Projects System


LOGO

We have a strategic plan that we are already executing 61 Copper South Australia site tour | November 2026 We have awarded >US$ 3 bn of major contracts and have a strategy for the known project execution challenges Carrapateena Crusher 2 Completed Prominent Hill Expansion (PHOX) Commissioning Southern Mine Area Decline (SMAD) ~50% complete Laying the foundations for Phase 1 1,600 new construction camp rooms ~70% complete Partnering with the best Modularisation and standardisation Grouping projects by work type to extract synergies Key execution strategies… … which also address possible challenges regarding labour availability Phase 1 design and engineering >2 m design hours completed


LOGO

Phase 1 Capex: US$5.8 – 7.5bn Phase 1 Capex: US$3.2 – 4.1bn Capex: Sustaining and growth Mines and Concentrators Smelter Enabling projects Grouping projects by work type to extract synergies 62 Copper South Australia site tour | November 2026 We have separated upcoming projects into 3 core work types to improve delivery outcomes 1 Block cave, materials handling, surface processing and TSF EPCM with D&S package and construction contractors Accommodation, site infrastructure and logistics    Fit — for — purpose Each program can select the delivery and contractor model to suit scope    Economies of scale Shared teams, common equipment and program — wide sourcing    Replication Standard designs and repeatable delivery across similar facilities Competitive tension Creates performance incentives across delivery partners CXP MCG SRE SCM NPI Core work types


LOGO

Partnering with the best 63 Copper South Australia site tour | November 2026 Our delivery partners have proven capability across underground, processing, engineering design and delivery 1 Core work types | Project partners Block caves : Worley has direct experience with recent block cave operations Delivered six underground programs globally since 2016 including Oyu Tolgoi Delivering significant cost savings against local benchmarks 7 / 10 recent high — throughput copper smelters globally Smelter design: Nerin appointed to design significant aspects of SRE facilities Phase 1 Capex: US$5.8 – 7.5bn Phase 1 Capex: US$3.2 – 4.1bn Capex: Sustaining and growth Mines and Concentrators Smelter Enabling projects Block cave, materials handling, surface processing and TSF EPCM with D&S package and construction contractors Accommodation, site infrastructure and logistics CXP MCG SRE SCM NPI


LOGO

Install predictably Modularisation and standardisation 64 Copper South Australia site tour | November 2026 Modularisation, pre — fabrications and replication reduce site labour, interfaces and schedule risk, and enhance safety Faster Reduce bespoke design/engineering and speed up installation Cheaper Standardisation & replication Minimise people on site and travel Safer Improved installation methods and reduced site congestion Design early for delivery Set modularisation categories, logistics during early engineering Standardise design, equipment and vendor selection supporting scale Use proven module yards, pre — cast, pre — assembly and skid — mounted equipment Smaller site crews, fewer interfaces and repeatable installation methods improve efficiency and safety Standardise Fabricate offsite


LOGO

Key takeaways 65 Copper South Australia site tour | November 2026 BHP has a strong project execution track record We have secured tier 1 partners with proven capability in block caving and smelter design and construction We are embedding lessons from Jansen across our projects portfolio, including in South Australia Our modular execution approach is safer, cheaper and faster We have a strategic plan for delivery of the South Australian growth program which we are executing


LOGO

BHP SUMMARY


LOGO

Our strategy to double copper production 67 Copper South Australia site tour | November 2026 We have a strategy to deliver 500 ktpa Cu (~800 ktpa CuEq) 1 by 2035 and ~650 ktpa Cu (~1 Mtpa CuEq) by 2040 1 Copper South Australia production (ktpa) 14 – 17% Internal rate of return 2 US$18 – 23 k/t Capital intensity ( CuEq ) 3 Attractive indicative IRR Competitive capital intensity Phase 1 Growth Program (0.2) – 0.0 (US$/lb real) 4 Indicative FY35 unit cost 0 200 400 600 800 1,000 FY26 PHOX CXP MCG Carra SLC ramp down By 2035 Phase 2 By 2040 Copper By-product (CuEq) Phase 1 +10 ktpa Cu +120 ktpa Cu +100 ktpa Cu +150 ktpa Cu — 50 ktpa Cu Note: FY26 Copper SA production is based on FY26 actuals. See ‘Forward — looking production information: assumptions and copper eq uivalent methodology’ on slide 73.


LOGO

Key messages Copper South Australia site tour | November 2026 68 A strong plan to double copper production by 2040 through block caving and two-stage smelting Copper SA is a more stable and consistent operation, providing a stronger basis for investment Tier 1 resource, 100% owned We have a strategy to deliver ~500 ktpa copper by 2035 and to double production by 20401, enabled by block caving and two-stage smelting Phased approach to growth which leverages modularisation and ‘best in class’ partners to lower risk Self-funded Phase 1 capital program with low capital intensity ($18—23k/t2 CuEq) and program IRR 14-17%3 By-products add margin resilience—potential for ~1 Mt CuEq by 20401


LOGO

BHP


LOGO

Footnotes 70 Copper South Australia site tour | November 2026 Copper and its place within BHP Slide 7 – BHP’s portfolio sits within attractive mining jurisdictions (1) First production from Jansen Stage 1 is expected to be delivered in mid — CY 27 . Jansen Stage 2 production is expected in FY 31 . Full production from Stage 1 and Stage 2 is expected to be 8 . 5 Mtpa . Once fully ramped up, production at Jansen (Stage 1 and 2 ) is expected to exceed the current capacity of the other largest potash mines in Canada, Rocanville and Esterhazy, based on publicly available financial information . (2) For the ASX Mineral Resource for the Resolution Copper project, refer to the Mineral Resources and Ore Reserves in the BHP Annual Report 2026 . BHP declared an ASX Mineral Resource for Resolution of 1 . 86 billion tonnes at 1 . 52 % copper for the first time in FY 26 . U . S . investors are advised to refer to the mineral resources and mineral reserves presented in the BHP annual report on Form 20 — F, filed with the U . S . Securities and Exchange Commission (SEC), which presents estimates prepared in accordance with SEC regulations Subpart 1300 of Regulation S — K . (3) World’s largest copper mine refers to the Compiled Copper Mineral Resources as at 1 September 2026 on slide 82 — 84 . Antamina is a top 10 copper producer, based on S&P Capital IQ data for 2025 . (4) Vicuña has the potential to be a t op 5 copper and gold producer based on 10 — year average once Stage III fully ramped up with ~ 500 ktpa of copper and ~ 800 kozpa of gold . (5) BHP internal analysis based on WAIO C 1 reported unit costs compared to publicly available unit costs reported by major competitors (including Vale, Fortescue and Rio Tinto), adjusted based on publicly available financial information . (6) BMA production shown on a 100 % basis and PHCC production based on the Wood Mackenzie 2025 dataset . Slide 8 – Commodity selection drives value in mining (1) Cost curves for each commodity shown as follows : i) Iron ore – 2026 all — in adjusted costs (US $ / dmt 61 % Fe equivalent, CFR China) ; ii) Copper – 2026 C 1 costs (net of by — products) ; iii) Steelmaking coal – 2026 value — in use all — in sustaining costs for the seaborne market ; iv) Potash – 2035 FOB operating cost including royalties . Source for iron ore, copper and steelmaking coals : Wood Mackenzie’s 2026 cost curves . Source for potash : BHP analysis, macroeconomic assumptions and CRU . The numbers in circles are equivalent to the 90 — 95 th percentile producer divided by the 25 th percentile producer . (2) Market sizes consider demand for 2025 and average prices from 2015 to 2025 . Source : BHP analysis . Slide 9 – Forecast copper demand growth requires new supply … (1) Source: BHP analysis. Note: Traditional end uses for copper demand reflects building, construction and other uses linked to g ene ral industrialisation / urbanisation. Non — traditional uses include decarbonisation, digitalisation and data centre investment. (2) Source: Wood Mackenzie Q3 2026 global copper supply / demand (includes base mine production adjusted for implied smelter recoveries, and mine disruptions) (3) Source for Historical: BHP analysis. Source for Forecast: Wood Mackenzie Q3 2026 global copper supply / demand (includes dire ct — use scrap and secondary). (4) Source: BHP analysis. CAGR from 2026 — 2040. Slide 10 – … and new mine supply is becoming more challenging (1) Source : Average historic projects capital intensity ( 2001 – 2025 ) : Wood Mackenzie Projects Q 3 2026 . Average capital intensity ( 2026 — 2035 ) : Wood Mackenzie, weighted average of greenfield base and probable projects Q 3 2026 . (2) Source : Wood Mackenzie Production Q 3 2026 all mines . (3) Source : Wood Mackenzie Margins and Capex Q 3 2026 , growth capex related to expansion capex only . Real conversion of capital intensities : BHP analysis . Slide 11 – BHP is already the world’s largest listed copper producer … (1) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . (2) Source : S&P Global Market Intelligence attributable copper production 2026 . ‘BHP today’ as at 30 June 2026 . Slide 12 – … with an attractive pathway to grow to 2 Mtpa Cu by 2035 … (1) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and FID . (2) Potential FID as early as end of 2026 for Vicuña Stage 1 . (3) Total production out of the facility . Average after ramp — up — FY 34 to FY 43 ENC specific production . (4) Represents potential production output from Spence SCPY and ripios dump projects, plus Cerro Colorado restart . (5) For the ASX Mineral Resource for the Resolution Copper project, refer to the Mineral Resources and Ore Reserves in the BHP Annual Report 2026 . U . S . investors are advised to refer to the mineral resources and mineral reserves presented in the BHP annual report on Form 20 — F, filed with the U . S . Securities and Exchange Commission (SEC), which presents estimates prepared in accordance with SEC regulations Subpart 1300 of Regulation S — K . Slide 13 – … and funded entirely from Copper’s operating cash flows (1) We use various non — IFRS financial information to reflect our underlying financial performance . Non — IFRS financial information (as outlined in ASIC Regulatory Guide 230 ) is not defined or specified under the requirements of IFRS, but is derived from the Group’s Consolidated Financial Statements prepared in accordance with IFRS . For a complete list of Non — IFRS financial information and their respective definitions and calculation methodology, please refer to OFR 8 – Non — IFRS information in the BHP Annual Report 2026 . Non — IFRS financial information is unaudited . Copper segment free cash flows on this slide are presented on an attributable basis . Segment and asset level free cash flow excludes centrally managed interest and taxes reported under Group and Unallocated (G&U) . (2) Note : See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . (3) Free cash flow is a non — IFRS financial measure . Segment and asset cash flows exclude centrally managed interest and taxes reported in Group and Unallocated (G&U) . The analysis therefore does not represent Group cash available after all centrally managed tax and financing costs . (4) Average of CY/FY 2026 and 2027 . FCF break — even copper price calculated as the spot copper price that implies zero FCF for Cu segment for that year . For BHP full portfolio — FCF break — even copper price at consensus iron ore US $ 91 /t . This is an illustrative BHP Group portfolio measure reflecting cash flows from BHP’s diversified portfolio . It is not a standalone copper segment, asset operating cost or break — even price . (5) US $ 5 /lb calculated using median UBS long term consensus prices as of July 2026 . (6) FCF break — even copper price at consensus iron ore US $ 91 /t . Slide 14 – Key takeaways (1) Largest listed copper producer globally based on S&P Global Market Intelligence 2026 attributable copper production data . (2) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and FID . (3) Represents total targeted incremental copper production growth at Copper SA, relative to total targeted incremental copper production growth for the BHP Group between FY 27 and FY 35 .


LOGO

Footnotes (continued) 71 Copper South Australia site tour | November 2026 Introduction to Copper South Australia Slide 16 – Copper SA: A world class copper, gold and uranium asset (1) Mine life is estimated based on Ore Reserves and Mineral Resources and subject to conversion of resources into reserves and assuming a nominal production rate, as at 30 June 2026 . (2) Olympic Dam contained copper resource based on the updated Mineral Resource disclosed in BHP FY 27 Q 1 Operational Review, Appendix 3 . Contained metal is the metal estimated to occur within the reported resource ; it is not an estimate of recoverable or saleable production . (3) Source : S&P Global Market Intelligence . (4) Map shows listed, non — state — owned companies to highlight potential investment . Slide 18 – …with a locally based workforce with deep expertise (1) Source : Australian Bureau of Statistics 2026 as of September 2026 and BHP analysis . (2) Based on a ‘point in time’ snapshot of employees as at 8 November 2026 . Slide 19 – Success is everyone going home safe and well (1) High — potential injuries (HPIs) are recordable injuries and first aid cases where there was the potential for a fatality . Slide 20 – We have integrated Carrapateena and Prominent Hill (1) Original estimate based on synergy expectation of >US $ 50 m pa disclosed in the FY 23 acquisition presentation . Slide 21 – Diversified markets for copper and by — products (1) Concentrate grade range for Prominent Hill and Carrapateena from 30 June 2024 — 30 June 2026 . Slide 23 – A number of strategic decisions have already been made (1) Reflects strategic decision — making . Projects are at different levels of study maturity and remain subject to further study and decision . Improving operational and financial performance Slide 26 – BOS and technology are improving operational stability… (1) The BHP Operational Excellence Index (OEI) assessments are conducted by a team of internal BHP assessors trained and coached by senior McKinsey OEI assessors . They use McKinsey’s dedicated maturity assessment tool, process and system which is similar in nature to the Shingo Prize assessments and benchmarked across more than 1 , 200 individual assessments . There are approximately 70 global companies actively using the McKinsey benchmarking tool today . OEI chart reflects data as of August 2026 . (2) McKinsey’s OEI provides a benchmark for establishing operational performance baselines and measuring improvements over time . A score above 55 (out of 100 ) is among the best operational — excellence organisations in the world . 79 is the maximum score achieved by any organisation using the McKinsey assessment tool . (3) Prominent Hill and Carrapateena mines were acquired May 2023 . Slide 28 – Production is now more stable and at record levels… (1) CuEq calculated using UBS fixed long — term consensus prices as of May 2026 : copper US $ 4 . 76 /lb, gold US $ 3 , 354 / toz , silver US $ 45 / toz , uranium US $ 82 /lb . See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . (2) Wood Mackenzie Production Q 3 2026 historical nominal copper price . Enduring connections Slide 32 – Creating shared value across South Australia (1) Source: Deloitte Access Economics analysis based on information from FY25. Slide 35 – Well positioned to further decarbonise our operations (1) For FY26, 42% is calculated including RECs surrendered both voluntarily and to meet renewable energy — related compliance obligations across all Copper SA sites. The FY26 actual percentage of Copper SA renewable electricity consumption under a Pow er Purchase Agreement is 30%, reflecting surrendered RECs supplied by the Neoen Power Purchase Agreement for Olympic Dam. The 35% previously disclosed was calculated including RECs surrendered voluntarily across all Copper SA sites but included compliance — related RECs for Olympic Dam only. Doubling production by 2040 Slide 37 – Our strategy to double copper production … (1) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and decision . (2) Nominal basis, inclusive of CXP, MCG and SRE . Calculations based on median July 2026 UBS long term consensus price deck : Copper US $ 5 . 00 /lb, gold US $ 3 , 500 / toz , silver US $ 46 / toz and uranium US $ 85 /lb . (3) Capital intensity includes Carrapateena and Mine & Concentrator Growth only . (4) Real Jan 27 basis . Indicative only – shown for illustrative purposes . FY 35 indicative unit cost based on the same FX and by — product price assumptions as FY 27 unit cost guidance for Copper SA . Also assumes : 1 ) 500 kt copper production, 2 ) 300 kt of CuEq by — product production 3 ) mining costs reflect those presented on slide 40 . Slide 38 – … through a program of integrated projects … (1) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and FID . Slide 40 – Block caving drives structural mining cost improvement (1) Excludes processing, smelting, refining and all other operating costs . See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and decision . (2) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and decision . Slide 43 – Phased approach to growth provides flexibility (1) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and FID . (2) Free cashflow calculated on median July 2026 UBS long term consensus price deck : Copper US $ 5 . 00 /lb, gold US $ 3 , 500 / toz , silver US $ 46 / toz and uranium US $ 85 /lb . Slide 44 – Delivering on Copper SA’s potential (1) Source : S&P Global Market Intelligence Capital IQ CY 2025 consolidated production . BHP assets as at 30 June 2026 . Copper equivalent production calculated using median long run consensus prices as of July 2026 : copper US $ 5 . 00 /lb, gold US $ 3 , 500 / toz , silver US $ 46 / toz , uranium US $ 85 /lb, molybdenum US $ 20 /lb, cobalt US $ 19 /lb, zinc US $ 1 . 3 /lb, lead US $ 0 . 9 /lb (2) Source : Wood Mackenzie, BHP analysis . (3) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and decision .


LOGO

Footnotes (continued) 72 Copper South Australia site tour | November 2026 A phased and integrated series of investments Slide 47 – Phase 1: Growing to ~500 ktpa Cu and ~800 ktpa CuEq (1) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and FID . Slide 48 – Phase 1: Prominent Hill Expansion (PHOX) (1) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and decision . (2) 5 — year average post ramp up . (3) Life of Mine extension post project completion . Slide 49 – Phase 1: Carrapateena Expansion (CXP) (1) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and FID . (2) Nominal basis . Calculations based on median July 2026 UBS long term consensus price deck : Copper US $ 5 . 00 /lb, gold US $ 3 , 500 / toz , silver US $ 46 / toz and uranium US $ 85 /lb . (3) 5 — year average post ramp up . (4) Life of Mine extension post project completion . Slide 50 – Phase 1: Olympic Dam Mine & Concentrator Growth (MCG) (1) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and decision . (2) Nominal basis . Calculations based on median July 2026 UBS long term consensus price deck : Cu $ 5 . 00 /lb, gold $ 3 , 500 /oz, silver $ 46 and uranium $ 85 /lb . (3) 10 — year average post ramp up . (4) 5 — year average post ramp up . (5) Life of Mine extension post project completion . Slide 51 – Phase 1: Olympic Dam Mine & Concentrator Growth (MCG) (1) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and FID . (2) 10 — year average post ramp up . (3) Capital estimates represent the mid — point of capex guidance range shown on slide 50 for ‘FY 26 results basis’ . Slide 52 – Smelter and Refinery expansion (SRE) (1) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and FID . Slide 53 – Growing gold, uranium and silver (1) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and FID . (2) Calculated based on median July 2026 UBS long term consensus price deck : gold US $ 3 , 500 / toz , silver at US $ 46 / toz and uranium at US $ 85 /lb . Slide 54 – Phase 2: Growing to 650 ktpa copper and 1 Mt CuEq (1) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and decision . Slide 55 – Phase 2: Growth potential at Olympic Dam (1) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and FID . (2) Indicative mine production is based on the SA copper mineral resource estimates in the measured, indicated and inferred category divided by the assumed production rates in the figure . This figure is conceptual in nature and is intended to illustrate the potential life of the SA copper mineral resource estimates . It is not an aspiration, production target or forecast . Slide 56 – Phase 2: Growth potential at Ankata (formerly Oak Dam) (1) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and FID . Slide 57 – Phase 2: Creating one of the world’s premier copper assets (1) Source : S&P Global Market Intelligence Capital IQ CY 2025 consolidated production . BHP assets shown as of 30 June 2026 . (2) See ’Forward — looking production information : assumptions and copper equivalent methodology’ on slide 73 . Projects are at different levels of study maturity and remain subject to further study and FID . Project execution Slide 59 – BHP’s project execution is strong (1) Per Bloomberg Intelligence, data is as of 31 July 2026 and based on a sample including 5 — 6 projects per company that i) were commissioned from 2016 onwards ; ii) have disclosed capital expenditures above US $ 300 m ; and iii) have sufficient public disclosure to assess delivery against original budget and schedule . Projects are considered on time if commissioned within 6 months of the original schedule . Projects are considered on budget if the latest capital expenditure budget is within 11 % of the initial budget . The evaluated sample represents ~US $ 80 bn of aggregate project capital expenditures . (2) Size of dotted circles are approximate representations of the capital expenditures in the chart data . (3) Analysis considers Jansen Stage 1 . Summary Slide 67 – Our strategy to double copper production (1) See ‘Forward — looking production information: assumptions and copper equivalent methodology’ on slide 73. Projects are at differe nt levels of study maturity and remain subject to further study and FID. (2) Nominal basis, inclusive of CXP, MCG and SRE . Calculations based on median July 2026 UBS long term consensus price deck : Copper US $ 5 . 00 /lb, gold US $ 3 , 500 / toz , silver US $ 46 / toz and uranium US $ 85 /lb (3) Comprises mines and concentrator capital only . Capital intensity range based on lower and upper ends of capital expenditure guidance . (4) Real Jan 27 basis . Indicative only – shown for illustrative purposes . FY 35 indicative unit cost based on the same FX and by — product price assumptions as FY 27 unit cost guidance for Copper SA . Also assumes : 1 ) 500 kt copper production, 2 ) 300 kt of CuEq by — product production 3 ) mining costs reflect those presented on slide 40 . Slide 68 – Key messages (1) See ‘Forward — looking production information: assumptions and copper equivalent methodology’ on slide 73. Projects are at differe nt levels of study maturity and remain subject to further study and FID. (2) Carrapateena and Olympic Dam mines and concentrator capital only. Low/high total capital used for range. (3) Nominal basis, inclusive of CXP, MCG and SRE. Calculations based on median July 2026 UBS long term consensus price deck: Copper US$5.00/lb, gold US$3,500/ toz , silver US$46/ toz and uranium US$85/lb. See ‘Forward — looking production information: assumptions and copper equivalent methodology’ on slide 73. Projects are at different levels of study maturity and remain sub jec t to further study and FID.


LOGO

Footnotes 73 Copper South Australia site tour | November 2026 Forward — looking production information, assumptions and copper equivalent methodology Only information expressly identified as production guidance or a production target constitutes BHP production guidance or a production target, as applicable . Unless otherwise stated, information is not intended to be a projection, forecast or production target . All other forward — looking production figures, ranges, growth rates, capacities, profiles and pathways in this presentation represent BHP’s current aspirations or illustrative pathways, as applicable, including the (i) the estimated ~ 5 % Copper segment CuEq CAGR over that period ; (ii) the pathway to ~ 2 Mtpa of attributable group copper production by 2035 ; (iii) the Copper South Australia and Vicuña future production profiles ; and (iv) Copper South Australia Phase 1 and Phase 2 growth project development examples . These statements reflect BHP’s current intention and aspirations for future copper production and are not intended to be predictive in nature (and should not be relied upon as such) . Unless otherwise stated, the following assumptions apply to the forward — looking production information in this presentation : • Copper segment CuEq growth from FY 27 to FY 35 is based on BHP’s attributable share of production from BHP’s copper assets and from non — operated joint ventures . Copper equivalent production for this aspiration includes contribution from by — products and is calculated using UBS long term consensus prices as of May 2026 of US $ 4 . 76 /lb for copper, US $ 3 , 354 / toz for gold, US $ 45 / toz for silver, US $ 17 /lb for molybdenum and US $ 8 2 /lb for uranium . • Copper South Australia CuEq growth from FY 27 to FY 40 includes contribution from by — products and is calculated using median UBS long term consensus prices as of July 2026 of US $ 5 . 00 /lb for copper, US $ 3 , 500 / toz for gold, US $ 46 / toz for silver, US $ 85 /lb for uranium . • Copper equivalent production for peer analysis includes contribution from by — products and is calculated using median UBS long term consensus prices as of July 2026 of US $ 5 . 00 /lb for copper, US $ 3 , 500 / toz for gold, US $ 46 / toz for silver, US $ 85 /lb for uranium, US $ 20 /lb for molybdenum, US $ 19 /lb for cobalt, US $ 1 . 3 /lb for zinc and US $ 0 . 9 /lb for lead . Unless otherwise stated, forward — looking production information includes potential increases in production rates, as well as potential production from BHP’s assets and non — operated joint ventures and exploration, and is subject to the completion of technical studies to support Mineral Resource and Ore Reserves estimates, capital allocation, regulatory approvals, market capacity, and, in certain cases, the development of exploration assets, which factors are uncertain . The Phase 2 aspirational growth at Copper South Australia includes Inferred Resources from Ankata and exploration studies at OD Deeps . The production profiles and associated financial information for the Phase 1 and Phase 2 growth projects for Copper South Australia are not guidance and are only intended to be an indicative example of future aspirational production capacity and economic outcomes for Copper South Australia following completion of those growth projects . Project — specific Vicuña CuEq information is presented on a 100 % project basis and uses the fixed prices of US $ 4 . 60 /lb for copper, US $ 3 , 300 /oz for gold and US $ 40 /oz for silver, consistent with the consensus forecasts applied in the Vicuña Integrated Technical Report 2026 , dated 16 February 2026 (the “Vicuña PEA”) . Vicuña production included in Group or Copper segment attributable — production information reflects BHP’s 50 % interest . The Vicuña PEA is preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to support classification as Mineral Reserves under ASX or SEC reporting regulations . The PEA does not establish Mineral Reserves or demonstrate economic viability, and there is no certainty that estimates will be realised . Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability . Refer also to the “Forward — looking statements” section on slide 2 and the risk factors in the BHP Annual Report 2026 .


LOGO

Abbreviations and Glossary 74 Copper South Australia site tour | November 2026 AKO Ankata NPI Non — Process Infrastructure BC Block Cave OEM Original Equipment Manufacturer BOS BHP Operating System OD Olympic Dam Copper SA Copper South Australia ODD Olympic Dam Deeps Cu:S Copper to Sulphur ratio PEA Preliminary Economic Assessment CuEq Copper Equivalent PHOX Prominent Hill Expansion CXP Carrapateena Expansion Project RFDS Royal Flying Doctor Service EPCM Engineering Procurement and Construction Management SCM Smelter Campaign Maintenance FPIC Free, Prior and Informed Consent SLC Sub — Level Caving FID Final Investment Decision SLOS Sub — Level Open Stoping FOB Free On Board SMA Southern Mining Area JORC Joint Ore Reserves Committee SRE Smelter and Refinery Expansion MCG Mine and Concentrator Growth TSF Tailings Storage Facility NMA Northern Mining Area UG Underground


LOGO

We are sequencing our major projects Illustrative timeline Maturity CY26 CY27 CY28 CY29 CY30 CY31 CY32 CY33 CY34 CY35+ Phase 1 Growth Projects Prominent Hill Expansion (PHOX) Transforming Prominent Hill from truck haulage to shaft hoisting Smelter Campaign Maintenance 2027 (SCM27) Major 6 — yearly maintenance including tie — in works for SRE    Carrapateena Expansion (CXP) Block caving operation ~450m below existing Sub Level Cave    Smelter and Refinery Expansion (SRE) Expansion to 1,100 ktpa, sized for ongoing Carrapateena concentrate    OD Mine & Concentrator Growth (MCG) Establishes block — cave platform, unlocking scale and resource utilisation at OD    Staging our options to maximise value 75 Copper South Australia site tour | November 2026 Taking a sequenced approach to project delivery with ongoing tollgates to maintain capital discipline Execution Ramp up Studies First production First production First production Potential FID Potential FID First production 
FID First production Potential FID


LOGO

Maturity Estimated capital expenditure (US$ bn 1 ) Estimated capital intensity (US$k/CuEq t) Potential FID (year) Potential first production (year) Potential production profile (ktpa CuEq) 2 Indicative IRR at consensus copper price (nominal,%) 3 Phase 1: Mines & Concentrators Prominent Hill Expansion (PHOX) • Transforms Prominent Hill from truck haulage to shaft hoisting    0.9 (forecast final cost) N/A Commissioning H2 CY26 ~60 / 100 N/A Carrapateena Expansion (CXP) • Block caving operation ~450m below existing Sub Level Cave    1.8 – 2.1 13 – 15 H1 CY28 FY30 ~100 / 140 19 — 22 OD Mine & Concentrator Growth (MCG) • Establishes block — cave platform, unlocking scale and resource utilisation at OD    4.1 – 5.4 22 — 28 CY29 FY34 ~120 / 190 13 — 15 Phase 1: Smelter & Refinery Smelter Expansion 4 • Expansion to 1,100 ktpa, sized for ongoing Carrapateena concentrate    3.2 – 4.1 N/A H2 CY27 FY32 ~360 (Cu Cathode) N/A Copper SA Phase 1 growth program set to deliver 76 Copper South Australia site tour | November 2026 An attractive set of options that unlock more of Olympic Dam’s resource and enable growth through bulk mining 1. All estimated capital expenditures are quoted on a real basis (1 Jul 2026). Capital expenditure excludes commercial commitmen t i nvestments (for example leases and outsourced infrastructure). 2. See ‘Forward — looking production information: assumptions and copper equivalent methodology’ on slide 73. Projects are at differe nt levels of study maturity and remain subject to further study and FID 3. Nominal basis. Calculations based on median July 2026 UBS long term consensus price deck: Cu US$5.00/lb, gold US$3,500/ toz , silver US$46/ toz and uranium US$85/lb. 4. Smelter sizing subject to Final Investment Decision, with remaining concentrate sold to market.


LOGO

Maturity Estimated capital expenditure (US$ bn 1 ) Estimated capital intensity (US$k/CuEq t) Potential FID (year) Potential first production (year) Potential production profile 2 (ktpa Cu / CuEq) Indicative IRR at consensus copper price (nominal,%) Phase 2: Expanding to 650 ktpa Cu and ~1 Mtpa CuEq Mines & Concentrators • Ankata (previously Oak Dam) or Olympic Dam (ODD)    4.5 – 5.8 20 – 26 CY32 CY38 ~190 / 230 CuEq N/A Copper SA Phase 2 growth creates enduring value 77 Copper South Australia site tour | November 2026 Future expansions benefit from installed infrastructure, providing scale at low incremental capital intensities 1. All estimated capital expenditures are quoted on a real basis (1 Jul 2026). Capital expenditure excludes commercial commitmen t i nvestments (for example leases and outsourced infrastructure). 2. See ‘Forward — looking production information: assumptions and copper equivalent methodology’ on slide 73. Projects are at differe nt levels of study maturity and remain to subject further study and FID.


LOGO

Smelter Campaign Maintenance (SCM27) 78 Copper South Australia site tour | November 2026 SCM27 is a critical bridge to two — stage smelting, supporting both operational reliability and long — term growth Project overview • Major lifecycle maintenance program of the OD Smelter • Critical sustaining, maintenance and improvement works that can only be completed outside of BAU outages • Includes tie — ins for SRE: – Tapholes, acid plant and, cooling and services (e.g. water, steam, oxygen) • Planned shorter outage and more capital efficient than prior SCMs Capex (US$bn) FID Execution $0.6bn Oct 2026 H2 CY27 1 2 3 4 5 6 7 8 9 10 11 DB Furnace – Entry, West Wall, Hearth Working Lining, Settler Roof 1 Gas & Dust – ESP Remediation, EJ 4341EX1004, ESP Bypass Blind 2 Feed Prep — #1 Steam Coil Dryer & Modulode Surge Hopper Bin 3 Gas & Dust — WHB Refurbishment, CV1010 Replacement, EJ 4341EX1004, ESP Bypass Blind 4 Electric Slag Furnace Reline 5 Acid Plant Strong Acid — IPAT FAT DT Inspection & Repairs, Tanks AA Replacement & DA Remediation 6 7 8 9 10 11 Utilities — Cooling Tower #2 (inc. Fire Pipe Remediation) Acid Plant Sulphur — TK1053 Remediation, Steam Isolation Upgrades, TK1050 Remediation Anode Furnace — AF#3 Reline, Drivetrain Refurb Acid Plant Dry Gas — Converter Catalyst Changeout/ Structural Repairs & HX1020 Interpass HEX Replacement Oxygen — SRE Tie In Sequence (Location: various)


LOGO

Enabling project: Northern Water Project (NWP) 79 Copper South Australia site tour | November 2026 Project overview • Copper SA currently uses ~60 ML/day with ~35 ML/day sourced from the Great Artesian Basin • The Northern Water Project has three parts: – Marine infrastructure – Desalination plant – ~360 km conveyance pipeline Multi — user facility project led by government with BHP as major offtaker Phase 1 Water Phase 2 Water FID First water 75 — 90 ML/day 105 — 120 ML/day 2027 FY32 Proposed NWP pipeline route


LOGO

Enabling project: Power supply project (PSP) 80 Copper South Australia site tour | November 2026 Existing Partial Upgrade Full Build Transmission capacity (MW) 300 340 780 Critical enabler of the Copper SA growth program, designed to ensure sufficient and reliable power to support production at O lym pic Dam Project overview • We are nearing electricity transmission capacity (300 MW current capacity of the existing 260km 275kV transmission line) • We will need to increase capacity for our growth projects Two options under study : • Option 1 : staged upgrade to support Phase 1 requirements – Upgrade Gridlink capacity by 40 MW to 340 MW – Capex ~ US$0.1 bn 1 – Subsequently upgrade capacity up to 780 MW by installation of double circuit transmission lines • Option 2: full upgrade to support Phase 1 + 2 growth requirements – Immediate one stage upgrade capacity up to 780 MW by construction of double circuit transmission lines – Potential capex ~US$ 1.0 – 1.1 bn 1 : delivery model under consideration including offtake or private capital 1. All estimated capital expenditures are quoted on a real basis (1 Jul 2026).


LOGO

Uranium Expansion ( Hydromet ) 81 Copper South Australia site tour | November 2026 Brownfield expansion replicates Olympic Dam uranium flowsheet at low cost; i ncreases uranium production capacity to ~6 ktpa U 3 O 8 Project overview • Brownfield uranium expansion within broader MCG program • Expands leaching tailings stream enabling ~15% grade uplift – Leverages existing tailings leach and decantation circuits – Adds leach tanks to optimise uranium recovery – Utilises existing precipitation facilities with targeted upgrades Market overview • Demand is growing: – Energy security concerns in US, Japan and Europe support reactor restarts and life extensions. China’s lead in new nuclear pipeline – Technology, data centres and AI power demand driving upside • First modern Western Small Modular Reactors (SMRs) likely to enter commercial operation in the 2030s. Scale — up dependent on financing, supply — chain, and regulatory progress • New mine supply required after 2030


LOGO

Competent Person Statement: Copper Mineral Resources 82 Copper South Australia site tour | November 2026 Copper Mineral Resources Competent Person Statement The information in this slide relates to Copper Mineral Resources as at 1 September 2026. Mineral Resources are inclusive of Ore Reserves and is based on information compiled by Marcelo Cortes as Competent Person (compiler) for all declared Mineral Resources. The information in this presentation that relates to the Copper Mineral Resources reported by the Company in compliance with the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves, 2012’ (‘The JORC Code 2012 Edition’) in the 2026 BHP Annual Report and Operational Review for the Quarter ended 30 September 2026. Reports are available to view on www.bhp.com . M. Cortes is a current Fellow of the Australasian Institute of Mining and Metallurgy ( FAusIMM ) and he is full — time employee of BHP. M. Cortes has sufficient experience that is relevant to the style of mineralisation and type of deposits under consideration and to the activity which he is undertaking to qualify as Competent Person as defined in the 201 2 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code). M. Cortes owns shares in BHP and is entitled to participate in employee share holding plans. M. Cortes consents to the inclusion in the presentation of the matters based on their information in the form and context in which it appears. Mineral Resources as presented are reported in 100 per cent basis. Dry tonnages are reported and all tonnage and quality info rma tion has been rounded, hence small differences may be present in the totals. Total contained copper metal is presented in the table overleaf as kilotonnes (kt) and is presented at 100 per cent basis. No metallurgical recovery has been applied to the calculation of contained coppe r metal. Mineral Resources classification is applied based on mineralisation type, geological understanding and an assessment of reasonable pr osp ects for eventual economic extraction. Copper South Australia Mineral Resources Competent Person Statement The information in this slide relates to Copper South Australia Mineral Resources as at 1 September 2026. Mineral Resources a re inclusive of Ore Reserves and is based on information compiled by Lachlan Macdonald as Competent Person (compiler) for all declared Copper South Australia Mineral Resources. The information in this presentation t hat relates to the Copper South Australia Mineral Resources reported by the Company in compliance with the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves, 2012’ (‘The JOR C Code 2012 Edition’) in the 2026 BHP Annual Report and Operational Review for the Quarter ended 30 September 2026. Reports are available to view on www.bhp.com . L. Macdonald is a current Member of the Australasian Institute of Mining and Metallurgy ( MAusIMM ) and he is full — time employee of BHP. L. Macdonald has sufficient experience that is relevant to the style of mineralisation and type of deposits under consideration and to the activity which he is undertaking to qualify as Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code). L. Macdonald owns shares in BHP and is entitled to participate in employee share holding plans. L. Macdonald consents to the inclusion in the presentation of the matters based on their information in the form and context in which it appears. Mineral Resources as presented are reported in 100 per cent basis. Dry tonnages are reported and all tonnage and quality information has been rounded, hence small differences may be present in the totals. Total contained copper metal is presented in the table below as kilotonnes (kt) and is presented at 100 per cent basis. No metallurgical recovery has been applied to the calculation of contained copper metal. Mineral Resources classification is applied based on mineralisation type, geological understanding and an assessment of reasonable prospects for e ventual economic extraction.


LOGO

Competent Person Statement: Copper Mineral Resources 83 Copper South Australia site tour | November 2026 Deposit Material type Measured Resources Indicated Resources Inferred Resources Total Resources BHP interest % Mt %Cu Mt %Cu Mt %Cu Mt %Cu Contained Metal (Cu kt) Copper operations Escondida Oxide 70 0.55 13 0.53 2.0 0.51 84 0.54 454 57.5 Mixed 40 0.47 36 0.48 
20 0.45 96 0.46 442 Sulphide 4,710 0.56 3,990 0.53 9,060 0.53 17,800 0.55 97,900 Cerro Colorado Oxide 73 0.60 111 0.62 7.6 0.54 192 0.61 1,170 100 Supergene Sulphide 56 0.58 99 0.58 21 0.62 176 0.59 1,040 Transitional Sulphide 92 0.45 118 0.42 20 0.40 230 0.43 989 Hypogene Sulphide 256 0.40 602 0.36 749 0.35 1,610 0.36 5,800 Spence Oxide 4.5 0.54 1.6 0.58 – – 6.1 0.55 34 100 Supergene Sulphide 66 0.54 29 0.46 0.3 0.44 95 0.52 494 Transitional Sulphide 8.6 0.49 0.3 0.41 – – 8.9 0.49 44 Hypogene Sulphide 696 0.45 674 0.43 679 0.41 2,050 0.43 8,820 Copper projects Pampa Escondida Sulphide 294 0.53 1,150 0.55 5,400 0.44 6,840 0.46 31,500 57.5 Pinta Verde Oxide 101 0.59 64 0.52 15 0.54 180 0.56 1,010 57.5 Sulphide – – 23 0.50 37 0.45 60 0.47 282 Chimborazo Sulphide – – 135 0.50 80 0.60 215 0.54 1,160 57.5 Resolution Sulphide – – 724 1.89 1,130 1.28 1,860 1.52 28,300 45 Succoth OC Sulphide – – 61 0.57 57 0.52 120 0.54 648 100 Copper gold operations Carrapateena UG Sulphide 130 0.98 470 0.61 310 0.28 900 0.55 4,950 100 Prominent Hill UG Sulphide 49 1.19 49 0.96 47 0.88 145 1.01 1,460 100 Copper gold projects Ankata (previously Oak Dam) UG Sulphide – – – – 1,340 0.66 1,340 0.66 8,840 100 Fremantle Doctor UG Sulphide – – – – 100 0.51 100 0.51 510 100 Filo del Sol Sulphide – – 1,730 0.46 8,720 0.34 10,500 0.36 50 Copper Oxide – – 467 0.32 431 0.23 898 0.28 Silver Oxide – – 71 0.36 95 0.08 166 0.20 Josemaria Sulphide 648 0.33 961 0.25 683 0.22 2,290 0.26 Vicuña 1 
14,800 0.31 46,600 Copper uranium gold operation Olympic Dam UG Sulphide — block cave 4,000 0.61 4,130 0.57 2,600 0.60 10,730 0.59 63,300 100 UG Sulphide — SLOS 840 1.59 540 1.56 210 1.44 1,590 1.56 24,800 Copper zinc operation Antamina Sulphide Cu only 285 0.75 345 0.85 627 0.84 1,260 0.82 10,300 33.75 Sulphide Cu — Zn 60 0.90 154 1.04 148 1.04 362 1.02 3,690 UG Sulphide Cu only – – – – 361 1.12 361 1.12 4,040 UG Sulphide Cu — Zn – – – – 119 1.12 119 1.12 1,330 Compiled Copper Mineral Resources as at 1 September 2026 (1) Vicuña comprises the Filo del Sol and Josemaría Mineral Resources. BHP reports Mineral Resources at the deposit level; co mbi ned totals are presented for reference only.


LOGO

Competent Person Statement: Copper South Australia Mineral Resources 84 Copper South Australia site tour | November 2026 Deposit Material type Measured Resources Indicated Resources Inferred Resources Total Resources BHP interest % Mt %Cu Mt %Cu Mt %Cu Mt %Cu Contained Metal (Cu kt) Copper gold operations Carrapateena UG Sulphide 130 0.98 470 0.61 310 0.28 900 0.55 4,950 100 Prominent Hill UG Sulphide 49 1.19 49 0.96 47 0.88 145 1.01 1,460 100 Copper gold projects Ankata (previously Oak Dam) UG Sulphide – – – – 1,340 0.66 1,340 0.66 8,840 100 Fremantle Doctor UG Sulphide – – – – 100 0.51 100 0.51 510 100 Copper uranium gold operation Olympic Dam UG Sulphide — block cave 4,000 0.61 4,130 0.57 2,600 0.60 10,730 0.59 63,300 100 UG Sulphide — SLOS 840 1.59 540 1.56 210 1.44 1,590 1.56 24,800 Compiled Copper Mineral Resources as at 1 September 2026


SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

 

      BHP Group Limited
Date: November 23, 2026     By:  

/s/ Stefanie Wilkinson

    Name:   Stefanie Wilkinson
    Title:   Group General Counsel and Group Company Secretary