Entry into a Material Definitive Agreement · Creation of a Direct Financial Obligation or an Obligation under an Off-Balance Sheet Arrangement
Item 1.01 Entry into a Material Definitive Agreement. On June 25, 2026, Applied Optoelectronics, Inc. (the “Company”) entered into a Standard Form of Agreement Between Owner and Design-Builder (AIA Document A141 - 2024), together with the related exhibits package (collectively, the “Design-Build Agreement”), with LCC3 Solution Inc. (the “Design-Builder”).…
Applied Optoelectronics, Inc. (AOI) is a leading developer and manufacturer of advanced optical and Hybrid Fiber-Coax (HFC) networking products that are the building blocks for AI datacenters, CATV and broadband fiber access networks around the world. AOI supplies this critical infrastructure to tier-one customers across cloud computing, CATV broadband, telecom, and FTTH markets. The company has R&D facilities in Atlanta, GA, and engineering and manufacturing facilities at its corporate headquarters in Sugar Land, TX, as well as in Taipei, Taiwan and Ningbo, China. For additional information, visit www.ao-inc.com. # # #
Select an item to read the extracted section. The as-filed document remains the primary evidence.
Item 1.01Item 1.01 - Entry into Material Agreement
Item 1.01 Entry into a Material Definitive Agreement.
On June 25, 2026, Applied Optoelectronics, Inc.
(the “Company”) entered into a Standard Form of Agreement Between Owner and Design-Builder (AIA Document A141 - 2024),
together with the related exhibits package (collectively, the “Design-Build Agreement”), with LCC3 Solution Inc. (the “Design-Builder”).
Pursuant to the Design-Build Agreement, the Design-Builder will provide design-build services for the Company’s OMD 3 (FAB4) cleanroom
construction project located at 11555 North Spectrum Blvd., Houston, Texas 77047 (the “Project”).
The Project consists of the design-build of approximately
195,591 square feet of ISO Class 6-certified cleanroom space, 36,500 square feet of office space, and 73,780 square feet of space designated
for shipping and receiving, quality and reliability testing, and inventory operations. The scope of the Project includes design, engineering,
procurement, construction, testing, commissioning, and related closeout activities.
The total contract amount for the Project is approximately
$94.1 million, inclusive of design, construction, and related professional services, as set forth in the Design-Build Agreement. Payments
under the Design-Build Agreement are generally based on progress, with 10% retainage withheld from each pay application and released upon
final completion, subject to final acceptance and completion of punch list items. Pay applications are submitted monthly, and payments
are due within 15 days after the Company’s receipt of a properly completed pay application.
The Design-Build Agreement provides for liquidated
damages in the event of delays in achieving specified key milestones or substantial completion, subject to contractual adjustments and
conditions, with aggregate liquidated damages capped at $4.9 million.
The Design-Build Agreement also provides that the
Design-Builder may be eligible to earn certain incentives, subject to the terms and conditions set forth therein, including (i) schedule-based
incentives tied to the timely achievement of specified key milestones of up to $6.0 million and (ii) performance-based incentives, including
up to $4.9 million tied to cleanroom validation testing and up to $4.9 million tied to warranty performance.
The Project has a targeted Substantial Completion
date of January 10, 2027.
Item 2.03Item 2.03 - Creation of Direct Financial Obligation
Item 2.03 Creation of a Direct Financial Obligation or an Obligation under
an Off-Balance Sheet Arrangement of a Registrant.
The information contained in Item 1.01 of this
Current Report on Form 8-K with respect to the Lease Agreement is incorporated by reference into Item 2.03.